Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VISHWANATH DARSHAN is a Residential / Group Housing project by ASHAPURA COMBINES in Thane, Maharashtra, registered with MahaRERA as P51700054131 on 29 Dec 2023. Possession is promised by 31 Dec 2029. 12 of the 216 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameVISHWANATH DARSHAN
- TypeResidential / Group Housing
- Location
- Wadeghar
- Wadeghar-Kalyan West
- Kalyan-Dombivali (M Corp.)
- Kalyan
- Thane
- 421301
- Pincode421301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700054131
- ReraGenie IDRG-MH-06432
Builder
- NameASHAPURA COMBINES
- Entity typePartnership
- PartnersMANGESH DASHRATH GAIKAR, HARILAL NATHU PATEL, VIPUL HARILAL PATEL
- Other registrations4 more →
- Completed2 of 5
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Dec 2023
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings1 building record
- Documents filed88 files
Current status
Figures as on 20 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VISHWANATH DARSHAN | NA | 24 | 24 | 199 | 17 | 216 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.
VISHWANATH DARSHAN: 47% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
| Layout House drainage and chamber | Yes | 0% |
Parking filed167
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership68
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| HARSHAL BABAN NAIK | Ghatkopar | Mumbai Suburban |
| PRAKASH BABAN NAIK | Ghatkopar | Mumbai Suburban |
| KAVITA PRAMOD MHATRE | Ghatkopar | Mumbai Suburban |
| NIRMALA SATYAVAN PATIL | Ghatkopar | Mumbai Suburban |
| GAJANAN KALU DALVI | Ghatkopar | Mumbai Suburban |
| SANTOSH GAJANAN DALVI | Ghatkopar | Mumbai Suburban |
| SURESH KALU DALVI | Ghatkopar | Mumbai Suburban |
| RAMESH KALU DALVI | Ghatkopar | Mumbai Suburban |
| KAMLABAI WAMAN PATIL | Ghatkopar | Mumbai Suburban |
| UJWALA VILAS MIRKUTE | Ghatkopar | Mumbai Suburban |
| RAKESH MANOHAR KONKAR | Ghatkopar | Mumbai Suburban |
| UMESH MANOHAR KONKAR | Ghatkopar | Mumbai Suburban |
| SUNITA SHANKAR PAWAR | Ghatkopar | Mumbai Suburban |
| SANDESH GAJANAN DALVI | Ghatkopar | Mumbai Suburban |
| SANDEEP GAJANAN DALVI | Ghatkopar | Mumbai Suburban |
| SANJAY SURESH DALVI | Ghatkopar | Mumbai Suburban |
| ABDUL RAUF GULAM AKBAR MOULVI | Ghatkopar | Mumbai Suburban |
| FAHIM AHMED GULAM AKBAR MOULVI | Ghatkopar | Mumbai Suburban |
| REHENA NAZIR FALKE | Ghatkopar | Mumbai Suburban |
| RUKSHANA SAHNAWAZ MAJID | Ghatkopar | Mumbai Suburban |
| BALARAM BABU PATIL | Ghatkopar | Mumbai Suburban |
| KASHIBAI BALARAM PATIL | Ghatkopar | Mumbai Suburban |
| ASHOK BALARAM PATIL | Ghatkopar | Mumbai Suburban |
| KIRTI ASHOK PATIL | Ghatkopar | Mumbai Suburban |
| RAVINDRA BALARAM PATIL | Ghatkopar | Mumbai Suburban |
| VASANTI RAVINDRA PATIL | Ghatkopar | Mumbai Suburban |
| PREMA JAYRAM BAHIRE | Ghatkopar | Mumbai Suburban |
| REKHA GANESH GHANSOLKAR | Ghatkopar | Mumbai Suburban |
| SUDAM BABU PATIL | Ghatkopar | Mumbai Suburban |
| PARVATI SUDAM PATIL | Ghatkopar | Mumbai Suburban |
| YOGESH SUDAM PATIL | Ghatkopar | Mumbai Suburban |
| AKLESH SUDAM PATIL | Ghatkopar | Mumbai Suburban |
| SAVITA JAYWANT PATIL | Ghatkopar | Mumbai Suburban |
| KAVITA ARVIND VAITI | Ghatkopar | Mumbai Suburban |
| VITHABAI TUKARAM BHAGAT | Ghatkopar | Mumbai Suburban |
| SHEWANTA DHANAJAY BHOPI | Ghatkopar | Mumbai Suburban |
| SUMAN YASHWANT KOT | Ghatkopar | Mumbai Suburban |
| VAIJAYANTI BALARAM PATIL | Ghatkopar | Mumbai Suburban |
