Home / Browse projects / Sangli, Maharashtra / PANSE PATIL HARMONY
PANSE PATIL HARMONY
RG-MH-16101 · RERA P53100024897 · Last updated on MahaRERA portal: 6 Oct 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PANSE PATIL HARMONY is a Residential / Group Housing project by AVANEESH BUILDCON LLP in Sangli, Maharashtra, registered with MahaRERA as P53100024897 on 9 Mar 2020. The registration is recorded completed; possession was promised by 30 Dec 2024.
At a glance
Project
- NamePANSE PATIL HARMONY
- TypeResidential / Group Housing
- Location
- BEHIND NEW COURT BUILDING WANLESSWADI
- BEHIND PURVA GARDEN HOTEL
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416414
- Pincode416414
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100024897
- ReraGenie IDRG-MH-16101
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Mar 2020
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed34 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PANSE PATIL HARMONY | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
PANSE PATIL HARMONY: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIJAYKUMAR B PATIL |
| Engineer | SURESH G SAKHARE |
| Chartered Accountant | SHRINIWAS N BHOSALE |
| Partner | Role in project |
|---|---|
| AVANEESH BUILDCON LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Feb 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Feb 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 14 Feb 2023
Documents filed34
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf | 6 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22 23.pdf | 6 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: consulting engineer certificate.pdf | 21 Feb 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: architect certificate.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 19-20.pdf | 19 Feb 2023 |
| Other - FinanceFile: letter for rera.pdf | 19 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: bhogwata pramanpatra completion certificate.pdf | 14 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3 31321.pdf | 1 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 31322_compressed.pdf | 1 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20 21.pdf | 1 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21 22.pdf | 1 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 30 Aug 2022 |
| Declaration about Commencement CertificateFile: COMMENCEMNT CERTIFICATE.pdf | 13 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: BOOKED INVENTORY.pdf | 13 Apr 2022 |
| Building plan approvalFile: DRAWING SIXTH FLOOR PLAN B W.pdf | 18 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: DRAWING SIXTH FLOOR PLAN B W.pdf | 18 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: BANDKAM PARVANA SIXTH FLOOR.pdf | 18 Mar 2022 |
| Proforma of Allotment letterFile: agreement to sale format new for rera update.pdf | 12 Nov 2021 |
| PAN CardFile: pancard 28082019 AVANEESH.pdf | 29 Sep 2021 |
| Details of encumbrancesFile: INCUMBRANCE CERTIFICATE.pdf | 26 Jul 2021 |
| Declaration about Commencement CertificateFile: COMMENCEMNT CERTIFICATE.pdf | 26 Jul 2021 |
| Building plan approvalFile: DRAWING bw.pdf | 22 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: DRAWING bw.pdf | 22 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CERTIFICATE b w.pdf | 22 Jul 2021 |
| Layout approvalFile: MOJANI NAKASHA.pdf | 29 Feb 2020 |
| Building plan approvalFile: BUILDING DRG.pdf | 29 Feb 2020 |
| Copy of the legal title reportFile: LEAGLE SCRUTINY REPORT.pdf | 29 Feb 2020 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf | 29 Feb 2020 |
| Copy of Layout Approval (in case of layout)File: MOJANI NAKASHA.pdf | 29 Feb 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING DRG.pdf | 29 Feb 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTI.pdf | 29 Feb 2020 |
| Declaration in FORM BFile: FORM B.pdf | 29 Feb 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf | 29 Feb 2020 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 29 Feb 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 34 filed documents as one ZIP, foldered, with a manifest
Keep PANSE PATIL HARMONY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BEHIND PURVA GARDEN HOTEL790+ in Sangli
Filed coordinates, straight-line distance. 93 registered projects within 2 km.
GOVIND ICON
G.K. ASSOCIATES
SAFFRON CITY
SAFFRON INFRA
ANANDVAN
MILESTONE BUILDERS
PLATINUM PLAZA
ASHOK BABGONDA PATIL
Jeevan Anand
SMS LIFE SPACE PRIVATE LIMITED
SHILWANT KSHITIJ
VINAYAK MAHADEV SHILWANT
See every Sangli project, with the district possession charts
Builder: AVANEESH BUILDCON LLP
AVANEESH BUILDCON LLP has 2 registrations on MahaRERA, including PANSE PATIL HARMONY and VISHNU HARI REGENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What are my rights if PANSE PATIL HARMONY is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PANSE PATIL HARMONY?
The registered promoter entity is AVANEESH BUILDCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PANSE PATIL HARMONY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PANSE PATIL HARMONY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PANSE PATIL HARMONY?
The professionals named in the filing: Architect: VIJAYKUMAR B PATIL; Engineer: SURESH G SAKHARE; Chartered Accountant: SHRINIWAS N BHOSALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PANSE PATIL HARMONY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback