Home / Browse projects / Pune, Maharashtra / VTP Leonara Building B
VTP Leonara Building B
RG-MH-21120 · RERA P52100011811 · Last updated on MahaRERA portal: 29 Mar 2025
Source: official MahaRERA filing
Red flags
- 21 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VTP Leonara Building B is a Residential / Group Housing project by NNP BUILDCON PVT. LTD in Pune, Maharashtra, registered with MahaRERA as P52100011811 on 31 Aug 2017. The registration is recorded completed; possession was promised by 14 Jun 2025. 21 complaints are on record with the regulator.
At a glance
Project
- NameVTP Leonara Building B
- TypeResidential / Group Housing
- Location
- Mann mhalunge road
- mhalunge
- Mahalunge
- Mulshi
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100011811
- ReraGenie IDRG-MH-21120
Builder
- NameNNP BUILDCON PVT. LTD
- Entity typeCompany
- DirectorsBhushan Vilas Palresha, Nilesh Vilas Palresha
- Other registrations9 more →
- Completed8 of 10
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Aug 2017
- Promised completion14 Jun 2025
- Revised completionNone
- Buildings1 building record
- Documents filed111 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Phase II Soc 6 T11 B Building | NA | 26 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
Phase II Soc 6 T11 B Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities19
As on 29 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Lounge | Yes | 0% |
| Multipurpose Court | Yes | 0% |
| Sky Walk | Yes | 0% |
| Swimming Pool | Yes | 0% |
Parking filed129
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mhalunge Land Developers LLP | Baner | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK A ARCHITECTURE |
| Engineer | JW CONSULTANTS LLP |
| Partner | Role in project |
|---|---|
| NNP BUILDCON PVT. LTD | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 1233/2014/2014 | C J S D Pune | NOT RELATED TO PROJECT LAND STATUS PENDING |
| 100601/2014/2014 | District Court | NOT RELATED TO PROJECT LAND STATUS PENDING |
| CP/1285/2015/2015 | Mumbai High Court | NOT RELATED TO PROJECT LAND STATUS PENDING |
Complaints filed with MahaRERA21
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000000233 | Sudhakar Kapure | River view properties pvt. ltd and Kumar Urban development Ltd | 16/09/2017 |
| CC005000000022249 | Gurminder Singh Chaggar | RIVERVIEW PROPERTIES PVT LTD | 23/11/2018 |
| CC005000000022729 | LeenaSoman | Kul Ecoloch Welfare Association | 04/03/2019 |
| CC005000000043665 | Shantanu Kathale | NNP Buildcon LLP | 19/11/2019 |
| CC005000000043666 | Anil Vijayrao Bind | NNP Buildcon LLP | 19/11/2019 |
| CC005000000043669 | giju skaria | NNP Buildcon LLP | 20/11/2019 |
| CC005000000043670 | Mukund Pande | NNP BUILDCON LLP | 20/11/2019 |
| CC005000000043671 | Abjijit J pawar | NNP Builtcon LLP | 20/11/2019 |
| CC005000000043672 | Shailesh P Shanbhag | NNP BUILDCON LLP | 20/11/2019 |
| CC005000000043673 | Shashank Ramrao Pawar | NNP BUILDCON LLP | 07/12/2019 |
| CC005000000043674 | Rajesh Raghunath Moray | NNP Buildcon LLP | 20/11/2019 |
| CC005000000043675 | Prasanta Adak | NNP BUILDCON LLP | 20/11/2019 |
| CC005000000043676 | Charu Singh | NNP BUILDCON LLP | 20/11/2019 |
| CC005000000043677 | Neelam Singh | NNP BUILDCON LLP | 20/11/2019 |
| CC005000000053970 | Shweta Chaubey | NNP Buildcon LLP | 23/01/2020 |
| CC005000000053971 | Gourhari Jana | NNP Buildcon LLP | 23/01/2020 |
| CC005000000054101 | Supriya Pawashe | NNP Buildcon LLP | 03/03/2020 |
| CC005000000054102 | Pallab Maity | NNP Buildcon LLP | 07/03/2020 |
| CC005000000054121 | Shivam Dhar | NNP Buildcon LLP | 09/03/2020 |
| CC005000000167429 | Ashwin Purushotam | Bhushan VTP | 04/08/2022 |
| CC12400874 | NNP BUILDCON PVT. LTD | POOJA ASHOK MOHITE | 23/11/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Feb 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Feb 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Jul 2024
Documents filed111
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: VTP LEONARA.pdf | 29 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: VTP Leonara B 30062024.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: LEONARA B 30092024.pdf | 14 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 LEONARA B.pdf | 9 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: LEONARA B CL EXP FORM 4 OC.pdf | 7 Aug 2024 |
| Details of encumbrancesFile: ENCUMBRAMCE WRT FINANCE- LEONARA B.pdf | 5 Aug 2024 |
| Building plan approvalFile: LEOANRA B BUILDING compressed.pdf | 27 Jul 2024 |
| Building Plan Approval (IOD)File: LEOANRA B BUILDING compressed.pdf | 27 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 30062024.pdf | 27 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 06072024.pdf | 27 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Leonara Bldg B G Completion.pdf | 24 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B.pdf | 19 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A LEONARA A B C D E F G 31032024.pdf | 16 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 31032024.pdf | 6 May 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY LEONARA B 31032024.pdf | 6 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 31032024.pdf | 27 Apr 2024 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 31032024.pdf | 27 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 31122021.pdf | 21 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY LEONARA B 31122023.pdf | 10 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 31122023.pdf | 9 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 31122023.pdf | 24 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 31122023.pdf | 20 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 30092023.pdf | 1 Jan 2024 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 30092023.pdf | 1 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A LEONARA 31032023.pdf | 30 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 30092023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY LEONARA B 30092023.