VYOMKESH
RG-MH-10236 · RERA P52100013422 · Last updated on MahaRERA portal: 29 Oct 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 30 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 22 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VYOMKESH is a Residential / Group Housing project by VIJAY ARVIND RAYKAR in Pune, Maharashtra, registered with MahaRERA as P52100013422 on 5 Oct 2017. Possession was promised by 30 Apr 2024 and is now 30 months past that date. The completion date has moved by 22 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameVYOMKESH
- TypeResidential / Group Housing
- Location
- SINHGAD ROAD
- WADGAON BUDRUK
- Wadgaon Bk
- Haveli
- Pune
- 411041
- Pincode411041
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100013422
- ReraGenie IDRG-MH-10236
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Oct 2017
- Promised completion30 Apr 2024
- Revised completionRevised to 30 Apr 2024 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed126 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vyomkesh | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.
Vyomkesh: 50% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed60
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BABAN SHRIPATI YEVALE | Wadgaon Bk | Pune |
| TANAJI MADHAV KOKATE | Wadgaon Bk | Pune |
| SAMBHAJI MADHAV KOKATE | Wadgaon Bk | Pune |
| ANIL MADHAV KOKATE | Wadgaon Bk | Pune |
| KUNAL VASANTRAO KOKATE | Wadgaon Bk | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pankaj Sanghvi |
| Engineer | ARUN GOKHALE |
| Partner | Role in project |
|---|---|
| VIJAY ARVIND RAYKAR | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPLAN SANCTION
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471350 | Vyomkesh Co-operative Housing Society Ltd | M/s Sumeru Developers | 22/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed126
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: VYOMKESH DEC 22_compressed.pdf | 29 Oct 2023 |
| Certificates of CA (Form 3)File: VYOMKESH SEP 23_compressed.pdf | 29 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf | 14 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Sumeru Dev001.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: vyomkesh form3_compressed.pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2 Certificates of CA (Form 5).pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5- 19-20.pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 28 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT VYOMKESH.pdf | 9 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sumeru Developers 12-7-2022001.pdf | 9 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sumeru Developers 01-11-2022001.pdf | 9 Dec 2022 |
| Certificates of CA (Form 3)File: Form-3 Vyomkesh 1001_compressed.pdf | 9 Dec 2022 |
| Certificates of CA (Form 3)File: form 3.pdf | 9 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate_compressed.pdf | 2 Sep 2022 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 2 Sep 2022 |
| Building plan approvalFile: Plan 1_compressed_1_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 2_compressed_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 3_compressed_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 4_compressed_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 4_compressed_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 5_compressed_11zon.pdf | 18 Jun 2022 |
| Building plan approvalFile: Plan 6_compressed.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 1_compressed_1_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 2_compressed_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 3_compressed_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 4_compressed_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 4_compressed_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 5_compressed_11zon.pdf | 18 Jun 2022 |
| Building Plan Approval (IOD)File: Plan 6_compressed.pdf | 18 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Vyomkesh001_compressed.pdf | 18 Jun 2022 |
| Certificates of CA (Form 3)File: FORM 3 VYOMKESH_compressed-compressed.pdf | 18 Jun 2022 |
| Layout approvalFile: Plan 1_compressed_1_11zon.pdf | 8 Mar 2022 |
| Layout approvalFile: Plan 2_compressed_11zon.pdf | 8 Mar 2022 |
| Layout approvalFile: Plan 3_compressed_11zon.pdf | 8 Mar 2022 |
| Layout approvalFile: Plan 4_compressed_11zon.pdf | 8 Mar 2022 |
| Layout approvalFile: Plan 5_compressed_11zon.pdf | 8 Mar 2022 |
