Red flags

  • Completion date moved by 16 months
  • 2 extensions taken
  • Rs 2.00 crore secured on the land, in favour of JANKALYAN NAGARI SAHAKARI PATSANSTHAMARYADIT KARAD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 16 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
32 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

VISHNU HARI REGENCY is a Others project by AVANEESH BUILDCON LLP in Sangli, Maharashtra, registered with MahaRERA as P53100049307 on 7 Feb 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 16 months from the original filing. 2 of the 34 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameVISHNU HARI REGENCY
  • TypeOthers
  • Location
    • SANGLI MADHAVNAGAR ROAD
    • CHINTAMANI NAGAR NEAR HOTEL PRASHANT
    • OPP GHANSHYAM NAGAR
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100049307
  • ReraGenie IDRG-MH-87874

Builder

  • NameAVANEESH BUILDCON LLP
  • Entity typePartnership
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2023First promiseDec 2025Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Feb 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed92 files

Current status

6%2 of 34 units booked
72.8%Work done, per cost certificate

Figures as on 28 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VISHNU HARI REGENCYNA75221234

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

VISHNU HARI REGENCY: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 28 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered8
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area394 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofJANKALYAN NAGARI SAHAKARI PATSANSTHAMARYADIT KARAD
Secured amountRs 2.00 crore
CERSAI search filedYes
Declared on11 Aug 2025
LandownerVillageDistrict
PRASHANT VISHNUPANT HARUGADESangli Miraj Kupwad (M Corp.)Sangli

Approvals and building plan

Sanctioning authoritySANGLI MIRAJ KUPWAD CORPORATION
Permissible FSI1248.22
Proposed, not sanctioned1,248 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHAVEER NAGAR VARDHAMAN COMPLEX HIGH SCHOOL ROAD VAKHARBHAG SANGLI
Estimated costRs 2.97 cr
Cost incurredRs 2.16 cr
Work done72.77%
BuildingWingEstimatedIncurred
VISHNU HARI REGENCYNARs 2.97 crRs 2.16 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMBER SHINDE
EngineerVIKAS UDDHAV PATIL
Chartered AccountantSHRINIWAS N BHOSALE
Chartered AccountantBPCH AND CO
PartnerRole in project
AVANEESH BUILDCON LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P53100049307/WarDec 2025 → Apr 2027

Reason as filed by the promoterNA

EA05122518552Dec 2025 → Dec 2026

Reason as filed by the promoter2. That due to slow customer booking response and resultant delays in financial inflows, the progress of construction has been affected, leading to unavoidable delay in achieving the originally committed timelines

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1 30-06-2026.pdf28 Sep 2026
Withdrawal Update Form 2File: Form2 30-6-2026.pdf28 Sep 2026
Withdrawal Update Form 3File: FORM-3_30-06-2026.pdf28 Sep 2026
Withdrawal Update Form 1File: Form-1 31-3-2026.pdf25 Sep 2026
Withdrawal Update Form 2File: Form2 31-3-2026.pdf25 Sep 2026
Withdrawal Update Form 3File: FORM-3_31-03-2026.pdf25 Sep 2026
Form 5 (FY 2025-2026)File: FORM-5 2025-2026.pdf19 Aug 2026
Form 5 (FY 2024-2025)File: FORM-5 2024-2025.pdf19 Aug 2026
Withdrawal Update Form 1File: Withdrawal Application Form1_31122025_VHR.pdf27 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 _31122025_VHR.pdf27 May 2026
Withdrawal Update Form 3File: form 3 _31122025_vishnu hari.pdf27 May 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf27 May 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-2026.pdf27 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1_31122025_VHR.pdf10 Mar 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 _31122025_VHR.pdf10 Mar 2026
Withdrawal Update Form 3File: form 3 _31122025_vishnu hari.pdf10 Mar 2026
Withdrawal Update Form 1File: Form1 30-9-25.pdf28 Nov 2025
Withdrawal Update Form 2File: Form2 30-9-25.pdf28 Nov 2025
Withdrawal Update Form 3File: form-3 30-9-25.pdf28 Nov 2025
Withdrawal Update Form 1File: form 1 30-6-25.pdf27 Nov 2025
Withdrawal Update Form 2File: form 2 30-6-25.pdf27 Nov 2025
Withdrawal Update Form 3File: form-3 30-6-25.pdf27 Nov 2025
Form 1File: FORM 1 31-3-25.pdf15 Oct 2025
Form 2File: FORM 2 31-3-25.pdf15 Oct 2025
Form 3File: FORM 3 31-3-25.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-3-25.pdf15 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 upto sep vhr.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DEC24.pdf12 Feb 2025
Details of encumbrances concerned to FinanceFile: encumbrance financial jankalyan patsantha.pdf10 Feb 2025
Details of encumbrances concerned to LegalFile: encumbrance financial jankalyan patsantha.pdf10 Feb 2025
Other - FinanceFile: CHUK DURUSTI DAST - jankalyan_compressed (1).pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 ARCHITECT CERTIFICATE 31122024.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 30092024.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 ENGINEER CERTIFICATE 31122024.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD BOOKED INVENTRY 30092024.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD BOOKED INVENTRY 31122024.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 02-08-24.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cert 31032024.pdf3 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 30062024.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER FRON 2 VHR 31032024.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTFICAL 30062024.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventry.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventry 30062024.pdf3 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form -3 31032024.pdf3 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form -3 30062024.pdf3 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30092023.pdf16 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 31122023.pdf16 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30092023.pdf16 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31122023.pdf16 Mar 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD 30092023.pdf16 Mar 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD 31122023.pdf16 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE 30-9-2023.pdf9 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE 31-12-2023.pdf9 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 310323.pdf20 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 30062023.pdf20 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 31032023.pdf20 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 1-07-23.pdf20 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM -2A.pdf20 Sep 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD 310323.pdf20 Sep 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTRY.pdf20 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 VHR 31032023.pdf20 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 VHR 30062023.pdf20 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 VHR 31032023.pdf20 Sep 2023
Details of encumbrances concerned to FinanceFile: no encumbrance certificate - legal.pdf23 Jan 2023
Details of encumbrances concerned to LegalFile: no encumbrance certificate - legal.pdf23 Jan 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE FINANCIAL NEW.pdf20 Jan 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE FINANCIAL NEW.pdf20 Jan 2023
Copy of the legal title reportFile: declartion for plot copy_compressed.pdf11 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf3 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf3 Jan 2023
CERSAI detailsFile: undertaking.pdf3 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf3 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of intrest in other real estate organisation- madhukar panse.pdf3 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of intrest in other real estate organisation- dilip patil.pdf3 Jan 2023
Proforma of Allotment letterFile: MODEL FORM OF ALLOTMENT LETTER.pdf3 Jan 2023
Proforma of Agreement for saleFile: agreement to sale draft final with dispute resolition 2412023.pdf3 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT OREDER 34 REVISED.pdf3 Jan 2023
Deviation Report with respect to Allotment letterFile: no deviation certificate.pdf3 Jan 2023
Deviation Report with respect to model copy of AgreementFile: no deviation certificate AGREEMENT TO SALE (2)_compressed.pdf3 Jan 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
PANSE PATIL HARMONYP53100024897BEHIND PURVA GARDEN HOTEL, SangliMar 2020CompletedDec 2024Dec 2024

How this compares with Sangli

6%of this project is bookeddistrict median 16%
11%of Sangli projects moved their completion datethis one moved by 16 months
29%of Sangli registrations have lapsed or been cancelledthis one is on the register

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep VISHNU HARI REGENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP GHANSHYAM NAGAR790+ in Sangli

2 kmVISHNU HARI REGENCYCompleted 21Lapsed / revoked 12Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: AVANEESH BUILDCON LLP

AVANEESH BUILDCON LLP has 2 registrations on MahaRERA, including PANSE PATIL HARMONY and VISHNU HARI REGENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if VISHNU HARI REGENCY is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISHNU HARI REGENCY?

The registered promoter entity is AVANEESH BUILDCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISHNU HARI REGENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VISHNU HARI REGENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISHNU HARI REGENCY?

The professionals named in the filing: Architect: AMBER SHINDE; Engineer: VIKAS UDDHAV PATIL; Chartered Accountant: SHRINIWAS N BHOSALE; Chartered Accountant: BPCH AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISHNU HARI REGENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISHNU HARI REGENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISHNU HARI REGENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.