ReraGenieLog inGet a buyer report

Home / Browse projects / Sangli, Maharashtra / DECCAN KRISHNA

Registered No litigation declared Others project

DECCAN KRISHNA

By DECCAN PRAMOTORS

RG-MH-17223 · RERA P53100028351 · Last updated on MahaRERA portal: 21 Oct 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • No extension sought by the promoter; the date moved only under MahaRERA's automatic 4-month extension
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Oct 2026Possession promised1 month past this date
2 of 11Construction stages donefurthest along: Stilt Floor, 90%
62 of 107Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 205 documents Report an error

DECCAN KRISHNA is a Others project by DECCAN PRAMOTORS in Sangli, Maharashtra, registered with MahaRERA as P53100028351 on 18 Feb 2021. Possession was promised by 30 Oct 2026 and is now 1 months past that date. The completion date has moved by 4 months under MahaRERA's automatic 4-month extension for the West Asia conflict, which the promoter did not apply for. 45 of the 107 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameDECCAN KRISHNA
  • TypeOthers
  • Location
    • CTS NO 14375 NEAR BYPASS ROAD
    • SANGLI MADHVNAGAR HIGHWAY SANGLI
    • BY PASS ROAD
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100028351
  • ReraGenie IDRG-MH-17223

Builder

  • NameDECCAN PRAMOTORS
  • Entity typePartnership
  • GSTIN27AARFD1097M1ZS
  • Partnerschetan prakash chavan, PRIYA AVINASH ATTAL, snehal dhaval gore

Key dates

1 months past promisethis monthRegisteredFeb 2021First promiseJun 2026Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Feb 2021
  • Promised completion30 Oct 2026
  • Revised completionRevised to 30 Oct 2026 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed205 files

Current status

42%45 of 107 units booked
127.2%Work done, per cost certificate

Figures as on 21 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DECCAN KRISHNANA888819107

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

DECCAN KRISHNA: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor90%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered20
Open Space10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,800 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Oct 2026

Approvals and building plan

Sanctioning authoritysangli miraj kupwad municipal corporation
Permissible FSI4792.13
Proposed, not sanctioned2,487 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAMINARAYAN BLDG JAIHIND COLONY VISHRAMBAG SANGLI
Estimated costRs 7.98 cr
Cost incurredRs 10.15 cr
Work done127.21%
BuildingWingEstimatedIncurred
DECCAN KRISHNANARs 7.98 crRs 10.15 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAMIR GOKHALE
EngineerPRANAV KULKARNI
Engineersayyad abdul rauf abutahe
Chartered Accountantabhijit s pachhapure
PartnerRole in project
DECCAN PRAMOTORS-

Extensions1

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jun 2026 → Oct 2026

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Feb 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed205

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 205 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 30-9-2026.pdf21 Oct 2026
Withdrawal Update Form 2File: FORM 2 30-9-2026.pdf21 Oct 2026
Withdrawal Update Form 3File: FORM 3 30-9-2026.pdf21 Oct 2026
Form 1File: form1.pdf31 Aug 2026
Form 2File: Form 2 - 31-3-24.pdf31 Aug 2026
Form 3File: form3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Aug 2026
Form 1File: form1.pdf31 Aug 2026
Form 2File: Form 2 - 30-6-24.pdf31 Aug 2026
Form 3File: form3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Aug 2026
Form 1File: Form 1 - .pdf31 Aug 2026
Form 2File: Form 2 - 30-09-24.pdf31 Aug 2026
Form 3File: form3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Aug 2026
Form 1File: Form 1 - 31-12-24.pdf31 Aug 2026
Form 2File: FORM 2.pdf31 Aug 2026
Form 3File: FORM 3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf31 Aug 2026
Form 1File: Form 1 - 31-03-25.pdf31 Aug 2026
Form 2File: FORM2 31-03-2025.pdf31 Aug 2026
Form 3File: FORM 3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf31 Aug 2026
Form 1File: Form 1 - 30-06-25.pdf31 Aug 2026
Form 2File: FORM 2 pdf.pdf31 Aug 2026
Form 3File: FORM 3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: SOL UNSOLD.pdf31 Aug 2026
Form 1File: Form 1 - 30-09-25.pdf31 Aug 2026
Form 2File: FORM2 30-09-2025.pdf31 Aug 2026
Form 3File: form 3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Aug 2026
Form 1File: Form 1 - 31-12-25.pdf31 Aug 2026
Form 2File: FORM2 31-12-2025.pdf31 Aug 2026
Form 3File: form 3.pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf31 Aug 2026
Form 1File: Form 1 - 31-03-26.pdf31 Aug 2026
Form 2File: FORM 2 31-03-2026.pdf31 Aug 2026
Form 3File: FORM 3 .pdf31 Aug 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf31 Aug 2026
Form 2A (FY 2020-2021)File: Form 2A (2020-21).pdf29 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A (2021-22).pdf29 Aug 2026
Form 2A (FY 2022-2023)File: Form 2A (2022-23).pdf29 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A(2023-24).pdf29 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A(2024-25).pdf29 Aug 2026
Form 2A (FY 2026-2027)File: Form 2A (2026-27).pdf29 Aug 2026
Form 5 (FY 2020-2021)File: Form 5(2020-21).pdf28 Aug 2026
Form 5 (FY 2021-2022)File: Form 5(2021-22).pdf28 Aug 2026
Form 5 (FY 2022-2023)File: Form 5(2022-23).pdf28 Aug 2026
Form 5 (FY 2023-2024)File: Form 5(2023-24).pdf28 Aug 2026
Form 5 (FY 2024-2025)File: Form 5(2024-25).pdf28 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf26 Aug 2026
Form 1File: form1 (1).pdf25 Aug 2026
Form 2File: FORM 2.pdf25 Aug 2026
Form 3File: FORM 3 CA.pdf25 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold 1.pdf25 Aug 2026
Form 5 (FY 2025-2026)File: ANNUAL RETURN FORM 5_FY 2025-26.pdf25 Aug 2026
Form 1File: form1.pdf24 Aug 2026
Form 2File: form2.pdf24 Aug 2026
Form 3File: form3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026
Form 1File: form1.pdf24 Aug 2026
Form 2File: form 2.pdf24 Aug 2026
Form 3File: form3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026
Form 1File: form 1.pdf24 Aug 2026
Form 2File: form 2.pdf24 Aug 2026
Form 3File: form3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026
Form 1File: form 1.pdf24 Aug 2026
Form 2File: form 2.pdf24 Aug 2026
Form 3File: form3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026
Form 1File: form1.pdf24 Aug 2026
Form 2File: form2.pdf24 Aug 2026
Form 3File: form 3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026
Form 1File: form 1.pdf24 Aug 2026
Form 2File: form2.pdf24 Aug 2026
Form 3File: form3.pdf24 Aug 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf24 Aug 2026

How this compares with Sangli

42%of this project is bookeddistrict median 14%
12%of Sangli projects moved their completion datethis one moved by 4 months
29%of Sangli registrations have lapsed or been cancelledthis one is on the register

Computed across the 800+ Sangli projects on ReraGenie, from their own filings.

Keep DECCAN KRISHNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BY PASS ROAD800+ in Sangli

2 kmDECCAN KRISHNACompleted 51Lapsed / revoked 36Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: DECCAN PRAMOTORS

DECCAN PRAMOTORS has 1 registration on MahaRERA, including DECCAN KRISHNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if DECCAN KRISHNA is delayed beyond 30 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DECCAN KRISHNA?

The registered promoter entity is DECCAN PRAMOTORS, a partnership as per the filing. Its GSTIN 27AARFD1097M1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DECCAN KRISHNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DECCAN KRISHNA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DECCAN KRISHNA?

The professionals named in the filing: Architect: SAMIR GOKHALE; Engineer: PRANAV KULKARNI; Engineer: sayyad abdul rauf abutahe; Chartered Accountant: abhijit s pachhapure. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DECCAN KRISHNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DECCAN KRISHNA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DECCAN KRISHNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.