Home / Browse projects / Pune, Maharashtra / VTP BELLISSIMO PHASE 3

Registered No litigation declared Residential / Group Housing project

VTP BELLISSIMO PHASE 3

By MAGNITE DEVELOPERS PRIVATE LIMITED

RG-MH-44315 · RERA P52100048331 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 1,200.00 crore secured on the land, in favour of CREDIT OPPORTINITIES III GIFT CITY FUND

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 4 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 67%
65 of 208Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

VTP BELLISSIMO PHASE 3 is a Residential / Group Housing project by MAGNITE DEVELOPERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100048331 on 26 Dec 2022. Possession is promised by 31 Jul 2027. The completion date has moved by 4 months from the original filing. 143 of the 208 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVTP BELLISSIMO PHASE 3
  • TypeResidential / Group Housing
  • Location
    • HINJEWADI MANN ROAD
    • HINJEWADI
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048331
  • ReraGenie IDRG-MH-44315

Builder

  • NameMAGNITE DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309PN2022PTC207434
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsBHUSHAN VILAS PALRESHA, NILESH VILAS PALRESHA
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2022First promiseMar 2027Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Mar 2027)
  • Buildings1 building record
  • Documents filed112 files

Current status

69%143 of 208 units booked
54.4%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 9NA30262080208

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 67%.

TOWER 9: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
Sanitary Fittings within the flats / premises7%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes10%
Street LightingYes10%
Community BuildingsYes10%
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes55%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes35%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered15
Open Space10

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,298 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofCREDIT OPPORTINITIES III GIFT CITY FUND
Secured amountRs 1,200.00 crore
CERSAI search filedYes
Declared on11 Jul 2025
LandownerVillageDistrict
Ashdan Township Ventures Private Limited-Pune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY
Permissible FSI20177.22
Proposed, not sanctioned17,177 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANORI PUNE
Estimated costRs 55.07 cr
Cost incurredRs 29.94 cr
Work done54.37%
BuildingWingEstimatedIncurred
TOWER 9NARs 53.97 crRs 29.94 cr
-NARs 1.10 cr-

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK ARCH
ArchitectANA CONSORTIUM PVT LTD
ArchitectVK:a
EngineerSTRUDCOM CONSULTANTS PRIVATE LIMITED
EngineerAJAY RELEKAR
EngineerSIDDIQUE MODAK
EngineerPravin Patil
Chartered AccountantSAC AND CO LLP
Chartered AccountantSAC & CO LLP
Chartered AccountantPriyanka Chordiya & Associates
PartnerRole in project
MAGNITE DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100048331/WarMar 2027 → Jul 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12605663MAGNITE DEVELOPERS PRIVATE LIMITEDMRS TEJASWINEE UTPAT (Allottee)01/09/2026
CC12605665MAGNITE DEVELOPERS PRIVATE LIMITEDMRS TEJASWINEE UTPAT (Allottee)01/09/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2027

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: RERA FORM-1 BELLISSIMO PHASE 3.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2- bellissimo Phase-3.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 VTP Bellissimo Ph 3 june26 compressed.pdf18 Jul 2026
Form 2A (FY 2025-2026)File: Bellissimo Phase 3 Form 2A.pdf18 Jun 2026
Withdrawal Update Form 1File: FORM-1 BELLISSIMO PHASE 3.pdf15 Apr 2026
Withdrawal Update Form 2File: BELLISSIMO PHASE 3 -FORM 2.pdf15 Apr 2026
Withdrawal Update Form 3File: FORM 3 BELLISSIMO PHASE 3.pdf15 Apr 2026
Withdrawal Update Form 1File: FORM-1 BELLISSIMO PHASE 3.pdf16 Jan 2026
Withdrawal Update Form 2File: FORM 2 BELLISSIMO PHASE 3.pdf16 Jan 2026
Withdrawal Update Form 3File: FORM 3 Bellissimo ph 3 23122025 sign_11zon.pdf16 Jan 2026
Withdrawal Update Form 1File: FORM-1 BELLISSIMO PHASE 3.pdf16 Oct 2025
Withdrawal Update Form 2File: FORM 2 Bellissimo phase 3 30092026.pdf16 Oct 2025
Withdrawal Update Form 3File: FORM 3 BELLISSIMO PHASE 3_compressed.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5- BELLISSIMO PHASE 3.pdf11 Sep 2025
Form 2A (FY 2024-2025)File: FORM 2A BELLISSIMO PHASE 3.pdf1 Jul 2025
Form 1File: FORM 1 BELLISSIMO PHASE 3 31032025.pdf22 May 2025
Form 2File: Form 2 Bellissimo Phase 3.pdf22 May 2025
Form 3File: Form 3 VTP bellisimo Ph 3 31032025.pdf22 May 2025
Disclosure of Sold and Booked InventoryFile: BELLISSIMO PH3 31032025.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Bellissimo Phase 3.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 VTP bellisimo Ph 3 31032025.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 31032025.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: BELLISSIMO PH3 31032025.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 31122024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 31122024.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 31122024.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 31122024.pdf10 Jan 2025
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 31122024.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 31122024.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 31122024.pdf8 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 30092024.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 30092024.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 30092024.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 30092024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 30092024.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 30092024.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PH 3 30092024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PH 3 30092024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PH 3 30092024.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: BELLISSIMO PH3 30092024.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: BELLISSIMO PH3 30092024.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: BELLISSIMO PH3 30092024.pdf14 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: from 5 VTP BELLISSIMO PHASE 3 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: from 5 VTP BELLISSIMO PHASE 3 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: from 5 VTP BELLISSIMO PHASE 3 31-03-2024_compressed.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 VTP BELLISSIMO PHASE 3.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PH 3 070624.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO P 3 300624.pdf18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PH 3 30062024.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: VTP Bellissimo P 3 30062024.pdf6 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A BELLISSIMO PHASE 3 31032024.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY BELLISSIMO PHASE 3 31032024.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 31032024.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 31032024.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 31032024.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 07102023.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 31122023.pdf5 Feb 2024
Disclosure of sold/ booked inventoryFile: INVENTORY BELLISSIMO PHASE 3 31122023.pdf5 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 BELLISSIMO PHASE 3 2022-23.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO 3 31122023.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 31122023.pdf22 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A BELLISSIMO PHASE 3 31032023.pdf2 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PHASE 3 30092023.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 BELLISSIMO PHASE 3 30092023.pdf28 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 30092023.pdf28 Oct 2023
Disclosure of sold/ booked inventoryFile: INVENTORY BELLISSIMO PHASE 3 30092023.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - BELL PH 3 31032023.pdf7 Oct 2023
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 INVENTORY 31122022.pdf25 Sep 2023
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 INVENTORY 31032023.pdf25 Sep 2023
Disclosure of sold/ booked inventoryFile: BELLISSIMO PHASE 3 INVENTORY 30062023.pdf25 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph-3.pdf19 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PHASE 3 30062023.pdf13 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 BELLISSIMO PH 3 30062023.pdf9 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Form 2A-Phase III.pdf19 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 BELLISSIMO PH 3 31032023.pdf15 May 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
No experienceHinjewadiCompletedDec 2022Dec 2022

How this compares with Pune

69%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VTP BELLISSIMO PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HINJEWADI13,700+ in Pune

2 kmVTP BELLISSIMO PHASE 3Completed 37Lapsed / revoked 15Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: MAGNITE DEVELOPERS PRIVATE LIMITED

MAGNITE DEVELOPERS PRIVATE LIMITED has 3 registrations on MahaRERA, including VTP BELLISSIMO PHASE 1 and VTP BELLISSIMO PHASE 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VTP BELLISSIMO PHASE 3 is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VTP BELLISSIMO PHASE 3?

The registered promoter entity is MAGNITE DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45309PN2022PTC207434 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VTP BELLISSIMO PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VTP BELLISSIMO PHASE 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VTP BELLISSIMO PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VTP BELLISSIMO PHASE 3?

The professionals named in the filing: Architect: VK ARCH; Architect: ANA CONSORTIUM PVT LTD; Architect: VK:a; Engineer: STRUDCOM CONSULTANTS PRIVATE LIMITED; Engineer: AJAY RELEKAR; Engineer: SIDDIQUE MODAK. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VTP BELLISSIMO PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VTP BELLISSIMO PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VTP BELLISSIMO PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.