Home / Browse projects / Pune, Maharashtra / VTP Cygnus BuildingT12 and Commercial

Completed No litigation declared Others project

VTP Cygnus BuildingT12 and Commercial

By ARHUM ERECTORS PRIVATE LIMITED

RG-MH-15334 · RERA P52100023473 · Last updated on MahaRERA portal: 16 Sep 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Rs 489.00 crore secured on the land, in favour of KOTAK REALTY FUND

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
14 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 99%
2Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

VTP Cygnus BuildingT12 and Commercial is a Others project by ARHUM ERECTORS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100023473 on 16 Dec 2019. The registration is recorded completed; possession was promised by 30 Jun 2025. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVTP Cygnus BuildingT12 and Commercial
  • TypeOthers
  • Location
    • Manjari Road
    • Manjari
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100023473
  • ReraGenie IDRG-MH-15334

Builder

  • NameARHUM ERECTORS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400PN2021PTC201688
  • GSTIN27AAVCA3261F1ZI
  • DirectorsNilesh Vilaskumar Palresha, Bhushan Palresha Vilaskumar Palresha, Anil Shantilal Kankariya, Meena Manohar Karne
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredDec 2019PromisedJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Dec 2019
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
T12NA290000
CommercialNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 99%.

T1291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Commercial78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises17%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 16 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes0%
Street LightingYes30%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered26
Open Space24
BuildingClosed/CoveredOpen SpaceTotal
T1211213
Commercial251237

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,666 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofKOTAK REALTY FUND
Secured amountRs 489.00 crore
Declared on3 Oct 2024
LandownerVillageDistrict
Ashdan Developers Pvt LTDBanerPune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY PUNE
Permissible FSI16220.84
Proposed, not sanctioned1,168 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectvk arch
EngineerRAVI VIVEKANANDAN
EngineerShahanawaz shaikh
Chartered AccountantKailash Agarwal & Asso for Form Five
Chartered AccountantSPAK & Co
Chartered AccountantPriyanka Chordiya & Associates
PartnerRole in project
ARHUM ERECTORS PRIVATE LIMITED-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12502263DEEPAK KUMAR RAIARHUM ERECTORS PRIVATE LIMITED05/07/2025
CC12503653ARHUM ERECTORS PRIVATE LIMITEDAnkita Ashok Rawalkar alias Ankita Nikitkumar Malke14/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 May 2025