| Manglya Alias Mangesh Vitthal Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Sangeeta Mangesh Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Aavish Alias Avinash Vitthal Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Vandana Avinash Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Nirabai Alias Nirmala Mangaldas Patil | Ghatkopar | Mumbai Suburban |
| Kantibai Alias Kanta Prakash Kene | Ghatkopar | Mumbai Suburban |
| Pandabai Alias Sumitra Dinkar Naik | Ghatkopar | Mumbai Suburban |
| Heerabai Baban Naik | Ghatkopar | Mumbai Suburban |
| Fashibai Eknath Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Haresh Eknath Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Anita Haresh Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Sharad Eknath Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Lalita Sharad Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Sharmila Barku Alias Barkya Kharbe | Ghatkopar | Mumbai Suburban |
| Bhagirthi Alias Bhagubai Vandar Madhavi | Ghatkopar | Mumbai Suburban |
| Gulab Kaluram Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Naresh Kaluram Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Asha Naresh Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Vidya Naresh Vitari | Ghatkopar | Mumbai Suburban |
| Lata Bharat Chaudhari | Ghatkopar | Mumbai Suburban |
| Janabai Ramchandra Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Sham Ramchandra Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Usha Sham Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Rajesh Sham Naik | Ghatkopar | Mumbai Suburban |
| Dipti Sham Naik | Ghatkopar | Mumbai Suburban |
| Vasudev Ramchandra Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Lata Vasudev Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Heerabai Yashwant Naik Alias Vanjurkar | Ghatkopar | Mumbai Suburban |
| Laxmibai Alias Pramila Sudarshan Chaudhari | Ghatkopar | Mumbai Suburban |
| Usha Dattu Alias Dattatray Bhoir | Ghatkopar | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| VISHWANATH DARSHAN | NA | Rs 61.21 cr | Rs 19.32 cr |
| - | NA | Rs 1.50 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DEEPAK PATIL |
| Engineer | SHANTI CONSULTANT |
| Engineer | JAYENDRA VISANJI VIRA |
| Chartered Accountant | M K RAMANI |
| Chartered Accountant | K H R & CO |
| Partner | Role in project |
|---|---|
| ASHAPURA COMBINES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Dec 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Aug 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect certificate-Vishwanath.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Architect certificate-Vishwanath.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Architect certificate-Vishwanath.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: Architect certificate-Vishwanath.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Engineer's Certificate - FORM 2.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Engineeru0027s Certificate - FORM 2.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Engineeru0027s Certificate - FORM 2.pdf | 20 Jun 2026 |
| Withdrawal Update Form 2File: Engineeru0027s Certificate - FORM 2.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Vishwanath Darshar-From-3 CA Certificate-dt -06-12-2023_11zon.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Vishwanath Darshar-From-3 CA Certificate-dt -06-12-2023_11zon.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Vishwanath Darshar-From-3 CA Certificate-dt -06-12-2023_11zon.pdf | 20 Jun 2026 |
| Withdrawal Update Form 3File: Vishwanath Darshar-From-3 CA Certificate-dt -06-12-2023_11zon.pdf | 20 Jun 2026 |
| Form 1File: VISHWANATH DARSHAN ARCHITECT CERTIFICATE 31-03-2025.pdf | 21 May 2026 |
| Form 2File: VD-FORM 2- AS ON 31-3-25.pdf | 21 May 2026 |
| Form 3File: VD-FORM3 AS ON 31-3-25.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: VD- SOLD INVENTORY AS ON 31-3-25.pdf | 21 May 2026 |
| Form 2A (FY 2025-2026)File: ENGINEER CERTIFICATE VISHWANATH DARSHAN 31-3-26.pdf | 30 Apr 2026 |
| Form 1File: FORM 1 - VISHWANATH DARSHAN ARCHITECT CERTIFICATE 31-3-26.pdf | 29 Apr 2026 |
| Form 2File: FORM 2 -ENGINEER CERTIFICATE VISHWANATH DARSDHAN 31-3-26.pdf | 29 Apr 2026 |
| Form 3File: Form 3 - Vishwanath Darshan 31-3-26.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY - VD - 31-3-26.pdf | 29 Apr 2026 |
| Form 1File: 1 Architect Certificate 31-12-2025.pdf | 27 Jan 2026 |
| Form 2File: 2 ENGINEER Certificate 31-12-2025.pdf | 27 Jan 2026 |
| Form 3File: Form 3 - VD Scan copy.pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 27 Jan 2026 |
| Form 1File: VD ARCHITECT CERTIFICATE 30-9-25.pdf | 13 Nov 2025 |
| Form 2File: VD ENGINEER CERTIFICATE 30-9-25.pdf | 13 Nov 2025 |
| Form 3File: VD-Form-3 as on 30-9-25.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Vishwanath Darshan-Sold Unsold Inventory.pdf | 13 Nov 2025 |
| Form 2A (FY 2024-2025)File: VISHWANATH DARSHAN ENGINEER CERTIFICATE 31-3-25.pdf | 26 Sep 2025 |
| Form 5 (FY 2024-2025)File: Vsihwanath darshan - Form 5-YR-2024-25.pdf | 26 Sep 2025 |
| Form 1File: VISHWANATH DARSHAN ARCHITECT CERTIFICATE 30-6-25.pdf | 11 Sep 2025 |
| Form 2File: VISHWANATH DARSHAN ENGINEER CERTIFICATE 30-6-25.pdf | 11 Sep 2025 |
| Form 3File: VD- Form 3-dt-30-6-25.pdf | 11 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: VD - Inventory Details-30-6-25.pdf | 11 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: VISHWANATH DARSHAN SOLD INVENTORY 31-3-25.pdf | 12 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: VISHWANATH DARSHAN ENGINEER CERTIFICATE 31-3-25.pdf | 12 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6th -Form 3 - Vishwanath Darshan -31-3-25 (3).pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VISHWANATH DARSHAN ENGINEER CERTIFICATE 31-03-2025.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: vishwanath darshan sold list 31-12-24.pdf | 29 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE QUALITY VISHWANATH DARSHAN 31-03-24.pdf | 23 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5-VD - Form3 - 31-12-24-SIGNED.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5-ENGINEER CERTIFICATE VISHWANATH DARSHAN 31-12-24.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE VISHWANATH DARSHAN 31-12-24.pdf | 8 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE VISHWANATH DARSHAN 31-03-24.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE VISHWANATH DARSHAN 30-06-24.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2nd Form 3 - Vishwanath Darshan -31-3-24.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3-VD - Form3 - 30-6-24-SIGNED.pdf | 23 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4-VD - Form3 - 30-9-24-SIGNED.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE VISHWANATH DARSHAN 30-9-24.pdf | 21 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-ENGINEER CERTIFICATE VISHWANATH DARSHAN 1-04-24.pdf | 20 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3-ENGINEER CERTIFICATE VISHWANATH DARSHAN 1-07-24.pdf | 20 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4-ENGINEER CERTIFICATE VISHWANATH DARSHAN 1-10-24.pdf | 20 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VD-Form 5-2024-UPLOADED.pdf | 15 Nov 2024 |
| Building plan approvalFile: Plan no 3_11zon.pdf | 20 Dec 2023 |
| Copy of the legal title reportFile: ilovepdf_merged (42)_11zon.pdf | 20 Dec 2023 |
| Details of encumbrances concerned to FinanceFile: encumbrance finance.pdf | 20 Dec 2023 |
| Details of encumbrances concerned to FinanceFile: encumbrance legal.pdf | 20 Dec 2023 |
| Details of encumbrances concerned to LegalFile: encumbrance finance.pdf | 20 Dec 2023 |
| Details of encumbrances concerned to LegalFile: encumbrance legal.pdf | 20 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan no 3_11zon.pdf | 20 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Verification- Vishwanath Darshan (1).pdf | 20 Dec 2023 |
| Other - LegalFile: CONFIRMATION DEED Anandibai dalvi_11zon.pdf | 20 Dec 2023 |
| Other - LegalFile: CONFIRMATION DEED maina chuadhari_11zon.pdf | 20 Dec 2023 |
| Other - TechnicalFile: CC Verification- Vishwanath Darshan (1).pdf | 20 Dec 2023 |
| Other - TechnicalFile: Format -D, vishwanath Darshan .pdf | 20 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: GetUserDocumentFileContent (4).pdf | 4 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: DEVIATION REPORT - ALLOTMENT.pdf | 4 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT - AGREEMENT.pdf | 4 Oct 2023 |
| Layout approvalFile: Plan no 1_11zon (1).pdf | 2 Aug 2023 |
| Building plan approvalFile: Plan no 1_11zon (1).pdf | 2 Aug 2023 |
| Building plan approvalFile: Plan 2_11zon (1).pdf | 2 Aug 2023 |
| PAN CardFile: ASHAPURA COMBINES - PAN.pdf | 2 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration Legal Charge Vishwanath Darshan.pdf | 2 Aug 2023 |
| Details of encumbrances concerned to LegalFile: Declaration Legal Charge Vishwanath Darshan.pdf | 2 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: Plan no 1_11zon (1).pdf | 2 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan no 1_11zon (1).pdf | 2 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2_11zon (1).pdf | 2 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate-Vishwanath.pdf | 2 Aug 2023 |
| Declaration about Commencement CertificateFile: Declaration CC Vishwanath Darshan.pdf | 2 Aug 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VISHWANATH DARSHAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Wadeghar-Kalyan West7,600+ in Thane
Filed coordinates, straight-line distance. 183 registered projects within 2 km.
PODDAR RIVIERA PHASE - I
Poddar Housing and Development Limited
Sinhagad by Bhagwati Haware - Wing - B
Bhagwati Haware Properties Supertech
Pratapgad by Bhagwati Haware - Wing - C
Bhagwati Haware Properties Supertech
Rajgad by Bhagwati Haware - Wing - D
Bhagwati Haware Properties Supertech
PODDAR RIVIERA PHASE - III
Poddar Housing and Development Limited
THARWANI PARKGLEN PHASE I
THARWANI REALTORS
See every Thane project, with the district possession charts
Builder: ASHAPURA COMBINES
ASHAPURA COMBINES has 5 registrations on MahaRERA, including NEELKANTH SHRUSHTI and RAMESHWAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if VISHWANATH DARSHAN is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VISHWANATH DARSHAN?
The registered promoter entity is ASHAPURA COMBINES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VISHWANATH DARSHAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VISHWANATH DARSHAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VISHWANATH DARSHAN?
The professionals named in the filing: Architect: DEEPAK PATIL; Engineer: SHANTI CONSULTANT; Engineer: JAYENDRA VISANJI VIRA; Chartered Accountant: M K RAMANI; Chartered Accountant: K H R & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VISHWANATH DARSHAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback