Red flags
- Registration lapsed
- Possession 36 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 34 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VTP SOLITAIRE PHASE 1 AB is a Residential / Group Housing project by WESTERNCITY TOWNSHIPS LLP in Pune, Maharashtra, registered with MahaRERA as P52100000727 on 23 Jul 2017. Possession was promised by 31 Oct 2023 and is now 36 months past that date. The completion date has moved by 34 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NameVTP SOLITAIRE PHASE 1 AB
- TypeResidential / Group Housing
- Location
- Pashan link road
- Pashan
- Haveli
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000727
- ReraGenie IDRG-MH-10195
Builder
- NameWESTERNCITY TOWNSHIPS LLP
- Entity typePartnership
- GSTIN27AAOFV6229Q1Z5
- PartnersASHOK DHANRAJ CHORDIA, ATUL ASHOK CHORDIA, BHUSHAN VILASKUMAR PALRESHA
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on23 Jul 2017
- Promised completion31 Oct 2023
- Revised completionRevised to 31 Oct 2023 (originally 31 Dec 2020)
- Buildings3 building records
- Documents filed101 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 16 | 0 | 0 | 0 | 0 |
| B WING | NA | 16 | 0 | 0 | 0 | 0 |
| MAHADA BUILDING | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 8 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 33 construction stages are filed complete across 3 buildings.
A WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
MAHADA BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed137
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 33 | 27 | 60 |
| B WING | 34 | 22 | 56 |
| MAHADA BUILDING | 10 | 11 | 21 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| YELLOWSTONE PROPCON LLP | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | EARTH SONG SATHOSH MP |
| Architect | A DESIGN STUDIO |
| Architect | MINAL FIRAKE |
| Engineer | GA BHILARE |
| Chartered Accountant | SPAK & Co |
| Partner | Role in project |
|---|---|
| WESTERNCITY TOWNSHIPS LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to delay in environmental clearance, and due to delay in construction .
Reason as filed by the promoterThis is an application for Post Facto extension. Project registration was valid up to 30.12.2022. Occupation Certificates granted by Pune Municipal Corporation on 24.06.2022 and 13.04.2023. Entire project has been completed. Full Occupation Certificates are received and uploaded on project webpage of MahaRera website. Form 4 has also been prepared. To record Form 4, need an extension covering the date of Occupation Certificate.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000177709 | Rukmani Madre | WESTERN CITY TOWNSHIPS LLP | 29/12/2022 |
| CC12603879 | WESTERNCITY TOWNSHIPS LLP | SHEKHAR VITTAL MATE | 23/06/2026 |
| CC12603880 | WESTERNCITY TOWNSHIPS LLP | SHEKHAR VITTAL MATE | 23/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Nov 2024
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: VTP SOLITAIRE-Society Registration Certificate.pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 31122024.pdf | 29 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec-24 Western City.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 VTP SOLItaire Phase 1 30092024.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 PH 1 30062024.pdf | 16 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4- Solitaire Phase 1 AB.pdf | 14 Jan 2025 |
| Certificates of CA (Form 3)File: Form3 VTP Solitaire Ph-1 Sign copy.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLITAIRE PHASE 1 31122024.pdf | 14 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 SOL PHASE 1 15012024_compressed.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 31122023.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 31032024.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 30122022.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 30092022.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 30062022.pdf | 28 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOL PH 1 31032024.pdf | 28 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SOL PH 1 2023-2024_compressed.pdf | 28 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4- Solitaire Phase 1 AB.pdf | 12 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged (3).pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: SOLITAIRE P1 30092024.pdf | 21 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 30092024.pdf | 19 Oct 2024 |
| Certificates of CA (Form 3)File: Form3 VTP Solitaire Ph-1 Sign copy.pdf | 15 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Westerncity Ph 1 Q2 Sign copy.pdf | 15 Oct 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOLITAIRE MHADA SOCIETY REGISTRATION CERTIFICATE.pdf | 19 Aug 2024 |
| Building plan approvalFile: VTP SOLITAIRE PHASE 1 2021.pdf | 27 Jul 2024 |
| Building plan approvalFile: VTP SOLITAIRE PHASE 1 2022.pdf | 27 Jul 2024 |
| Building Plan Approval (IOD)File: VTP SOLITAIRE PHASE 1 2021.pdf | 27 Jul 2024 |