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: T-12.pdf16 Sep 2025
Other - TechnicalFile: OC VERIFICATION MAIL T12 AND COMMERCIAL.pdf4 Jul 2025
Other - TechnicalFile: Form 4 T12 Commercial.pdf25 Jun 2025
Other - TechnicalFile: Form 4 T12 Commercial.pdf25 Jun 2025
Other - TechnicalFile: Form 4 T12 Commercial.pdf25 Jun 2025
Other - TechnicalFile: Form 4 T12 Commercial.pdf25 Jun 2025
Form 1File: Form 1 Beaumonde T 2.pdf22 May 2025
Form 2File: Form 2 Cygnus T 12 31032025.pdf22 May 2025
Form 3File: cygnus T12 and commer.pdf22 May 2025
Disclosure of Sold and Booked InventoryFile: CYGNUS T12 COMM 31032025.pdf22 May 2025
Building plan approvalFile: revised plan t12.pdf3 May 2025
Building Plan Approval / NA Order for plotted developmentFile: revised plan t12.pdf3 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate T12- commercial.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Cygnus T 12.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: cygnus T12 and commer.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Cygnus T 12 31032025.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: CYGNUS T12 COMM 31032025.pdf8 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-T12 31122024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: CYGNUS T12 31122024.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CYGNUS T12 31122024.pdf10 Jan 2025
Details of encumbrancesFile: T12.pdf20 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CYGNUS T12 16072024.pdf5 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate-T10 AND T12.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T12 17102024.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CYGNUS T12 30092024.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BEAUMONDE T12 30092024.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: CYGNUS T12 30092024.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T-12 080724.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 2 CYGNUS T-12 080724.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: CYGNUS 12 30062024.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 VTP Cygnus T12 300624.pdf16 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A CYGNUS T12 31032024.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY CYGNUS T12 31032024.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T12 31032024.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CYGNUS T12 31032024.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CYGNUS T12 31032024.pdf4 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T12 30062022.pdf21 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CYGNUS T12 30062022.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: INVENTORY CYGNUS T12 31122023.pdf16 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T12 31122023.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CYGNUS T12 31122023.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 T12 31122023.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 CYGNUS T12 30092023.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 CYGNUS T12 30092023.pdf25 Oct 2023
Disclosure of sold/ booked inventoryFile: INVENTORY CYGNUS T12 30092023.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CYGNUS T12 30092023.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CYGNUS T12 2022-23.pdf29 Sep 2023
Disclosure of sold/ booked inventoryFile: CYGNUS T12 30092022.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: CYGNUS T12 31122022.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: CYGNUS T12 31032023.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: CYGNUS T12 30062023.pdf6 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 T12 30062023.pdf4 Aug 2023
Details of encumbrancesFile: FE T12 010823.pdf1 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 T12 30062023.pdf1 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 T12 30062023.pdf31 Jul 2023
Details of encumbrancesFile: T12 FE.pdf28 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 T12 31032023.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A T12 31032022.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A T12 31032023.pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 T12 31032023.pdf5 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 T12 31032023.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 T12 31122021_compressed.pdf28 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 211019 - RERA Certificate - T12 19102021_compressed.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - TOWER 12 CYGNUS 30092022.pdf9 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - T12 - 2122.pdf1 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - T12.pdf28 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Cygnus T12.pdf28 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tower 12_compressed.pdf28 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 TOWER 12 CYGNUS.pdf29 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VTP CYGNUS T12 COMMERCIAL FORM 3.pdf29 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tower 12.pdf25 Jul 2022
Disclosure of sold/ booked inventoryFile: Tower 12_compressed.pdf4 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: T12.pdf23 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: T12.pdf11 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: T12.pdf11 Apr 2022
CERSAI detailsFile: T12.pdf9 Apr 2022
Disclosure of sold/ booked inventoryFile: Tower 12.pdf9 Apr 2022
Disclosure of sold/ booked inventoryFile: T12.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: T12 2021.pdf31 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: t-12-april 19 to march 20.pdf20 Nov 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VTP Cygnus BuildingT12 and Commercial on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Manjari13,700+ in Pune

2 kmVTP Cygnus BuildingT12 aCompleted 115Lapsed / revoked 117Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: ARHUM ERECTORS PRIVATE LIMITED

ARHUM ERECTORS PRIVATE LIMITED has 6 registrations on MahaRERA, including VTP Beaumonde Nation R2 Tower6 and VTP Beaumonde Building T3. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VTP Cygnus BuildingT12 and Commercial is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VTP Cygnus BuildingT12 and Commercial?

The registered promoter entity is ARHUM ERECTORS PRIVATE LIMITED, a company as per the filing. Its CIN U45400PN2021PTC201688 and GSTIN 27AAVCA3261F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VTP Cygnus BuildingT12 and Commercial?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VTP Cygnus BuildingT12 and Commercial?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VTP Cygnus BuildingT12 and Commercial?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VTP Cygnus BuildingT12 and Commercial?

The professionals named in the filing: Architect: vk arch; Engineer: RAVI VIVEKANANDAN; Engineer: Shahanawaz shaikh; Chartered Accountant: Kailash Agarwal & Asso for Form Five; Chartered Accountant: SPAK & Co; Chartered Accountant: Priyanka Chordiya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VTP Cygnus BuildingT12 and Commercial?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VTP Cygnus BuildingT12 and Commercial. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VTP Cygnus BuildingT12 and Commercial to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.