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 LEONARA B 2022-23.pdf | 29 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: LEONARA B 30092022.pdf | 30 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: LEONARA B 31122022.pdf | 30 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: LEONARA B 30062023.pdf | 30 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: VTP Leonara.pdf | 25 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 30062023.pdf | 25 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Leonara B.pdf | 25 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 30062023_compressed.pdf | 25 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: LEONARA B.pdf | 12 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B_compressed.pdf | 26 May 2023 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 310302023_compressed.pdf | 20 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Leonara B_compressed.pdf | 29 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 LEONARA B 31032023.pdf | 21 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Leonara B_compressed.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: FORM 3 LEONARA B 31122022_compressed.pdf | 15 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 211030 - RERA Certificate - B.pdf | 16 Mar 2023 |
| Certificates of CA (Form 3)File: FORM 3 31032019.pdf | 11 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 LEONARA B 31032020.pdf | 28 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 18-19 LEONARA B.pdf | 28 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 19-20 LEONARA B.pdf | 28 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Leonara B.pdf | 28 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 07122022.pdf | 24 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 13092022.pdf | 24 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 21072022.pdf | 24 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 14022022.pdf | 24 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 30072022.pdf | 24 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 19102022 (5).pdf | 24 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 18072022.pdf | 24 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - LEONARA B.pdf | 28 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VTP LEONARA 1811 FORM 1_compressed.pdf | 29 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 (4).pdf | 17 Oct 2022 |
| CERSAI detailsFile: Leonara AD.pdf | 19 Jul 2022 |
| Other - LegalFile: 1.pdf | 16 Jul 2022 |
| Other - LegalFile: 2.pdf | 16 Jul 2022 |
| Other - LegalFile: 3.pdf | 16 Jul 2022 |
| Other - LegalFile: 1.pdf | 16 Jul 2022 |
| Other - LegalFile: 2.pdf | 16 Jul 2022 |
| Other - LegalFile: 3.pdf | 16 Jul 2022 |
| Other - LegalFile: 1.pdf | 16 Jul 2022 |
| Other - LegalFile: 3.pdf | 16 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Leonara B.pdf | 13 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Leonara B.pdf | 4 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Leonara B.pdf | 28 Apr 2022 |
| CERSAI detailsFile: Leonara B.pdf | 14 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Leonara B.pdf | 13 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Leonara B.pdf | 11 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Leonara B.pdf | 14 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Leonara - B.pdf | 31 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Leonara QA no 3.pdf | 18 Nov 2021 |
| Declaration about Commencement CertificateFile: Leonara B.pdf | 11 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Leonara B.pdf | 20 Oct 2021 |
| Details of encumbrancesFile: Encumbrance Declaration NNP Buildcon.pdf | 30 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Leonara B.pdf | 11 May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 111 filed documents as one ZIP, foldered, with a manifest
Keep VTP Leonara Building B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near mhalunge13,700+ in Pune
Filed coordinates, straight-line distance. 77 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: NNP BUILDCON PVT. LTD
NNP BUILDCON PVT. LTD has 10 registrations on MahaRERA, including VTP Leonara E Buidling and VTP Alpine. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if VTP Leonara Building B is delayed beyond 14 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VTP Leonara Building B?
The registered promoter entity is NNP BUILDCON PVT. LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VTP Leonara Building B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VTP Leonara Building B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VTP Leonara Building B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VTP Leonara Building B?
The professionals named in the filing: Architect: VK A ARCHITECTURE; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VTP Leonara Building B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback