VTP Beaumonde Nation R2 Tower6
By ARHUM ERECTORS PRIVATE LIMITED
RG-MH-21082 · RERA P52100007942 · Last updated on MahaRERA portal: 4 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 14 months past the filed date
- Litigation declared, 5 cases
- 35 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
- Rs 882.50 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD
Clear
- Separate project account declared
- Allotment letter follows the model form
7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VTP Beaumonde Nation R2 Tower6 is a Residential / Group Housing project by ARHUM ERECTORS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100007942 on 18 Aug 2017. Possession was promised by 15 Aug 2025 and is now 14 months past that date. The completion date has moved by 12 months from the original filing. 209 of the 212 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 35 complaints are on record with the regulator.
At a glance
Project
- NameVTP Beaumonde Nation R2 Tower6
- TypeResidential / Group Housing
- Location
- Gat No 124
- Manjri
- MANJARI KH
- Haveli
- Pune
- 412307
- Pincode412307
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100007942
- ReraGenie IDRG-MH-21082
Builder
- NameARHUM ERECTORS PRIVATE LIMITED
- Entity typeCompany
- DirectorsNILESH VILASKUMAR PALRESHA, BHUSHAN VILASKUMAR PALRESHA, Anil Shantilal Kankariya, Meena Manohar Karne
- Other registrations5 more →
- Completed4 of 6
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion15 Aug 2025
- Revised completionRevised to 15 Aug 2025 (originally 16 Aug 2024)
- Buildings1 building record
- Documents filed127 files
Current status
Figures as on 4 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kul Nation R2 - Tower 6 | NA | 29 | 27 | 212 | 0 | 212 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Kul Nation R2 - Tower 6: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 40% |
| Storm Water Drains | Yes | 40% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 70% |
| Solid Waste Management And Disposal | Yes | 70% |
| Water conservation /Rain water harvesting | Yes | 60% |
| Energy managemcnt | Yes | 95% |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed123
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Arhum Erectors LLP | VIMANNAGAR | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Kul Nation R2 - Tower 6 | NA | Rs 64.87 cr | Rs 61.85 cr |
| - | NA | Rs 18.05 cr | Rs 18.05 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK:a |
| Architect | VK A ARCHITECTURE |
| Engineer | SANTOSH MOHITE |
| Engineer | J W Consultants LLP Formerly Y S Sane Associates |
| Engineer | STRUDCOM CONSULTANTS PRIVATE LIMITED |
| Engineer | VTP Realty |
| Engineer | PRADYUNMA SURYAWANSHI |
| Chartered Accountant | SPAK & CO. |
| Chartered Accountant | BOGATI & CO. |
| Partner | Role in project |
|---|---|
| ARHUM ERECTORS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Litigation declared5
| Case | Court | Status |
|---|---|---|
| 1170/2014/2014 | CJSD | LITIGATION ON OTHER SECTOR OF TOWNSHIP LAND NOT RELATED TO VTP BEAUMONDE TOWER SIX |
| 264/2015/2015 | CJSD | LITIGATION ON OTHER SECTOR OF TOWNSHIP LAND NOT RELATED TO VTP BEAUMONDE TOWER SIX |
| 494/2008/2008 | CJSD | LITIGATION ON OTHER SECTOR OF TOWNSHIP LAND NOT RELATED TO VTP BEAUMONDE TOWER SIX |
| 401943/2015/2015 | CJM PUNE | LITIGATION ON OTHER SECTOR OF TOWNSHIP LAND NOT RELATED TO VTP BEAUMONDE TOWER SIX |
| 479/2008/2008 | HIGH COURT MUMBAI | LITIGATION ON OTHER SECTOR OF TOWNSHIP LAND NOT RELATED TO VTP BEAUMONDE TOWER SIX |
Complaints filed with MahaRERA35
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022115 | Bhagwat B Mane | Ashdan Developers Private Limited | 06/10/2018 |
| CC12500711 | Abhishek Sahu | ARHUM ERECTORS PRIVATE LIMITED | 28/02/2025 |
| CC12504202 | Pratyush Pranjal | ARHUM ERECTORS PRIVATE LIMITED | 28/11/2025 |
| CC12602454 | SHIVKUMAR SINGH PUNDIR | ARHUM ERECTORS PRIVATE LIMITED | 27/04/2026 |
| CC12602888 | Poonam Nimje | ARHUM ERECTORS PRIVATE LIMITED | 16/05/2026 |
| CC12602783 | Kushal Bipin Tanna | ARHUM ERECTORS PRIVATE LIMITED | 13/05/2026 |
| CC12602784 | Hetal Rajendrasinh Parmar | ARHUM ERECTORS PRIVATE LIMITED | 13/05/2026 |
| CC12602809 | Kiran Udaykumar Shah | ARHUM ERECTORS PRIVATE LIMITED | 14/05/2026 |
| CC12602831 | Vishruti Suresh Yadav | ARHUM ERECTORS PRIVATE LIMITED | 14/05/2026 |
| CC12602958 | Pratik Prabhakar Kasare | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602934 | Ashvini Ashok Tandale | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602954 | Ajay Bhaskar Pawar | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602955 | Ajay Bhaskar Pawar | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602963 | Roshni Vijay Ganjepatil | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602964 | Vivekkumar Brijkishor Singh | ARHUM ERECTORS PRIVATE LIMITED | 19/05/2026 |
