ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / VRINDANAND-BLISS

Registered No litigation declared Residential / Group Housing project

VRINDANAND-BLISS

By MAKWANA AND TANMAY CONSTRUCTION

RG-MH-27630 · RERA P52100034827 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 17.25 crore secured on the land, in favour of Aditya Birla Finance Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Internal walls, 85%
18 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 109 documents Report an error

VRINDANAND-BLISS is a Residential / Group Housing project by MAKWANA AND TANMAY CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100034827 on 28 Apr 2022. Possession is promised by 31 Mar 2027. 14 of the 32 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameVRINDANAND-BLISS
  • TypeResidential / Group Housing
  • Location
    • NEAR PAN CARD CLUB NEAR ICON STERLING CENTRE
    • BANER
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034827
  • ReraGenie IDRG-MH-27630

Builder

  • NameMAKWANA AND TANMAY CONSTRUCTION
  • Entity typePartnership
  • PartnersUTTAM RAMNIKBHAI MAKWANA, UMESH RAJENDRA BORA
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredApr 2022PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2022
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed109 files

Current status

44%14 of 32 units booked
84.8%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLISSNA121132032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

BLISS: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered34
Open Space22

Land and ownership12

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,374 sq m
Land owned byThe promoter, with other names on the file
Named landowners12
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Ltd
Secured amountRs 17.25 crore
CERSAI search filedYes
Declared on11 Oct 2025
LandownerVillageDistrict
RAJASHREE RAJENDRA DINDEPune (M Corp.)Pune
ROHINI TAKATEPune (M Corp.)Pune
SHIVMURTI RAMCHANDRA GORDEPune (M Corp.)Pune
SURESH PANDIT WANIPune (M Corp.)Pune
JAGANANATH SITARAM PAWARPune (M Corp.)Pune
PRATIBHA PRAKASH SHIRODEPune (M Corp.)Pune
NILESH CHINTAMANI BAHALKARPune (M Corp.)Pune
SANJAY CHINTAMANI BAHALKARPune (M Corp.)Pune
SANGITA ANIL AMRUTKARPune (M Corp.)Pune
SHRADHA JAGANATH PAWARPune (M Corp.)Pune
HANUMANTH DAJI HULAWANPune (M Corp.)Pune
REKHA HANMANTH HULAWANPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityumesh bora
Permissible FSI3592.99
Proposed, not sanctioned3,593 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCRYSTAL ROOM BIBWEWADI-411037
Estimated costRs 11.60 cr
Cost incurredRs 9.84 cr
Work done84.83%
BuildingWingEstimatedIncurred
BLISSNARs 11.60 crRs 9.84 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX ARCHITECTS ASSOCIATES
EngineerUmesh Bora
Chartered AccountantSAC & Co LLP
Chartered AccountantPRIYANKA CHORDIYA AND ASSOCIATES
PartnerRole in project
MAKWANA AND TANMAY CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed109

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: arc certificat bliss_310326.pdf4 May 2026
Withdrawal Update Form 2File: form 2 bliss 31032026 sign.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 AS Vrindanand Bliss 31032026 sign.pdf4 May 2026
Withdrawal Update Form 1File: Form 1 Bliss 30092025 sign.pdf14 Feb 2026
Withdrawal Update Form 1File: Form 1 bliss 31122025.pdf14 Feb 2026
Withdrawal Update Form 2File: form 2 vrindanand bliss 30092025.pdf14 Feb 2026
Withdrawal Update Form 2File: Form 2 bliss 31122025.pdf14 Feb 2026
Withdrawal Update Form 3File: Form 3 AS Vrindanand Bliss 30092025 sign.pdf14 Feb 2026
Withdrawal Update Form 3File: FORM 3 BLISS 31122025 sign.pdf14 Feb 2026
Withdrawal Update Form 1File: architect certifiacte bliss-300625.pdf6 Aug 2025
Withdrawal Update Form 2File: Form 2 sign.pdf6 Aug 2025
Withdrawal Update Form 3File: Form 3 AS Vrindanand Bliss 30062025 sign.pdf6 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vrindanand bliss architect certificate.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vrindanand Bliss ca certificate.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vrindanand bliss-form 2.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 vrindananand bliss.pdf23 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 vrindanand bliss.pdf23 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 VRINDANAND-BLISS.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate for vrindanand bliss sept-24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vrindanand bliss architect certificate.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assuarance engineer certificate--bliss.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: disclosure of sold or book inventory.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: disclosure of sold or booked inventory.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 3 VRINDANAND-BLISS.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate vrindanand bliss.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate vrindanand bliss.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 VRINDANAND-BLISS.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf23 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf23 May 2024
Layout approvalFile: sanction plan 1 of 5 09102023 BLISS_compressed.pdf23 Feb 2024
Copy of Layout Approval (in case of layout)File: sanction plan 1 of 5 09102023 BLISS_compressed.pdf23 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 3 Commencement Certificates _ NA Order for plotted development.pdf23 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold unsold 30062023 BLISS.pdf23 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold unsold 30092023 BLISS.pdf23 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold unsold 31122023 BLISS final new.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 bliss with landowner units 30062023 both sign_compressed.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 300923 with landowner units both signed.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 bliss with landowner units 31122023 final both signed.pdf23 Feb 2024
Layout approvalFile: 3 Copy of Layout Approval highlighted.pdf1 Feb 2024
Copy of Layout Approval (in case of layout)File: 3 Copy of Layout Approval highlighted.pdf1 Feb 2024
Layout approvalFile: 3 Copy of Layout Approval (in case of layout).pdf31 Jan 2024
Copy of Layout Approval (in case of layout)File: 3 Copy of Layout Approval (in case of layout).pdf31 Jan 2024
Declaration about Commencement CertificateFile: 2 Commencement Certificates _ NA Order for plotted development.pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate bliss 311223.pdf31 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate bliss311223 SIGNED.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold unsold 31122023 BLISS final.pdf31 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 VRINDANAND BLISS 31122023 both sign_compressed.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Vrindanand Bliss 30092023 both signed_compressed.pdf18 Jan 2024
Layout approvalFile: Final Sanction_Layout.pdf9 Jan 2024
Layout approvalFile: Final Sanction_Floor Plan 1-7.pdf9 Jan 2024
Layout approvalFile: Final Sanction_Floor Plan 8-11.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Final Sanction_Layout.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Final Sanction_Floor Plan 1-7.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: Final Sanction_Floor Plan 8-11.pdf9 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement Sale-Bliss.pdf13 Dec 2023
Proforma of Agreement for saleFile: VRINDANAND BLISS_AGREEMENT OF SALE.pdf10 Dec 2023
Deviation Report with respect to model copy of AgreementFile: VRINDANAND BLISS_AGREEMENT OF SALE.pdf10 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: vrindanand bliss engineer certificate form-2A.pdf30 Nov 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf30 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf30 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: vrindanand bliss bank account.pdf30 Nov 2023
Deviation Report with respect to Allotment letterFile: deviation report vrindanand bliss.pdf30 Nov 2023
Layout approvalFile: Final Sanction_Layout.pdf26 Nov 2023
Building plan approvalFile: Final Sanction_Section.pdf26 Nov 2023
Copy of Layout Approval (in case of layout)File: Final Sanction_Layout.pdf26 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Final Sanction_Section.pdf26 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: commicement certificate baner.pdf26 Nov 2023
Declaration about Commencement CertificateFile: declaration of cc for bliss.pdf26 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate VRINDAVAN BLISS.pdf26 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Bliss.pdf26 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate-Bliss.pdf26 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 vrindanand bliss ca certificate.pdf26 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 VRINDANAND-BLISS 30-03-2023 both sign (1).pdf26 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate vrindanad bliss.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate bliss.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Makhwana-Vrindanand Bliss-both sign_compressed.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: vrindanad bliss engineer certificate.pdf20 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 VRINDANAND-BLISS.pdf20 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate.pdf19 May 2023

How this compares with Pune

44%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRINDANAND-BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANER13,700+ in Pune

Builder: MAKWANA AND TANMAY CONSTRUCTION

MAKWANA AND TANMAY CONSTRUCTION has 3 registrations on MahaRERA, including VRINDANAND ELITE and VRINDANAND-BLISS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VRINDANAND-BLISS is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRINDANAND-BLISS?

The registered promoter entity is MAKWANA AND TANMAY CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRINDANAND-BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRINDANAND-BLISS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRINDANAND-BLISS?

The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: Umesh Bora; Chartered Accountant: SAC & Co LLP; Chartered Accountant: PRIYANKA CHORDIYA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRINDANAND-BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRINDANAND-BLISS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRINDANAND-BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.