Vishnu Vatika Wing C Phase II
RG-MH-02898 · RERA P51700020130 · Last updated on MahaRERA portal: 4 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 43 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vishnu Vatika Wing C Phase II is a Residential / Group Housing project by VISHNU VATIKA in Thane, Maharashtra, registered with MahaRERA as P51700020130 on 29 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 43 months from the original filing. 92 of the 109 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameVishnu Vatika Wing C Phase II
- TypeResidential / Group Housing
- Location
- Badlapur Kanhor Road
- Badlapur Gaon
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- RERA no.P51700020130
- ReraGenie IDRG-MH-02898
Builder
- NameVISHNU VATIKA
- Entity typePartnership
- PartnersMUKESH BARKU MORE, HEMANT ANANDRAO NIMBALKAR, SHABBIR RAZAK SIROHA, VAIBHAV VISHNU PISEKAR
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Mar 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 May 2023)
- Buildings1 building record
- Documents filed179 files
Current status
Figures as on 4 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vishnu Vatika Wing C Phase II | NA | 14 | 14 | 103 | 6 | 109 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 88%.
Vishnu Vatika Wing C Phase II: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 88% |
Progress on shared amenities15
As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 92% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 88% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Santosh Shivram Bhagat | Badlapur (M Cl) | Thane |
| Sunil Shivram Bhagat | Badlapur (M Cl) | Thane |
| Prathmesh Sunil Bhagat | Badlapur (M Cl) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Vishnu Vatika Wing C Phase II | NA | Rs 11.92 cr | Rs 11.76 cr |
| - | NA | Rs 1.49 cr | Rs 1.43 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nilesh Barku More |
| Architect | M Square Architects |
| Engineer | Atul Kudtarkar & Associates |
| Chartered Accountant | Siddhant & Mayur Chartered Accountants |
| Chartered Accountant | Jagadish and Harish |
| Chartered Accountant | Shripati Gandhi Choudhari & Co. Chartered Accountant |
| Partner | Role in project |
|---|---|
| VISHNU VATIKA | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per the attachment
Reason as filed by the promoterAs per attachment
Reason as filed by the promoterThe main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Moreover, the contractors appointed for the various work also underperformed due to which overall schedule of construction effected. It may be noted that the project is located at Badlapur. Uncertain operational challenges like heavy rains during rainy season also disrupted regular construction work. The only pendi
Reason as filed by the promoterThe construction work of the project has been completed in all respects. This is duly evidenced by Table A of Form 1, i.e., the Architect’s Certificate. The primary reason for the delay in completion of the project was the slow pace of sales during the initial phases. Although the number of units sold has improved over time, the earlier sluggish sales adversely impacted on the project’s cash flow, thereby contributing to the delay. Additionally, certain contractors appointed for execution of various works did not perform as expected, which further affected the overall construction schedule. It
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed179
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 179 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A Wing C PH IIMarch 26.pdf | 4 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 - FY march 26 Phase 2 C Wing.pdf | 4 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 - FY march 26 Phase 2 C Wing.pdf | 4 Jul 2026 |
| Form 2A (FY 2024-2025)File: 2A 24-25.pdf | 3 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Wing C PH IIMarch 26.pdf | 3 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - FY march 25 Phase 2 C Wing.pdf | 3 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 (2025-26).PDF | 22 Jun 2026 |
| Withdrawal Update Form 2File: Form II (Q4) 2025-26.PDF | 22 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 (Q4) 2025-26.PDF | 22 Jun 2026 |
| Withdrawal Update Form 1File: Form I (Q2) 2025-26.PDF | 9 Apr 2026 |
| Withdrawal Update Form 1File: VV Form I (Q3) 2025-26.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: Form II (Q2) 2025-26.PDF | 9 Apr 2026 |
| Withdrawal Update Form 2File: VV Form II (Q3) 2025-26.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Phase II Sept-25.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Phase II Sept-25.pdf | 9 Apr 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - FY march 24 Phase 2 C Wing.pdf | 14 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - FY march 25 Phase 2 C Wing.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: VV Form 1 (Q1) 25-26.pdf | 30 Oct 2025 |
| Withdrawal Update Form 2File: Form II (Q1) 25-26.pdf | 30 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 (Q1) 25-26_compressed.pdf | 30 Oct 2025 |
| Form 1File: Form 1 Jun 24.PDF | 29 Oct 2025 |
| Form 2File: Form 2 June 24.PDF | 29 Oct 2025 |
| Form 3File: VV Form 3_Q1_2024-25.PDF | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Diclosure of Sold_Booked Inventory Jun 24.PDF | 29 Oct 2025 |
| Form 1File: VV Form 1 - Mar 24.PDF | 29 Oct 2025 |
| Form 2File: VV Form 2 - Mar 24.PDF | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory Vishnu Vatika.PDF | 29 Oct 2025 |
| Form 3File: March 24.pdf | 29 Oct 2025 |
| Form 1File: Form 1 Sep 24.PDF | 29 Oct 2025 |
| Form 2File: Form 2 Sep 24.PDF | 29 Oct 2025 |
| Form 3File: VV Form 3_Q2_2024-25.PDF | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Sep 24.PDF | 29 Oct 2025 |
| Form 2File: Form 2 Dec 24.PDF | 29 Oct 2025 |
| Form 1File: Form 1 Dec 24.PDF | 29 Oct 2025 |
| Form 3File: VV Form 3_Q3_2024-25.PDF | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Dec 24.PDF | 29 Oct 2025 |
| Form 1File: VV Form 1 March 25.pdf | 29 Oct 2025 |
| Form 2File: Form 2 March 25.PDF | 29 Oct 2025 |
| Form 3File: March 25 Form 3.pdf | 29 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Diclosure of Sold Booked Inventory Mar 25.PDF | 29 Oct 2025 |
| Form 2A (FY 2019-2020)File: Ph II Form 2A Mar 20.pdf | 29 Oct 2025 |
| Form 2A (FY 2018-2019)File: March 19.pdf | 29 Oct 2025 |
| Form 2A (FY 2020-2021)File: March 21.pdf | 29 Oct 2025 |
| Form 2A (FY 2021-2022)File: March 22_page-0001.pdf | 29 Oct 2025 |
| Form 2A (FY 2022-2023)File: VV Ph II Form 2A.PDF | 29 Oct 2025 |
| Form 2A (FY 2023-2024)File: Form 2A - Wing C 23-24.PDF | 29 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Wing C 24-25.PDF | 29 Oct 2025 |
| Form 5 (FY 2018-2019)File: Form 5 - Mar 19.PDF | 29 Oct 2025 |
| Form 5 (FY 2019-2020)File: Form 5 - Mar 20.PDF | 29 Oct 2025 |
| Form 5 (FY 2020-2021)File: Form 5 - Mar 21.PDF | 29 Oct 2025 |
| Form 5 (FY 2021-2022)File: Form 5 - Mar 22.PDF | 29 Oct 2025 |
| Form 5 (FY 2022-2023)File: Form 5 - Mar - 23.PDF | 29 Oct 2025 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold_Booked Inventory Jun 24.PDF | 17 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Sep 24.PDF | 17 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Dec 24.PDF | 17 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Diclosure of Sold Booked Inventory Mar 25.PDF | 17 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun 24.PDF | 17 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep 24.PDF | 17 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 24.PDF | 17 Jun 2025 |
| Certificates of CA (Form 3)File: 1Form 3 Vishnu Vatika C Wing Jun 24.pdf | 17 Jun 2025 |
| Certificates of CA (Form 3)File: 2Form 3 Vishnu Vatika C Wing Sep 24.pdf | 17 Jun 2025 |
| Certificates of CA (Form 3)File: 3Form 3 Vishnu Vatika C Wing Dec 24.pdf | 17 Jun 2025 |
| Certificates of CA (Form 3)File: 4Form 3 Vishnu Vatika C Wing Mar 25.pdf | 17 Jun 2025 |
| Certificates of CA (Form 3)File: 4Form 3 Vishnu Vatika C Wing Mar 25.pdf | 17 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 24.PDF | 17 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 24.PDF | 17 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 24.PDF | 17 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 25.PDF | 17 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Wing C 23-24.PDF | 17 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Vishnu Vatika.PDF | 20 May 2024 |
| Declaration in FORM BFile: Declaretation_Form B.PDF | 16 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VV Form 1 - Mar 24.PDF | 16 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VV Form 2 - Mar 24.PDF | 16 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: VV Ph II Form 2A.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 1 VV Ph II Form 3 - Mar 22.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 2 VV Ph II Form 3 - June 22.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 3 VV Ph II Form 3 - Sep 22.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 4 VV Ph II Form 3 - Dec 22.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 5 VV Ph II Form 3 - Mar 23.PDF | 16 May 2024 |
| Certificates of CA (Form 3)File: 6 VV Ph II Form 3 - June 23.PDF | 16 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 179 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vishnu Vatika Wing C Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Badlapur Gaon7,600+ in Thane
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: VISHNU VATIKA
VISHNU VATIKA has 2 registrations on MahaRERA, including VISHNU VATIKA WING A AND B PHASE I and Vishnu Vatika Wing C Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Vishnu Vatika Wing C Phase II is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vishnu Vatika Wing C Phase II?
The registered promoter entity is VISHNU VATIKA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vishnu Vatika Wing C Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vishnu Vatika Wing C Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vishnu Vatika Wing C Phase II?
The professionals named in the filing: Architect: Nilesh Barku More; Architect: M Square Architects; Engineer: Atul Kudtarkar & Associates; Chartered Accountant: Siddhant & Mayur Chartered Accountants; Chartered Accountant: Jagadish and Harish; Chartered Accountant: Shripati Gandhi Choudhari & Co. Chartered Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vishnu Vatika Wing C Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback