WESTWOOD ESTATES PHASE I

By A K CONSTRUCTIONS

RG-MH-19831 · RERA P52100004285 · Last updated on MahaRERA portal: 3 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 54 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
31 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

WESTWOOD ESTATES PHASE I is a Others project by A K CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100004285 on 9 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NameWESTWOOD ESTATES PHASE I
  • TypeOthers
  • Location
    • Opposite montvert tropez
    • wakad
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004285
  • ReraGenie IDRG-MH-19831

Builder

  • NameA K CONSTRUCTIONS
  • Entity typePartnership
  • PartnersRAHUL KALATE, SMT ASHA ARUN SANE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2019)
  • Buildings3 building records
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RESIDENTIAL WING ANA140000
RESIDENTIAL WING BNA140000
COMMERCIAL BUILDINGNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 3 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

RESIDENTIAL WING A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RESIDENTIAL WING B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
COMMERCIAL BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes70%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes85%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes85%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed62

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots62
Closed/Covered62
BuildingClosed/CoveredTotal
RESIDENTIAL WING A2121
RESIDENTIAL WING B2929
COMMERCIAL BUILDING1212

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,515 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
SITARAM R KASPATEWakadPune
KRISHNA R KASPATEWakadPune
SAMPAT KASPATEWakadPune
TARABAI D KASPATEWakadPune
VIKAS D KASPATEWakadPune
RAHUL KASPATEWakadPune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI13704.5
Proposed, not sanctioned11,704 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFORT MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMESH TEPAN
EngineerSTRUDCOM CONSULTANTS PVT LTD
PartnerRole in project
A K CONSTRUCTIONS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005203Dec 2019 → Dec 2020

Reason as filed by the promoterFirm has recently received sanction for construction of additional floors in Building ā€˜C’ vide its commencement certificate and sanction plan dated 29th August 2019. The respective copies alongwith self declaration is attached herewith.

EXT52100015078Dec 2019 → Jun 2024

Reason as filed by the promoterThe photo of completed Commercial building is attached below. The for the reason for obtaining completion certificate is that the unsold units of balance floor of Commercial building will be purchased by different vendor / allottees, as these various proposed allottees of unsold units requires internal changes to be made in electrical, plumbing layout and other internal civil changes etc. as per their own requirements. This can be observed from the two different completion certificate obtained for commercial building. The 3rd Floor i.e. office no. 303 and office no. 304 was purchased by single

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Oct 2022

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: FORM 4_PHASE I_compressed_compressed.pdf3 Mar 2025
Other - LegalFile: P52100004285- Extension Order Westwood Estates Phase I.pdf21 Aug 2023
Declaration in FORM BFile: A K Construction Form B.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ph-I.pdf21 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Westwood phase 1 cert 14_30092021_compressed.pdf21 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: A K Construction RERA Form 5.pdf20 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Commercial build Part Completion 303 304.pdf23 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: A K CONSTRUCTION Form 5 Phase I.pdf9 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AK Cons form 5 21-22.pdf8 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: AK Form 5 FY 19-20.pdf4 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_PhaseI_compressed.pdf9 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Commercial bldg_compressed.pdf9 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_compressed.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Phase I.pdf31 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ph-I.pdf22 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_compressed Ph-I.pdf22 Jan 2022
Declaration about Commencement CertificateFile: A k const.pdf14 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: 20210923082952.pdf7 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Westwood phase 1 cert 14_30092021_compressed.pdf7 Oct 2021
Certificates of CA (Form 3)File: Phase I 30-09-21_Signed.pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert 31032020.pdf14 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecht Certificate_30th June'21.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30621.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate Form 2A_Q12122.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Phase I Q1.pdf14 Aug 2021
Certificates of CA (Form 3)File: Phase I Form 3 CA Certificate 300621.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: AK ConstructionEngineer Certificate Phase I.PDF9 Aug 2021
Certificates of CA (Form 3)File: Phase I - Ak ConsT- Westwood (1)_compressed.pdf25 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert phase1 .pdf24 Feb 2020
Certificates of CA (Form 3)File: RERA Certificate- AK Construction- Phase I_compressed (1).pdf21 Jan 2020
Certificates of CA (Form 3)File: CA RERA Certificate Phase I.pdf8 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Phase I Completion Certificate.pdf6 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certi Phase 1.pdf3 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: AK phase 1 cert.pdf26 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert Phase 1.pdf21 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: AK CoN phase 1_compressed (1).pdf20 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 300619.pdf18 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ak phase 1 cert 8.pdf16 Aug 2019
Certificates of CA (Form 3)File: CA FORM 3 WEST WOOD PH 1 .pdf16 Aug 2019
Certificates of CA (Form 3)File: A K CONSTRUCTIONS Phase I 31319.pdf27 May 2019
Certificates of CA (Form 3)File: CA Certificate Phase 31032019.pdf27 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi certi Phase I 311218.pdf17 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi certi Phase I 280319.pdf17 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert phase 1.pdf17 Apr 2019
Certificates of CA (Form 5)File: FORM 5 A K CONSTRUCTION.pdf30 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf11 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf25 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Rera Certificate.pdf24 May 2018
Certificates of CA (Form 3)File: A K CONSTRUCTIONS RERA 24052018 CA Certificate.pdf24 May 2018
Certificates of CA (Form 3)File: FORM 3 NOVEMBER 2017.pdf30 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Oct 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf31 Jul 2017
Layout approvalFile: Layout_westwood estates.pdf29 Jul 2017
Copy of the legal title reportFile: Title_report.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout_westwood estates.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: REVISED ARCHITECT CERTIFICATE.pdf29 Jul 2017
Building plan approvalFile: Commencement Certificate.pdf28 Jul 2017
PAN CardFile: PAN Card.pdf28 Jul 2017
Details of encumbrancesFile: Mortgage Deed.pdf28 Jul 2017
Building Plan Approval (IOD)File: Commencement Certificate.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Final.pdf28 Jul 2017
Proforma of Allotment letterFile: Rera agreement - final.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 54 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WESTWOOD ESTATES PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near wakad13,700+ in Pune

2 kmWESTWOOD ESTATES PHASE ICompleted 138Lapsed / revoked 49Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 267 registered projects within 2 km.

Builder: A K CONSTRUCTIONS

A K CONSTRUCTIONS has 2 registrations on MahaRERA, including WESTWOOD ESTATES PHASE I and WESTWOOD ESTATES PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that WESTWOOD ESTATES PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if WESTWOOD ESTATES PHASE I is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WESTWOOD ESTATES PHASE I?

The registered promoter entity is A K CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WESTWOOD ESTATES PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for WESTWOOD ESTATES PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WESTWOOD ESTATES PHASE I?

The professionals named in the filing: Architect: RAMESH TEPAN; Engineer: STRUDCOM CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WESTWOOD ESTATES PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTWOOD ESTATES PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTWOOD ESTATES PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.