ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VRUNDAVAN

Registration lapsed No litigation declared Others project

VRUNDAVAN

By ABHAR PROPERTIES PRIVATE LIMITED

RG-MH-06118 · RERA P51800051895 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 6 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2026Possession promised6 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 70%
56 of 58Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

VRUNDAVAN is a Others project by ABHAR PROPERTIES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800051895 on 7 Jul 2023. Possession was promised by 15 Apr 2026 and is now 6 months past that date. 2 of the 58 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete.

At a glance

Project

  • NameVRUNDAVAN
  • TypeOthers
  • Location
    • 60 NEHRU ROAD
    • VILE PARLE (EAST)
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • RERA no.P51800051895
  • ReraGenie IDRG-MH-06118

Builder

  • NameABHAR PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsSHASHI PAUL LAKHWARA, VIJAY SHANTILAL MEHTA

Key dates

6 months past promisethis monthRegisteredJul 2023PromisedApr 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Jul 2023
  • Promised completion15 Apr 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed70 files

Current status

3%2 of 58 units booked
23.4%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VRUNDAVAN - A WINGNA10024731
VRUNDAVAN - B WINGNA10027027

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 70%.

VRUNDAVAN - A WING7%
ActivityProgress
Excavation70%
Basement (if any)5%
Podiums (if any)0%
Plinth5%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VRUNDAVAN - B WING7%
ActivityProgress
Excavation70%
Basement (if any)5%
Podiums (if any)0%
Plinth5%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed93

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots93
Closed/Covered93
BuildingClosed/CoveredTotal
VRUNDAVAN - A WING4646
VRUNDAVAN - B WING4747

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,219 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI6581.52
Proposed, not sanctioned4,518 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAHURA CENTRE , ANDHERI EAST , MUMBAI -400093
Estimated costRs 40.00 cr
Cost incurredRs 9.37 cr
Work done23.43%
BuildingWingEstimatedIncurred
VRUNDAVAN - A WINGNARs 40.00 crRs 9.37 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIVEK BHOLE ARCHITECTS PVT LTD
EngineerH M RAJE STRUCTURAL CONSULTANTS PVT LTD
Chartered AccountantNEHALI & CO
PartnerRole in project
ABHAR PROPERTIES PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 30-06-24 letter - Copy.pdf5 May 2026
Form 2File: FORM 2 2024-25 Q1 n.pdf5 May 2026
Form 3File: Signed CA Certificate-ABHAR etco Sept 24.pdf5 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Fy 2024-25 Q1.pdf5 May 2026
Form 1File: 30-09-24 letter - Copy.pdf5 May 2026
Form 2File: FORM 2 2024-25 Q2 n.pdf5 May 2026
Form 3File: Signed CA Certificate-ABHAR etco Sept 24.pdf5 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Fy 2024-25 Q2.pdf5 May 2026
Form 1File: 31-12-24 letter - Copy.pdf5 May 2026
Form 2File: FORM 2 2024-25 Q3 n.pdf5 May 2026
Form 3File: Signed CA Certificate-ABHAR etco Dec 24.pdf5 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Fy 2024-25 Q3.pdf5 May 2026
Form 1File: 31-03-25 letter - Copy.pdf5 May 2026
Form 2File: FORM 2 2024-25 Q4 n.pdf5 May 2026
Form 3File: Signed CA Certificate-ABHAR etco Mar 25.pdf5 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Fy 2024-25 Q4.pdf5 May 2026
Withdrawal Update Form 1File: 30-09-25 letter - Copy.pdf5 May 2026
Withdrawal Update Form 1File: 30-06-25 letter - Copy.pdf5 May 2026
Withdrawal Update Form 1File: 30-09-25 letter - Copy.pdf5 May 2026
Withdrawal Update Form 1File: 31-12-25 letter - Copy.pdf5 May 2026
Withdrawal Update Form 1File: 31-03-26 letter - Copy.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 2025-26 Q1 n.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 2025-26 Q1 n.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 2025-26 Q2 n.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 2025-26 Q3 n.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 2025-26 Q4 n.pdf5 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-ABHAR etco June 25.pdf5 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-ABHAR etco June 25.pdf5 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-ABHAR etco Sept 25.pdf5 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-ABHAR etco Dec 25.pdf5 May 2026
Withdrawal Update Form 3File: Signed CA Certificate-ABHAR etco Mar 26.pdf5 May 2026
Commencement Certificates / NA Order for plotted developmentFile: CC cancellation letter_20240926.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf31 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf31 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf31 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate - Vrundavan.pdf13 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf19 Oct 2023
Layout approvalFile: 20230620175905347 HIGHLIGHTED.pdf21 Jun 2023
Layout approvalFile: 20230620175932308.pdf21 Jun 2023
Layout approvalFile: 20230620180004425 (1).pdf21 Jun 2023
Layout approvalFile: 20230620180035037.pdf21 Jun 2023
Layout approvalFile: 20230620180114872.pdf21 Jun 2023
Layout approvalFile: 20230620180136761.pdf21 Jun 2023
Layout approvalFile: 20230620180217684.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620175905347 HIGHLIGHTED.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620175932308.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620180004425 (1).pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620180035037.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620180114872.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620180136761.pdf21 Jun 2023
Copy of Layout Approval (in case of layout)File: 20230620180217684.pdf21 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE NEW.pdf20 Jun 2023
Building plan approvalFile: IOA.pdf13 Jun 2023
PAN CardFile: PAN Card .Pdf13 Jun 2023
Copy of the legal title reportFile: TITLE REPORT.pdf13 Jun 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE.pdf13 Jun 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE.pdf13 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf13 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Jun 2023
Declaration about Commencement CertificateFile: CC DECLARATION.pdf13 Jun 2023
Declaration in FORM BFile: FORM B.pdf13 Jun 2023
CERSAI detailsFile: CERSAI DECL.pdf13 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DOI.pdf13 Jun 2023
Proforma of Agreement for saleFile: AGREEMENT FOR SALE (1).pdf13 Jun 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf13 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT LETTER.pdf13 Jun 2023
Deviation Report with respect to Allotment letterFile: deviation allotment.pdf13 Jun 2023
Deviation Report with respect to model copy of AgreementFile: deviation agreement.pdf13 Jun 2023

How this compares with Mumbai Suburban

3%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRUNDAVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE (EAST)6,700+ in Mumbai Suburban

Builder: ABHAR PROPERTIES PRIVATE LIMITED

ABHAR PROPERTIES PRIVATE LIMITED has 1 registration on MahaRERA, including VRUNDAVAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VRUNDAVAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VRUNDAVAN is delayed beyond 15 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRUNDAVAN?

The registered promoter entity is ABHAR PROPERTIES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRUNDAVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRUNDAVAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRUNDAVAN?

The professionals named in the filing: Architect: VIVEK BHOLE ARCHITECTS PVT LTD; Engineer: H M RAJE STRUCTURAL CONSULTANTS PVT LTD; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.