| CC12602974 | Dhaval Mansukhrai Thakkar | ARHUM ERECTORS PRIVATE LIMITED | 20/05/2026 |
| CC12602973 | Amarkumar Upendra Singh | ARHUM ERECTORS PRIVATE LIMITED | 20/05/2026 |
| CC12603007 | Jitendra Ramakant Meena | ARHUM ERECTORS PRIVATE LIMITED | 21/05/2026 |
| CC12603020 | Rajeev Rajendra Sehgal | ARHUM ERECTORS PRIVATE LIMITED | 21/05/2026 |
| CC12603130 | Vikesh Kumar Jhariya | ARHUM ERECTORS PRIVATE LIMITED | 26/05/2026 |
| CC12603132 | VILASH NARAN JAGANI | ARHUM ERECTORS PRIVATE LIMITED | 26/05/2026 |
| CC12603267 | Dharmesh Mohanlal Jain | ARHUM ERECTORS PRIVATE LIMITED | 31/05/2026 |
| CC12603187 | Chandrakala Kisanrao Chaudhari | ARHUM ERECTORS PRIVATE LIMITED | 28/05/2026 |
| CC12603230 | Shweta Somnath Narone | ARHUM ERECTORS PRIVATE LIMITED | 29/05/2026 |
| CC12603256 | Nilesh Sahebrao Mhaske | ARHUM ERECTORS PRIVATE LIMITED | 30/05/2026 |
| CC12603386 | Mahip Shyam Kataria | ARHUM ERECTORS PRIVATE LIMITED | 02/06/2026 |
| CC12603492 | Krishna Manjula Chilakamarri | ARHUM ERECTORS PRIVATE LIMITED | 06/06/2026 |
| CC12603470 | Varun Mahatma | ARHUM ERECTORS PRIVATE LIMITED | 05/06/2026 |
| CC12603584 | Truptil Vishwas Patil | ARHUM ERECTORS PRIVATE LIMITED | 10/06/2026 |
| CC12603603 | Sunil Dhake | ARHUM ERECTORS PRIVATE LIMITED | 11/06/2026 |
| CC12603714 | Ravi Mishra | ARHUM ERECTORS PRIVATE LIMITED | 16/06/2026 |
| CC12603695 | Rutuj Shendre | ARHUM ERECTORS PRIVATE LIMITED | 15/06/2026 |
| CC12603722 | Dibakar Paul | ARHUM ERECTORS PRIVATE LIMITED | 16/06/2026 |
| CC12603835 | Vishal Govindrao Harle | ARHUM ERECTORS PRIVATE LIMITED | 21/06/2026 |
| CC12603846 | Anand Mahajan | ARHUM ERECTORS PRIVATE LIMITED | 21/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 BEAUMONDE T6.pdf | 4 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 BEAUMONDE T6.pdf | 4 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 BEAUMONDE T6.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 BEAUMONDE T6 30062025.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 BEAUMONDE T6 30062025.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 BEAUMONDE T6 30062025.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 T6.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 T6.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 T6.pdf | 4 Jul 2026 |
| Form 5 (FY 2024-2025)File: T-6.pdf | 6 Sep 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A BEAUMONDE T6.pdf | 30 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Beaumonde t 6.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: beaumonde T6.pdf | 19 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Beaumonde T6.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 31032025.pdf | 8 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 31132024.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 31122024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 31122024.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BEAUMONDE T6 31122024.pdf | 10 Jan 2025 |
| Details of encumbrancesFile: T6.pdf | 20 Dec 2024 |
| Layout approvalFile: Pegasus Sec R2 CC 18012021.pdf | 19 Dec 2024 |
| Layout approvalFile: LAYOUT 2021.pdf | 19 Dec 2024 |
| Building plan approvalFile: scan1465.pdf | 19 Dec 2024 |
| Building plan approvalFile: scan1466.pdf | 19 Dec 2024 |
| Building plan approvalFile: scan1467.pdf | 19 Dec 2024 |
| Building plan approvalFile: scan1468.pdf | 19 Dec 2024 |
| Building plan approvalFile: scan1469.pdf | 19 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: Pegasus Sec R2 CC 18012021.pdf | 19 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT 2021.pdf | 19 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Pegasus Sec R2 CC 18012021.pdf | 19 Dec 2024 |
| Building Plan Approval (IOD)File: scan1465.pdf | 19 Dec 2024 |
| Building Plan Approval (IOD)File: scan1466.pdf | 19 Dec 2024 |
| Building Plan Approval (IOD)File: scan1467.pdf | 19 Dec 2024 |
| Building Plan Approval (IOD)File: scan1468.pdf | 19 Dec 2024 |
| Building Plan Approval (IOD)File: scan1469.pdf | 19 Dec 2024 |
| Declaration about Commencement CertificateFile: Format D - T6.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 17102024.pdf | 14 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 30092024.pdf | 14 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 BEAUMONDE T6_2023-2024.pdf | 14 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 30092024.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BEAUMONDE T6 30092024.pdf | 19 Oct 2024 |
| Declaration in FORM BFile: AFFIDAVIT-BEAUMONDE T6.pdf | 7 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE- BVP.pdf | 5 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE - NVP.pdf | 5 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 16072024.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE 6 30062024.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Vtp Beaumonde T6 300624.pdf | 16 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A BEAUMONDE T6 31032024.pdf | 16 May 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY BEAUMONDE T6 31032024.pdf | 6 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 31032024.pdf | 26 Apr 2024 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 31032024.pdf | 26 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BEAUMONDE T6 31032024.pdf | 4 Apr 2024 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 31032022.pdf | 29 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 31032022.pdf | 28 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 30062022.pdf | 21 Mar 2024 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 30062022.pdf | 21 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY BEAUMONDE T6 31122023.pdf | 16 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 31122023.pdf | 24 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BEAUMONDE T6 31122023.pdf | 22 Jan 2024 |
| Certificates of CA (Form 3)File: FORM 3 T6 31122023.pdf | 22 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: INVENTORY BEAUMONDE T6 30092023.pdf | 30 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 BEAUMONDE T6 30092023.pdf | 28 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 BEAUMONDE T6 30092023.pdf | 25 Oct 2023 |
| Certificates of CA (Form 3)File: FORM 3 BEAUMONDE T6 30092023.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 BEAUMONDE T6 2022-23.pdf | 29 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 30092022.pdf | 6 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 31122022.pdf | 6 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 31032023.pdf | 6 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: BEAUMONDE T6 30062023.pdf | 6 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 T6 30062023.pdf | 4 Aug 2023 |
| Details of encumbrancesFile: FE T6 010823.pdf | 1 Aug 2023 |
| Certificates of CA (Form 3)File: FORM 3 T6 30062023.pdf | 1 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 T6 30062023.pdf | 31 Jul 2023 |
| Details of encumbrancesFile: T6 FE.pdf | 28 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 T6 31032023.pdf | 26 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A T6 31032022.pdf | 26 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A T6 31032023.pdf | 26 Jul 2023 |
| Certificates of CA (Form 3)File: FORM 3 T6 31032023.pdf | 5 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 T6 31032023.pdf | 29 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 7 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VTP Beaumonde Nation R2 Tower6 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Manjri13,700+ in Pune
Filed coordinates, straight-line distance. 40 registered projects within 2 km.
MAGNACITY - Tower A2
Malnad Project (I) Pvt Ltd
Birla Evam Phase 1
Vypak Properties Private Limited
VTP AURELIA PHASE 1
ASOJ REALTY LLP
GODREJ BOULEVARD
Manjari Housing Projects LLP
Godrej Park Springs
Manjari Housing Projects LLP
VTP DOLCE VITA Phase 1
Ashdan Developers Private Limited
Builder: ARHUM ERECTORS PRIVATE LIMITED
ARHUM ERECTORS PRIVATE LIMITED has 6 registrations on MahaRERA, including VTP Beaumonde Nation R2 Tower6 and VTP Beaumonde Building T3. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that VTP Beaumonde Nation R2 Tower6 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VTP Beaumonde Nation R2 Tower6 is delayed beyond 15 Aug 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VTP Beaumonde Nation R2 Tower6?
The registered promoter entity is ARHUM ERECTORS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VTP Beaumonde Nation R2 Tower6?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VTP Beaumonde Nation R2 Tower6?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VTP Beaumonde Nation R2 Tower6?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VTP Beaumonde Nation R2 Tower6?
The professionals named in the filing: Architect: VK:a; Architect: VK A ARCHITECTURE; Engineer: SANTOSH MOHITE; Engineer: J W Consultants LLP Formerly Y S Sane Associates; Engineer: STRUDCOM CONSULTANTS PRIVATE LIMITED; Engineer: VTP Realty. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VTP Beaumonde Nation R2 Tower6?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback