WESTFIELD 3

By GRD INFRAPROJECTS PRIVATE LIMITED

RG-MH-16758 · RERA P52100026904 · Last updated on MahaRERA portal: 27 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 30 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 92%
26 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

WESTFIELD 3 is a Commercial project by GRD INFRAPROJECTS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100026904 on 3 Nov 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 16 of the 42 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameWESTFIELD 3
  • TypeCommercial
  • Location
    • Balewadi road
    • Balewadi
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100026904
  • ReraGenie IDRG-MH-16758

Builder

  • NameGRD INFRAPROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • ChairpersonDEVIDAS RAMDAS ATTARDE
  • Managing DirectorGaurav Devidas Attarde
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2020First promiseJun 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Nov 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed131 files

Current status

38%16 of 42 units booked
79.4%Work done, per cost certificate

Figures as on 27 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Westfield 03NA9504242

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

Westfield 03: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 27 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered24
Open Space72

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025
LandownerVillageDistrict
Gaurav AttardeBanerPune
Sandeep ChaoudhariBanerPune
Abhay kodgireDeglur (M Cl)Nanded
Ganpat WadekarBhosariPune
Abhay Sureshrao KodgireDeglur (M Cl)Nanded
Ganpat Mashnajirao WadekarWadgaon BkPune
Sandip Sudhakar ChaoudhariBanerPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI3449.83
Proposed, not sanctioned3,450 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTara Chambers, Pune Railway Station,Pune-
Estimated costRs 13.39 cr
Cost incurredRs 10.63 cr
Work done79.4%
BuildingWingEstimatedIncurred
Westfield 03NARs 13.39 crRs 10.63 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAuron Designs
ArchitectVASTUSHILP
EngineerJRCC Consultants LLP
EngineerANIL BAWASKAR
EngineerPRANAV MANOJ KHALATE
Chartered AccountantCA Sunil Shejhal
Chartered AccountantV S A P & Company
Chartered AccountantPILLAY AND ASSOCIATES
Chartered AccountantSnehal G Patil
Chartered AccountantPravin Pise & Associates
PartnerRole in project
GRD Infraprojects Private Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016628Jun 2024 → Dec 2024

Reason as filed by the promoterWe have delayed the project commencement due to changes in sales strategy. There are no bookings or agreements accepted. There are no allottees in the project. Hence no consent from the allottees is required.

EXT52100025994Jun 2024 → Mar 2026

Reason as filed by the promoterThe delay in completion of the project is primarily due to slow sales and financial constraints. The overall market conditions have been challenging, resulting in a lower-than-expected sales response. Due to this, the inflow of funds has been significantly impacted, which in turn has slowed down the pace of construction work. As the project is majorly self-funded through customer receipts, the lack of adequate sales has directly affected our ability to maintain consistent progress on-site. Furthermore, the increasing cost of raw materials and labor has added additional financial pressure. Desp

EA29032620432Jun 2024 → Dec 2026

Reason as filed by the promoterThe project is approximately 90% completed. Due to labour shortage and temporary fund constraints, the remaining work has been delayed. Therefore, we request to kindly grant an extension of 8 months to complete the balance construction work. Necessary steps are being taken to ensure timely completion.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Westfield 03.pdf27 Jul 2026
Withdrawal Update Form 2File: Form 2 - Westfield 3.pdf27 Jul 2026
Withdrawal Update Form 3File: F 3 - WESTFIELD - 03-..pdf27 Jul 2026
Withdrawal Update Form 1File: Westfield 03 - Form 1 FY25-26 Q4_page-0001.pdf7 May 2026
Withdrawal Update Form 2File: Westfield 03 - Form 2 FY25-26 Q4_page-0001.pdf7 May 2026
Withdrawal Update Form 3File: Form 3 - Westfield 03.pdf7 May 2026
Withdrawal Update Form 1File: Q3 Form 1 Westfield 03 2026.pdf31 Jan 2026
Withdrawal Update Form 2File: Q3 Form 2 Wsetfield 03 2026.pdf31 Jan 2026
Withdrawal Update Form 3File: Q3 Form 3 Wsetfield 03 2026.pdf31 Jan 2026
Form 1File: 12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf11 Oct 2025
Form 2File: WF FORM 2 OLD.pdf11 Oct 2025
Form 3File: WF 03 OLD.pdf11 Oct 2025
Disclosure of Sold and Booked InventoryFile: WF 3 SOLD UNSOLD.pdf11 Oct 2025
Withdrawal Update Form 1File: 12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf11 Oct 2025
Withdrawal Update Form 1File: WF 03 FORM-1 APR TO JUNE.pdf11 Oct 2025
Withdrawal Update Form 1File: WF 03 Form 1 JULLY - SEPT.pdf11 Oct 2025
Withdrawal Update Form 1File: WF 03 Form 1 JULLY - SEPT.pdf11 Oct 2025
Withdrawal Update Form 2File: WF FORM 2 OLD.pdf11 Oct 2025
Withdrawal Update Form 2File: WF 03 Form 2 APRIL JUNE.pdf11 Oct 2025
Withdrawal Update Form 2File: WF 03 Form 2 JULY-SEP.pdf11 Oct 2025
Withdrawal Update Form 2File: WF 03 Form 2 JULY-SEP.pdf11 Oct 2025
Withdrawal Update Form 3File: WF 03 OLD.pdf11 Oct 2025
Withdrawal Update Form 3File: Form 3 - WF 03 - APRIL- JUNE.pdf11 Oct 2025
Withdrawal Update Form 3File: Form 3 - WF 03 - APRIL- JUNE.pdf11 Oct 2025
Withdrawal Update Form 3File: WF 03 Form 3 JULY-SEP.pdf11 Oct 2025
Declaration in FORM BFile: FORM B.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WF 03 Form 1.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of soldBooked Inventory.pdf25 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A BANK DECLARATION.pdf25 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE.pdf25 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 DISCLOUSRE.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Westfield 03.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 2024-25 WF 03.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 2024-25 WF 03.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: WF 3 FORM 5.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20241225161424.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 WF 03.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Westfield 03- Engg certificate.pdf24 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold WF 03.pdf24 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 2024-25 Q1.pdf30 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Fy 2024-25 Q1.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Promoter Disclosure FY 2024-25 Q1.pdf30 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 2024-25Q1 W-03.pdf30 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 23-24 Q4 W-3.pdf27 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 FY 23-24 Q4 W03.pdf20 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 23-24 Q4 W-03.pdf20 May 2024
Disclosure of sold/ booked inventoryFile: Promoter Disclosure FY23-24 Q4 W-03.pdf20 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architech Certificate Westfield 3 Q3 FY 2023-24.pdf7 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Westfield 3 Form 2 Engineer Certificate Q 3.pdf6 Mar 2024
Disclosure of sold/ booked inventoryFile: Promoters Disclosure unit wise Westfield 03 Q3.pdf6 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3- FY 23-24 Q3 Westfield 3.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual Audit (W 3) FY 2022-23.pdf14 Feb 2024
CERSAI detailsFile: CERSAI_Search_Report_200296098993_For_Asset_Based_Search_07_02_2024_15_07_41_165.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 (Westfield 3).pdf24 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Westfield 03 RERA quarterly update Architect Certificate - Form 1 30-09-2023.pdf9 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate - Form 2 Westfield 03 Dt 30-09-2023.pdf9 Nov 2023
Disclosure of sold/ booked inventoryFile: Westfield 03 Dicloser List Sold and unsold Dt 30-09-2023.pdf9 Nov 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate - Westfield 3.pdf25 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q1 (Westfield- 3).pdf25 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 Q1.pdf2 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Form 2 W3.pdf2 Aug 2023
Disclosure of sold/ booked inventoryFile: Promoter Disclosure Q1 W3.pdf2 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q1 (Westfield- 3).pdf2 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Form 1 Final.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer certificate - Form 2A (FY 2022-23).pdf16 Jun 2023
Other - LegalFile: Allottees Consent - FSI Changes.pdf13 Jun 2023
Building plan approvalFile: Revised Highlited Plan page no-1.pdf7 Jun 2023
Details of encumbrances concerned to FinanceFile: GetUserDocumentFileContent.pdf7 Jun 2023
Details of encumbrances concerned to LegalFile: GetUserDocumentFileContent.pdf7 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Revised Highlited Plan page no-1.pdf7 Jun 2023
Other - LegalFile: Consent Letter Promoter - Enclosed format.pdf7 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q4 (Westfield- 3).pdf22 May 2023
Declaration about Commencement CertificateFile: Promoters Declaration - W 03 Q4.pdf20 May 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate - Westfield 3.pdf20 May 2023
Disclosure of sold/ booked inventoryFile: Promoters Declaration - W 03 Q4.pdf19 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: W03 Form 2A FY 21-22.pdf18 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate - Form 2A (FY 2022-23).pdf18 May 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Gaurav ResidencyS. No.128-67CompletedJul 2014Jul 2014

How this compares with Pune

38%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WESTFIELD 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Balewadi13,700+ in Pune

2 kmWESTFIELD 3Completed 159Lapsed / revoked 61Other 158Dot size: filed unitsN

Filed coordinates, straight-line distance. 378 registered projects within 2 km.

Builder: GRD INFRAPROJECTS PRIVATE LIMITED

GRD INFRAPROJECTS PRIVATE LIMITED has 4 registrations on MahaRERA, including Gaurav Pride and WESTFIELD 3. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if WESTFIELD 3 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WESTFIELD 3?

The registered promoter entity is GRD INFRAPROJECTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WESTFIELD 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for WESTFIELD 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WESTFIELD 3?

The professionals named in the filing: Architect: Auron Designs; Architect: VASTUSHILP; Engineer: JRCC Consultants LLP; Engineer: ANIL BAWASKAR; Engineer: PRANAV MANOJ KHALATE; Chartered Accountant: CA Sunil Shejhal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WESTFIELD 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTFIELD 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTFIELD 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.