| Building Plan Approval (IOD)File: VTP SOLITAIRE PHASE 1 2022.pdf | 27 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 30062024.pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOLITAIRE PHASE 1 30062024.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3 SOLITAIRE PHASE 1 AB.pdf | 17 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLITAIRE 1AB 30062024.pdf | 8 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-0460-2022.pdf | 2 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SOLITAIRE PHASE 1 31032024.pdf | 16 May 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY SOLITAIRE PHASE 1 31032024.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 31032024.pdf | 27 Apr 2024 |
| Certificates of CA (Form 3)File: FORM 3 SOLITAIRE PHASE 1 31032024.pdf | 27 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY SOLITAIRE PHASE 1 31122023.pdf | 25 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 31122023.pdf | 22 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A SOLITAIRE PHASE 1 31032020.pdf | 9 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A SOLITAIRE PHASE 1 31032022.pdf | 9 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 30062023.pdf | 6 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE PHASE 1 30092023.pdf | 6 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOLITAIRE PHASE 1 30062023.PDF | 3 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOLITAIRE PHASE 1 30092023.PDF | 3 Nov 2023 |
| Certificates of CA (Form 3)File: FORM 3 SOLITAIRE PHASE 1 30062023.pdf | 30 Oct 2023 |
| Certificates of CA (Form 3)File: FORM 3 SOLITAIRE PHASE 1 30092023.pdf | 30 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY SOLITAIRE PHASE 1 30092023.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A SOLITAIRE PHASE 1 31032023.pdf | 16 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLITAIRE PHASE 1 INVENTORY 30062023.pdf | 25 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 SOLITAIRE PHASE 1 22-23.pdf | 12 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SOLITAIRE PHASE 1 31032023.pdf | 26 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: 30092022 - Inventory - Solitaire.pdf | 26 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: 31122022 - Inventory - Solitaire.pdf | 26 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: 31032023 - Inventory - Solitaire.pdf | 26 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3 Solitaire Phase 1 31032023_compressed.pdf | 9 Jun 2023 |
| Certificates of CA (Form 3)File: Phase I 30622_compressed.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Phase I 30922_compressed.pdf | 20 May 2023 |
| Certificates of CA (Form 3)File: Phase I 311222_compressed.pdf | 20 May 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VTP Solitaire - Occupency Certificate -2 (1).pdf | 20 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE 1 A B 30062022.pdf | 1 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE 1 A B 30092022.pdf | 1 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SOLITAIRE 1 A B 31122022.pdf | 1 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate -SOLITAIRE.pdf | 28 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 2018.pdf | 2 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 2022.pdf | 2 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 2018.pdf | 2 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 2021.pdf | 2 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 2022.pdf | 2 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 - 2020.pdf | 2 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 - 2021_.pdf | 2 Feb 2023 |
| Certificates of CA (Form 3)File: form 3 - 2022.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2019.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 2019.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 3 - 2020.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - 2020.pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2022.pdf | 2 Feb 2023 |
| CERSAI detailsFile: Solitaire.pdf | 19 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Solitaire AB_compressed.pdf | 16 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Solitaire AB.pdf | 11 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5_Solitaire_PH I_compressed.pdf | 1 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VTP SOLITAIRE PHASE 1 AB on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pashan13,700+ in Pune
Filed coordinates, straight-line distance. 49 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: WESTERNCITY TOWNSHIPS LLP
WESTERNCITY TOWNSHIPS LLP has 2 registrations on MahaRERA, including VTP SOLITAIRE PHASE 1 AB and VTPSolitaire Building C AND D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that VTP SOLITAIRE PHASE 1 AB shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VTP SOLITAIRE PHASE 1 AB is delayed beyond 31 Oct 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VTP SOLITAIRE PHASE 1 AB?
The registered promoter entity is WESTERNCITY TOWNSHIPS LLP, a partnership as per the filing. Its GSTIN 27AAOFV6229Q1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VTP SOLITAIRE PHASE 1 AB?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VTP SOLITAIRE PHASE 1 AB?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VTP SOLITAIRE PHASE 1 AB?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VTP SOLITAIRE PHASE 1 AB?
The professionals named in the filing: Architect: EARTH SONG SATHOSH MP; Architect: A DESIGN STUDIO; Architect: MINAL FIRAKE; Engineer: GA BHILARE; Chartered Accountant: SPAK & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VTP SOLITAIRE PHASE 1 AB?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback