Home / Browse projects / Pune, Maharashtra / VLD Heritage

Registered No litigation declared Others project

VLD Heritage

By M/s VLD Associates

RG-MH-61604 · RERA P52100050131 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 80%
23 of 31Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

VLD Heritage is a Others project by M/s VLD Associates in Pune, Maharashtra, registered with MahaRERA as P52100050131 on 20 Mar 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 8 of the 31 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameVLD Heritage
  • TypeOthers
  • Location
    • Chinchwadgaon
    • Gandhi Peth
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050131
  • ReraGenie IDRG-MH-61604

Builder

  • NameM/s VLD Associates
  • Entity typeOthers
  • Named personsMr Rajendra Ganpatlal Varma, Mr Nandkumar Manikchand Lunawat, Smt Kusumbai Kantilal Dhoka, Smt Kalavati Ganpatlal Varma, Mr Kanhaiyalal Ganpatlal Varma

Key dates

this monthRegisteredMar 2023First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Mar 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed169 files

Current status

26%8 of 31 units booked
77.8%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VLD HeritageNA6625631

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

VLD Heritage: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area615 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 May 2025

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI2340.0
Proposed, not sanctioned2,340 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNigdi Pradhikaran Pune
Estimated costRs 6.72 cr
Cost incurredRs 5.22 cr
Work done77.79%
BuildingWingEstimatedIncurred
VLD HeritageNARs 5.80 crRs 4.61 cr
-NARs 92.00 lakhRs 62.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Dayanand K Shinde
EngineerMr Yogesh Kankariya
Chartered AccountantCA Pravin Pise and Associates
Chartered AccountantVAIBHAV S BHISE AND ASSOCIATES
PartnerRole in project
M/s VLD Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025688Dec 2024 → Dec 2025

Reason as filed by the promoterThe extension request is due to delays caused by acquisition and utilization of TDR. Please approve it

EA23122518937Dec 2024 → Dec 2026

Reason as filed by the promoterTechnical issues with the planning authority, resulting in delays in issuing the full Completion Certificate. Insufficient funding, material shortages, and unavailability of labour, further hindering our progress.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: F1june.pdf18 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf18 Jul 2026
Withdrawal Update Form 3File: F 3 - VLD HERITAGE.pdf18 Jul 2026
Withdrawal Update Form 1File: F1-Q4.pdf3 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf3 Jun 2026
Withdrawal Update Form 3File: F3-VLD.pdf3 Jun 2026
Withdrawal Update Form 1File: F1-Q3.pdf23 Jan 2026
Withdrawal Update Form 2File: F2-Q3.pdf23 Jan 2026
Withdrawal Update Form 3File: F3-VLD.pdf23 Jan 2026
Form 1File: F1-FINAL.pdf20 Oct 2025
Form 2File: Engineer Certificate.pdf20 Oct 2025
Form 3File: F3-VLD.pdf20 Oct 2025
Disclosure of Sold and Booked InventoryFile: SU-FINAL.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: VLD.pdf20 Oct 2025
Form 1File: F1-FINAL.pdf19 Jul 2025
Form 2File: F2-FINAL.pdf19 Jul 2025
Form 3File: F3-FINAL.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: SU-FINAL.pdf19 Jul 2025
Form 1File: F1-FINAL.pdf19 Jul 2025
Form 2File: F2-FINAL.pdf19 Jul 2025
Form 3File: F3-FINAL.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: SU-FINAL.pdf19 Jul 2025
Form 5 (FY 2022-2023)File: RERA AUDIT.pdf19 Jul 2025
Form 5 (FY 2023-2024)File: FORM-5(VLD)-1-6_merged.pdf19 Jul 2025
Form 1File: F1-MARCH-23.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU NARCH 23 (1).pdf24 May 2025
Form 1File: F1-JUNE-23.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU JUNE-23.pdf24 May 2025
Form 1File: F1-SEPT 23.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU SEPT 23.pdf24 May 2025
Form 1File: F1-DEC-23.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU DEC-23.pdf24 May 2025
Form 1File: F1-MARCH-24.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU.pdf24 May 2025
Form 1File: F1.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: F3.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU.pdf24 May 2025
Form 1File: FORM-1.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: FORM-3_compressed.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD-FEB-2024.pdf24 May 2025
Form 1File: F1.pdf24 May 2025
Form 2File: F2.pdf24 May 2025
Form 3File: FORM-3-1-6_merged.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: SU.pdf24 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-JUNE-23.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-SEPT-23.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-DEC-23.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-MARCH-24.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-JUNE-24.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-SEPT-24.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-DEC-24.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-MARCH-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-JUNE-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-DEC-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-SEPT-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-24.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-DEC-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-SEPT-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-JUNE-23.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-23.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-23.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-JUNE-23.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-SEPT-23 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-DEC-23 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-24 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-JUNE-24 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-SEPT-24 (1).pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-DEC-24 (1).pdf25 Mar 2025

How this compares with Pune

26%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VLD Heritage on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gandhi Peth13,700+ in Pune

2 kmVLD HeritageCompleted 34Lapsed / revoked 32Other 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 106 registered projects within 2 km.

Builder: M/s VLD Associates

M/s VLD Associates has 1 registration on MahaRERA, including VLD Heritage. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VLD Heritage is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VLD Heritage?

The registered promoter entity is M/s VLD Associates, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VLD Heritage?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VLD Heritage?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VLD Heritage?

The professionals named in the filing: Architect: Ar Dayanand K Shinde; Engineer: Mr Yogesh Kankariya; Chartered Accountant: CA Pravin Pise and Associates; Chartered Accountant: VAIBHAV S BHISE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VLD Heritage?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VLD Heritage. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VLD Heritage to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.