| Layout approvalFile: Plan 6_compressed.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 1_compressed_1_11zon.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 2_compressed_11zon.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 3_compressed_11zon.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 4_compressed_11zon.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 5_compressed_11zon.pdf | 8 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 6_compressed.pdf | 8 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf | 18 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT Certi VYOMKESH_compressed.pdf | 6 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certi sumeru dev_compressed.pdf | 6 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: SUMERU DEV sold unsold.pdf | 6 Jan 2022 |
| Certificates of CA (Form 3)File: form3.pdf | 6 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certi sumeru dev_compressed.pdf | 29 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance sumeru dev_compressed.pdf | 29 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: SUMERU DEV sold unsold.pdf | 29 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 7 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Vyomkesh Sold Unsold Inventory.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: VYOMKESH_compressed.pdf | 6 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 22-12-2020_compressed.pdf | 21 Aug 2021 |
| Declaration about Commencement CertificateFile: Declaration About CC ( Vyomkesh )06182021103854.pdf | 16 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 architect 30 JUNE 21.pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 2A 30 JUNE 21.pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2 30 JUNE 21.pdf | 16 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate 2A.pdf | 16 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD-BOOK INVENTORY06222021124210.pdf | 16 Aug 2021 |
| Details of encumbrancesFile: Closer Letter SBI VYOMKESH.pdf | 12 Mar 2021 |
| Details of encumbrancesFile: Release deed SBI (1).pdf | 12 Mar 2021 |
| Certificates of CA (Form 5)File: FORM 5.pdf | 6 Feb 2021 |
| Layout approvalFile: Sanction Layout Plan with Ground Floor.pdf | 2 Jan 2021 |
| Building plan approvalFile: Basement 1 2 Ground Floor Flan.pdf | 2 Jan 2021 |
| Building plan approvalFile: First Floor Plan.pdf | 2 Jan 2021 |
| Building plan approvalFile: 2nd 3rd Floor Plan 3rd Floor to 10th Floor Plan.pdf | 2 Jan 2021 |
| Building plan approvalFile: 4th Floor to 10 Floor Plan 7th Floor Plan.pdf | 2 Jan 2021 |
| Building plan approvalFile: 4th Floor to 10 Floor Plan 7th Floor Plan.pdf | 2 Jan 2021 |
| Building plan approvalFile: Section AA BB Elevation.pdf | 2 Jan 2021 |
| Copy of Layout Approval (in case of layout)File: Sanction Layout Plan with Ground Floor.pdf | 2 Jan 2021 |
| Building Plan Approval (IOD)File: Basement 1 2 Ground Floor Flan.pdf | 2 Jan 2021 |
| Building Plan Approval (IOD)File: First Floor Plan.pdf | 2 Jan 2021 |
| Building Plan Approval (IOD)File: 2nd 3rd Floor Plan 3rd Floor to 10th Floor Plan.pdf | 2 Jan 2021 |
| Building Plan Approval (IOD)File: 4th Floor to 10 Floor Plan 7th Floor Plan.pdf | 2 Jan 2021 |
| Building Plan Approval (IOD)File: 4th Floor to 10 Floor Plan 7th Floor Plan.pdf | 2 Jan 2021 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SUSHRUT RESIDENCY | SURVEY NO 41 HISSA NO 1 NARHE PUNE 411041 | 150 | Completed | Nov 2014 | Oct 2014 |
| GOURANG RESIDENCY | NARHE PUNE | 72 | Completed | Aug 2009 | Jul 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 126 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VYOMKESH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WADGAON BUDRUK13,700+ in Pune
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: VIJAY ARVIND RAYKAR
VIJAY ARVIND RAYKAR has 2 registrations on MahaRERA, including VYOMKESH and SUSHRUT RESIDENCY. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that VYOMKESH shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VYOMKESH is delayed beyond 30 Apr 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VYOMKESH?
The registered promoter entity is VIJAY ARVIND RAYKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VYOMKESH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VYOMKESH?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VYOMKESH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VYOMKESH?
The professionals named in the filing: Architect: Pankaj Sanghvi; Engineer: ARUN GOKHALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VYOMKESH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback