Home / Browse projects / Thane, Maharashtra / Vishnu Vatika Wing C Phase II

Registered No litigation declared Residential / Group Housing project

Vishnu Vatika Wing C Phase II

By VISHNU VATIKA

RG-MH-02898 · RERA P51700020130 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 43 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 43 months from the original
9 of 11Construction stages donefurthest along: Installation of Lifts, 88%
17 of 109Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 179 documents Report an error

Vishnu Vatika Wing C Phase II is a Residential / Group Housing project by VISHNU VATIKA in Thane, Maharashtra, registered with MahaRERA as P51700020130 on 29 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 43 months from the original filing. 92 of the 109 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameVishnu Vatika Wing C Phase II
  • TypeResidential / Group Housing
  • Location
    • Badlapur Kanhor Road
    • Badlapur Gaon
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • RERA no.P51700020130
  • ReraGenie IDRG-MH-02898

Builder

  • NameVISHNU VATIKA
  • Entity typePartnership
  • PartnersMUKESH BARKU MORE, HEMANT ANANDRAO NIMBALKAR, SHABBIR RAZAK SIROHA, VAIBHAV VISHNU PISEKAR
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredMar 2019First promiseMay 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Mar 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 May 2023)
  • Buildings1 building record
  • Documents filed179 files

Current status

84%92 of 109 units booked
98.4%Work done, per cost certificate

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vishnu Vatika Wing C Phase IINA14141036109

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 88%.

Vishnu Vatika Wing C Phase II: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.88%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes92%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes88%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,390 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Oct 2025
LandownerVillageDistrict
Santosh Shivram BhagatBadlapur (M Cl)Thane
Sunil Shivram BhagatBadlapur (M Cl)Thane
Prathmesh Sunil BhagatBadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Nagarparishad
Permissible FSI4206.0
Proposed, not sanctioned400 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1ST FLOOR DEODHAR MARKET OPP BADLAPUR RLY STN BADLAPUR WEST
Estimated costRs 13.41 cr
Cost incurredRs 13.19 cr
Work done98.38%
BuildingWingEstimatedIncurred
Vishnu Vatika Wing C Phase IINARs 11.92 crRs 11.76 cr
-NARs 1.49 crRs 1.43 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Barku More
ArchitectM Square Architects
EngineerAtul Kudtarkar & Associates
Chartered AccountantSiddhant & Mayur Chartered Accountants
Chartered AccountantJagadish and Harish
Chartered AccountantShripati Gandhi Choudhari & Co. Chartered Accountant
PartnerRole in project
VISHNU VATIKA-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019804May 2023 → May 2025

Reason as filed by the promoterAs per the attachment

EXT51700016637May 2023 → May 2024

Reason as filed by the promoterAs per attachment

EA26112518441May 2023 → Mar 2026

Reason as filed by the promoterThe main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Moreover, the contractors appointed for the various work also underperformed due to which overall schedule of construction effected. It may be noted that the project is located at Badlapur. Uncertain operational challenges like heavy rains during rainy season also disrupted regular construction work. The only pendi

EA04072621669May 2023 → Dec 2026

Reason as filed by the promoterThe construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sales during the initial phases. Although the number of units sold has improved over time, the earlier sluggish sales adversely impacted on the project’s cash flow, thereby contributing to the delay. Additionally, certain contractors appointed for execution of various works did not perform as expected, which further affected the overall construction schedule. It

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed179

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 179 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Wing C PH IIMarch 26.pdf4 Jul 2026
Form 5 (FY 2025-2026)File: Form 5 - FY march 26 Phase 2 C Wing.pdf4 Jul 2026
Form 5 (FY 2025-2026)File: Form 5 - FY march 26 Phase 2 C Wing.pdf4 Jul 2026
Form 2A (FY 2024-2025)File: 2A 24-25.pdf3 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A Wing C PH IIMarch 26.pdf3 Jul 2026
Form 5 (FY 2024-2025)File: Form 5 - FY march 25 Phase 2 C Wing.pdf3 Jul 2026
Withdrawal Update Form 1File: Form 1 Q4 (2025-26).PDF22 Jun 2026
Withdrawal Update Form 2File: Form II (Q4) 2025-26.PDF22 Jun 2026
Withdrawal Update Form 3File: Form 3 (Q4) 2025-26.PDF22 Jun 2026
Withdrawal Update Form 1File: Form I (Q2) 2025-26.PDF9 Apr 2026
Withdrawal Update Form 1File: VV Form I (Q3) 2025-26.pdf9 Apr 2026
Withdrawal Update Form 2File: Form II (Q2) 2025-26.PDF9 Apr 2026
Withdrawal Update Form 2File: VV Form II (Q3) 2025-26.pdf9 Apr 2026
Withdrawal Update Form 3File: Form 3 Phase II Sept-25.pdf9 Apr 2026
Withdrawal Update Form 3File: Form 3 Phase II Sept-25.pdf9 Apr 2026
Form 5 (FY 2023-2024)File: Form 5 - FY march 24 Phase 2 C Wing.pdf14 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 - FY march 25 Phase 2 C Wing.pdf14 Jan 2026
Withdrawal Update Form 1File: VV Form 1 (Q1) 25-26.pdf30 Oct 2025
Withdrawal Update Form 2File: Form II (Q1) 25-26.pdf30 Oct 2025
Withdrawal Update Form 3File: Form 3 (Q1) 25-26_compressed.pdf30 Oct 2025
Form 1File: Form 1 Jun 24.PDF29 Oct 2025
Form 2File: Form 2 June 24.PDF29 Oct 2025
Form 3File: VV Form 3_Q1_2024-25.PDF29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Jun 24.PDF29 Oct 2025
Form 1File: VV Form 1 - Mar 24.PDF29 Oct 2025
Form 2File: VV Form 2 - Mar 24.PDF29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory Vishnu Vatika.PDF29 Oct 2025
Form 3File: March 24.pdf29 Oct 2025
Form 1File: Form 1 Sep 24.PDF29 Oct 2025
Form 2File: Form 2 Sep 24.PDF29 Oct 2025
Form 3File: VV Form 3_Q2_2024-25.PDF29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Sep 24.PDF29 Oct 2025
Form 2File: Form 2 Dec 24.PDF29 Oct 2025
Form 1File: Form 1 Dec 24.PDF29 Oct 2025
Form 3File: VV Form 3_Q3_2024-25.PDF29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Dec 24.PDF29 Oct 2025
Form 1File: VV Form 1 March 25.pdf29 Oct 2025
Form 2File: Form 2 March 25.PDF29 Oct 2025
Form 3File: March 25 Form 3.pdf29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Mar 25.PDF29 Oct 2025
Form 2A (FY 2019-2020)File: Ph II Form 2A Mar 20.pdf29 Oct 2025
Form 2A (FY 2018-2019)File: March 19.pdf29 Oct 2025
Form 2A (FY 2020-2021)File: March 21.pdf29 Oct 2025
Form 2A (FY 2021-2022)File: March 22_page-0001.pdf29 Oct 2025
Form 2A (FY 2022-2023)File: VV Ph II Form 2A.PDF29 Oct 2025
Form 2A (FY 2023-2024)File: Form 2A - Wing C 23-24.PDF29 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - Wing C 24-25.PDF29 Oct 2025
Form 5 (FY 2018-2019)File: Form 5 - Mar 19.PDF29 Oct 2025
Form 5 (FY 2019-2020)File: Form 5 - Mar 20.PDF29 Oct 2025
Form 5 (FY 2020-2021)File: Form 5 - Mar 21.PDF29 Oct 2025
Form 5 (FY 2021-2022)File: Form 5 - Mar 22.PDF29 Oct 2025
Form 5 (FY 2022-2023)File: Form 5 - Mar - 23.PDF29 Oct 2025
Disclosure of sold/ booked inventoryFile: Diclosure of Sold_Booked Inventory Jun 24.PDF17 Jul 2025
Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Sep 24.PDF17 Jul 2025
Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Dec 24.PDF17 Jul 2025
Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Mar 25.PDF17 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun 24.PDF17 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep 24.PDF17 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 24.PDF17 Jun 2025
Certificates of CA (Form 3)File: 1Form 3 Vishnu Vatika C Wing Jun 24.pdf17 Jun 2025
Certificates of CA (Form 3)File: 2Form 3 Vishnu Vatika C Wing Sep 24.pdf17 Jun 2025
Certificates of CA (Form 3)File: 3Form 3 Vishnu Vatika C Wing Dec 24.pdf17 Jun 2025
Certificates of CA (Form 3)File: 4Form 3 Vishnu Vatika C Wing Mar 25.pdf17 Jun 2025
Certificates of CA (Form 3)File: 4Form 3 Vishnu Vatika C Wing Mar 25.pdf17 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 24.PDF17 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 24.PDF17 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 24.PDF17 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 25.PDF17 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Wing C 23-24.PDF17 Jun 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Vishnu Vatika.PDF20 May 2024
Declaration in FORM BFile: Declaretation_Form B.PDF16 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VV Form 1 - Mar 24.PDF16 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VV Form 2 - Mar 24.PDF16 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: VV Ph II Form 2A.PDF16 May 2024
Certificates of CA (Form 3)File: 1 VV Ph II Form 3 - Mar 22.PDF16 May 2024
Certificates of CA (Form 3)File: 2 VV Ph II Form 3 - June 22.PDF16 May 2024
Certificates of CA (Form 3)File: 3 VV Ph II Form 3 - Sep 22.PDF16 May 2024
Certificates of CA (Form 3)File: 4 VV Ph II Form 3 - Dec 22.PDF16 May 2024
Certificates of CA (Form 3)File: 5 VV Ph II Form 3 - Mar 23.PDF16 May 2024
Certificates of CA (Form 3)File: 6 VV Ph II Form 3 - June 23.PDF16 May 2024

How this compares with Thane

84%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 43 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vishnu Vatika Wing C Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur Gaon7,600+ in Thane

Builder: VISHNU VATIKA

VISHNU VATIKA has 2 registrations on MahaRERA, including VISHNU VATIKA WING A AND B PHASE I and Vishnu Vatika Wing C Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Vishnu Vatika Wing C Phase II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vishnu Vatika Wing C Phase II?

The registered promoter entity is VISHNU VATIKA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vishnu Vatika Wing C Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vishnu Vatika Wing C Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vishnu Vatika Wing C Phase II?

The professionals named in the filing: Architect: Nilesh Barku More; Architect: M Square Architects; Engineer: Atul Kudtarkar & Associates; Chartered Accountant: Siddhant & Mayur Chartered Accountants; Chartered Accountant: Jagadish and Harish; Chartered Accountant: Shripati Gandhi Choudhari & Co. Chartered Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vishnu Vatika Wing C Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vishnu Vatika Wing C Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vishnu Vatika Wing C Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.