Home / Browse projects / Pune, Maharashtra / VTP Euphoria Phase 2

Registered No litigation declared Residential / Group Housing project

VTP Euphoria Phase 2

By ASHDAN DEVELOPERS PRIVATE LIMITED

RG-MH-62034 · RERA P52100045848 · Last updated on MahaRERA portal: 18 Jun 2026

Source: official MahaRERA filing

Red flags

  • 18 complaints at MahaRERA
  • Rs 250.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
14 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 93%
3 of 360Units unsoldnot recorded sold or booked
18Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

VTP Euphoria Phase 2 is a Residential / Group Housing project by ASHDAN DEVELOPERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100045848 on 15 Jun 2022. Possession is promised by 30 Jun 2027. 357 of the 360 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete. 18 complaints are on record with the regulator.

At a glance

Project

  • NameVTP Euphoria Phase 2
  • TypeResidential / Group Housing
  • Location
    • Awhalwadi road
    • Manjari Kh
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • RERA no.P52100045848
  • ReraGenie IDRG-MH-62034

Builder

  • NameASHDAN DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsMEENA KARNE, Bhushan Vilas Kumar Palresha, Nilesh Vilas Kumar Palresha, Anil Shantilal Kankaria
  • Other registrations15 more →
  • Completed4 of 16
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2022PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jun 2022
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed99 files

Current status

99%357 of 360 units booked
99.2%Work done, per cost certificate

Figures as on 18 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 5NA33301200120
Tower 7NA33301200120
Tower 9NA33301200120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 18 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 93%.

Tower 555%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks44%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.13%
Tower 752%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure93%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises36%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%
Tower 958%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises44%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.14%

Progress on shared amenities15

As on 18 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Open Space15
BuildingOpen SpaceTotal
Tower 555
Tower 755
Tower 955

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,444 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 250.00 crore
CERSAI search filedYes
Declared on7 May 2026
LandownerVillageDistrict
Arhum Erectors Private Limited-Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority, Pune (PMRDA)
Permissible FSI51808.3
Proposed, not sanctioned29,386 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchViman Nagar, Pune
Estimated costRs 152.43 cr
Cost incurredRs 151.14 cr
Work done99.15%
BuildingWingEstimatedIncurred
Tower 9NARs 51.77 crRs 54.36 cr
Tower 5NARs 48.89 crRs 48.45 cr
Tower 7NARs 43.14 crRs 40.18 cr
-NARs 8.63 crRs 8.14 cr

Certifying professionals and partners13

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK Design & Projects PVT. LTD.
ArchitectVK Arch
ArchitectANA CONSORTIUM PVR LTD
EngineerMr Pravin Bhosale
EngineerSTRUDCOM CONSULTANT PRIVATE LIMITED
EngineerGIRISH AWINASHE
EngineerPravin Bhosale
Chartered AccountantS P A K & Co
Chartered AccountantSAC & cO LLP
Chartered AccountantBogati & Company
Chartered AccountantSPAK & CO.
Chartered AccountantSAC AND CO LLP
PartnerRole in project
ASHDAN DEVELOPERS PRIVATE LIMITED-

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC005000000370943Ashdan Developers Pvt. Ltd.SWATI VIJAY PATNE25/05/2024
CC005000000370944Ashdan Developers Pvt. Ltd.UMESH SHIVAJI AMATE25/05/2024
CC005000000370945Ashdan Developers Pvt. Ltd.DANDESWAR BISOYI25/05/2024
CC12500985ASHDAN DEVELOPERS PRIVATE LIMITEDRAMKHILAWAN BANJARE21/03/2025
CC12500981ASHDAN DEVELOPERS PRIVATE LIMITEDABHIJIT ANSHUMAN SALVI21/03/2025
CC12500980ASHDAN DEVELOPERS PRIVATE LIMITEDABHIMANYU A SALVI21/03/2025
CC12600596ASHDAN DEVELOPERS PRIVATE LIMITEDDANDESWAR BISOYI02/02/2026
CC12600597ASHDAN DEVELOPERS PRIVATE LIMITEDRAMKHILAWAN BANJARE02/02/2026
CC12600599ASHDAN DEVELOPERS PRIVATE LIMITEDMR UMESH SHIVAJI AMATE02/02/2026
CC12601126ASHDAN DEVELOPERS PRIVATE LIMITEDShweta Vasant Mahadik02/03/2026
CC12601128ASHDAN DEVELOPERS PRIVATE LIMITEDDINESH CHANDRA GUPTA02/03/2026
CC12601129ASHDAN DEVELOPERS PRIVATE LIMITEDVISHAL TANK02/03/2026
CC12601130ASHDAN DEVELOPERS PRIVATE LIMITEDWILLIAM MATHURAI02/03/2026
CC12601131ASHDAN DEVELOPERS PRIVATE LIMITEDPRIYANK SATARKAR02/03/2026
CC12601132ASHDAN DEVELOPERS PRIVATE LIMITEDRITESH PRAKASH02/03/2026
CC12602654Christina RayASHDAN DEVELOPERS PRIVATE LIMITED07/05/2026
CC12602508ASHDAN DEVELOPERS PRIVATE LIMITEDPrashant Kumar29/04/2026
CC12603362ASHDAN DEVELOPERS PRIVATE LIMITEDPAWANDEEP SINGH CHHABDA02/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form-2A -Euphoria - Phase-2.pdf18 Jun 2026
Withdrawal Update Form 1File: FORM 1 Euph Ph2 07042026.pdf20 Apr 2026
Withdrawal Update Form 2File: Form-2 - Euphoria - Phase 2..pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3 EUPH PH 2 30032026 F_11zon.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM 1 Euphoria Phase 2 08012026.pdf17 Jan 2026
Withdrawal Update Form 2File: FORM 2 EUPHORIA PHASE 2 20122025.pdf17 Jan 2026
Withdrawal Update Form 3File: FORM 3 Euphoria Phase 2 31122025.pdf17 Jan 2026
Withdrawal Update Form 1File: FORM 1 EUPHORIA PHASE 2 30092025.pdf20 Oct 2025
Withdrawal Update Form 2File: FORM 2 EUPHORIA PHASE 2 30092025.pdf20 Oct 2025
Withdrawal Update Form 3File: FORM 3 EUPHORIA PHASE 2 24062024_compressed (1).pdf20 Oct 2025
Form 5 (FY 2024-2025)File: vtp Euphoria phase 2_compressed.pdf24 Sep 2025
Form 1File: FORM 1 EUPHORIA PHASE 2 31032025.pdf25 Jun 2025
Form 2File: Form 2 Euphoria Ph 2.pdf25 Jun 2025
Form 3File: Form 3 Euphoria Ph 2.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: EUPHORIA PHASE2 31032025.pdf25 Jun 2025
Form 2A (FY 2024-2025)File: FORM 2A EUPHORIA PHASE 2.pdf23 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Euphoria Ph 2.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Euphoria Ph 2.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 31032025.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: EUPHORIA PH 2 31122024.pdf20 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: FORM 3 Euphoria Ph2 22102024.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 31122024.pdf10 Jan 2025
Details of encumbrancesFile: Euphoria phase 2.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Euphoria Phase 2.pdf3 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Euphoria Phase 2.pdf22 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 30092024.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 30092024.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: EUPHORIA PH2 30092024.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- EUPHORIA PHASE 2 09102024.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 260624 Euphoria P 2.pdf6 Jul 2024
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 30062024.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-VTP EUPHORIA PHASE 2 24062024.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A EUPHORIA PHASE 2 31032024.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY EUPHORIA PHASE 2 31032024.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 31032024.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 31032024.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 26032024.pdf4 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 23122022.pdf28 Mar 2024
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 31122023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 31122023.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 31122023.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 24112023.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 31122023.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 23112023.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Euphoria PH 2 23112023.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 06112023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 06112023.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 06112023-NEW.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 30092023.pdf6 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 30092023.pdf6 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY EUPHORIA PHASE 2 30092023.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 EUPHORIA PHASE 2 2022-23.pdf28 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 14092023.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 26092023.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 14092023.pdf7 Oct 2023
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 30092022.pdf7 Sep 2023
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 31122022.pdf7 Sep 2023
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 31032023.pdf7 Sep 2023
Disclosure of sold/ booked inventoryFile: EUPHORIA PHASE 2 30062023.pdf7 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPHORIA PHASE 2 24082023.pdf5 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 25082023.pdf5 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPHORIA PHASE 2 28082023.pdf5 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPHORIA PHASE 2 25082023.pdf29 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A EUPHORIA PHASE 2 31032023.pdf29 Aug 2023
Details of encumbrancesFile: FE Euphoria 2 010823.pdf2 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPH PHASE 2 30062023_compressed.pdf24 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Euphoria PH 2 - 30062023.pdf24 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Euphoria PH 2 - 30062023_compressed.pdf24 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form 3 - Euphoria Phase 2 - March 2023-1-6.pdf12 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form 3 - Euphoria Phase 2 - March 2023-7-12.pdf12 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Euphoria Phase 2 - 31-03-2023.pdf4 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EUPH PH 2 31032023.pdf29 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPH 2 30092022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPH 2 30092022_compressed.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EUPH 2 23122022.pdf29 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EUPH 2 30112022.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230323 - RERA Certificate -Euphoria - Ph 2.pdf28 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Euphoria 2.pdf28 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 TOWER 5 7 9.pdf29 Oct 2022

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VTP Euphoria Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Manjari Kh13,700+ in Pune

Builder: ASHDAN DEVELOPERS PRIVATE LIMITED

Ashdan Developers Private Limited has 16 registrations on MahaRERA, including Vtp Cygnus- Nation R1-Tower 9 and VTP Beaumonde-Nation R2 T1. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 9 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VTP Euphoria Phase 2 is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VTP Euphoria Phase 2?

The registered promoter entity is ASHDAN DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VTP Euphoria Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VTP Euphoria Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VTP Euphoria Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VTP Euphoria Phase 2?

The professionals named in the filing: Architect: VK Design & Projects PVT. LTD.; Architect: VK Arch; Architect: ANA CONSORTIUM PVR LTD; Engineer: Mr Pravin Bhosale; Engineer: STRUDCOM CONSULTANT PRIVATE LIMITED; Engineer: GIRISH AWINASHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VTP Euphoria Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VTP Euphoria Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VTP Euphoria Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.