Registered Litigation declared Residential / Group Housing project

WESTERN PARK

By WESTERN REAL ESTATE PVT. LTD.

RG-MH-27091 · RERA P51700004620 · Last updated on MahaRERA portal: 15 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 89 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 89 months from the original
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 142 documents Report an error

WESTERN PARK is a Residential / Group Housing project by WESTERN REAL ESTATE PVT. LTD. in Thane, Maharashtra, registered with MahaRERA as P51700004620 on 9 Aug 2017. Possession is promised by 31 Mar 2028. The completion date has moved by 89 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameWESTERN PARK
  • TypeResidential / Group Housing
  • Location
    • Village Ghodbunder
    • Mira Road East
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700004620
  • ReraGenie IDRG-MH-27091

Builder

  • NameWESTERN REAL ESTATE PVT. LTD.
  • Entity typeCompany
  • CINU70100MH1996PTC096028
  • GSTIN27AAACW1532C1ZT
  • DirectorHUZEFA ABBAS BADHRA

Key dates

this monthRegisteredAug 2017First promiseOct 2020Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 30 Oct 2020)
  • Buildings2 building records
  • Documents filed142 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AL- FAROOQUE APARTMENTNA120000
AL- SIDDIQUE APARTMENTNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

AL- FAROOQUE APARTMENT100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
AL- SIDDIQUE APARTMENT100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
AL- FAROOQUE APARTMENT11
AL- SIDDIQUE APARTMENT11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,655 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on1 Oct 2024

Approvals and building plan

Sanctioning authorityMira- Bhayander Mahanagar Corporation
Permissible FSI16956.78
Proposed, not sanctioned15,269 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1-2 AYESHA TOWER PLOT NO 220/8 S V ROAD JOGESHWARI WEST MUMBAI 400102

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH D MHATRE
ArchitectDuberia & Associates
EngineerSANTOSH MAHADEO KADAM
EngineerTrio Consultants
Chartered AccountantVivek Shah & Associates
Chartered AccountantU. G. Devi and Company
PartnerRole in project
WESTERN REAL ESTATE PVT. LTD.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011334Oct 2020 → Mar 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 57.23% allottees for purpose of extension of RERA registration period of the said project.

EXT51700008761Oct 2020 → Oct 2021

Reason as filed by the promoterProject is still under litigation

EXT51700027820Oct 2020 → Mar 2028

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and an ongoing legal case (Case No. 625/14, Thane Court), which has led to further delays. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure the timely completion of the project. Given these circumstances, we kindly request an extension until 31st March 2028 to c

Litigation declared2

CaseCourtStatus
625/14/2014THANEWITHNESS CROSSING IN PROCESS
625/14/2014ThaneOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000198460Adv Nasemm shaikhM/s Real Estate Pvt Ltd.08/12/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed142

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Western Park as on March 2026 (Merged).pdf15 Apr 2026
Form 2File: Form 2 - Western Park as on March 2026.pdf15 Apr 2026
Form 3File: Form 3 - Western Park as on March 2026.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Western Park as on March 2026.pdf15 Apr 2026
Form 1File: Form 1 - Western Park as on Sep 2025.pdf20 Jan 2026
Form 2File: Form 2 - Western Park as on Sep 2025.pdf20 Jan 2026
Form 3File: REVISED FORM 3 AS ON 30 SEP 2025_compressed.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Western Park as on Sep 2025.pdf20 Jan 2026
Form 1File: Western Park Form 1.pdf20 Jan 2026
Form 2File: Form 2 ENGINEER CERTIFICATE as on 31st December 2025.pdf20 Jan 2026
Form 3File: FORM 3 AS ON 31 DECEMBER 2025.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: FORM 29 SOLD UNSOLD INVENTORY AS ON 31 DEC 2025.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: REVISED Form 5 WREP FY 1 April 24 to 31 March 25.pdf26 Dec 2025
Form 1File: Form 1 - Western Park as on June 2025.pdf4 Nov 2025
Form 2File: Form 2 - Western park as on June 2025.pdf4 Nov 2025
Form 3File: Form 3 - Western Park as on June 2025.pdf4 Nov 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Western Park as on June 2025.pdf4 Nov 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Western Park as on March 2025.pdf19 Apr 2025
Certificates of CA (Form 3)File: Form 3 - Western Park as on March 2025.pdf19 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Western Park as on March 2025.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Western Park as on March 2025_compressed.pdf19 Apr 2025
Declaration in FORM BFile: Affidavit Cum Declaration.pdf10 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Form 2 Engineers Certificate.pdf10 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018.pdf10 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019.pdf10 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020.pdf10 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf10 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021 2022.pdf10 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf10 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Western Park as on Dec 2024.pdf23 Jan 2025
Certificates of CA (Form 3)File: Form 3 - Western Park as on Dec 2024.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Western Park as on Dec 2024.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Western Park as on Dec 2024.pdf23 Jan 2025
Certificates of CA (Form 3)File: FORM 3 - Western Park as on Sep 2024.pdf13 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Siddique as on 30 Sep 2024.pdf5 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Farooque as on 30 Sep 2024.pdf5 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Western Park as on Sep 2024.pdf5 Nov 2024
Disclosure of sold/ booked inventoryFile: Circular 29 - Western Park as on Sep 2024.pdf5 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Farooque as on 30 June 2024.pdf17 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Siddique as on 30 June 2024.pdf17 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Farooque as on 30 June 2024.pdf17 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ENGINEER CERTIFICATE as on 30 June 2024.pdf17 Jul 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate as on 30 June 2024.pdf17 Jul 2024
Home Buyer /Allottee Grievance Redressal CellFile: Complaint Redressal Cell PDF.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Western Park for FY 2023-24.pdf29 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Western Park for FY 2023-24.pdf29 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Western Park as on March 2024.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Western Park as on March 2024.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: Circular 29 - Western Park as on March 2024.pdf9 May 2024
Certificates of CA (Form 3)File: Form 3 - Western Park as on March 2024.pdf9 May 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate as on 31 Dec 2023.pdf9 May 2024
Certificates of CA (Form 3)File: Form 3 - Western Park as on March 2024.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Al Siddique as on 31 Dec 2023.pdf13 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Al Farooque as on 31 Dec 2023.pdf13 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM NO 02 as on 31 Dec 2023.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: Circular 29 as on 31 December 2023_compressed.pdf12 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Al Farooque as on 30 sep 2023.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Al Siddique as on 30 sep 2023_Redacted.pdf28 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM NO 02 as on 30 SEP 2023.pdf28 Oct 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Al Farooque as on 30 sep 2023.pdf28 Oct 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Al Siddique as on 30 sep 2023.pdf28 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate as on 30 sep 2023.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 AL FAROOQUE.pdf19 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 AL SIDDIQUE.pdf19 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 as on JUNE 2023.pdf19 Jul 2023
Certificates of CA (Form 3)File: Form 3.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf12 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 as on 2022-23.pdf12 Jul 2023
Certificates of CA (Form 3)File: WREP FORM 3 (FY 2022-2023) CA VIVEK SHAH_compressed.pdf4 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Farrouqe.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Al Siddique.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM NO 02 as on 31 MARCH 2023.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 (1) AS ON 31 ST MARCH 2023_11zon.pdf21 Apr 2023
Certificates of CA (Form 3)File: Form 3 CA CERTIFICATE_11zon.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf4 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf4 Apr 2023

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 89 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WESTERN PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mira Road East7,600+ in Thane

2 kmWESTERN PARKCompleted 37Lapsed / revoked 18Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: WESTERN REAL ESTATE PVT. LTD.

WESTERN REAL ESTATE PVT. LTD. has 1 registration on MahaRERA, including WESTERN PARK. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if WESTERN PARK is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WESTERN PARK?

The registered promoter entity is WESTERN REAL ESTATE PVT. LTD., a company as per the filing. Its CIN U70100MH1996PTC096028 and GSTIN 27AAACW1532C1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WESTERN PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against WESTERN PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for WESTERN PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WESTERN PARK?

The professionals named in the filing: Architect: AVINASH D MHATRE; Architect: Duberia & Associates; Engineer: SANTOSH MAHADEO KADAM; Engineer: Trio Consultants; Chartered Accountant: Vivek Shah & Associates; Chartered Accountant: U. G. Devi and Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WESTERN PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTERN PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTERN PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.