ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Vira Avenue

Registered No litigation declared Residential / Group Housing project

Vira Avenue

By Vira Realty India Private Limited

RG-MH-18365 · RERA P51800076751 · Last updated on MahaRERA portal: 15 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
7 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 95%
57 of 85Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

Vira Avenue is a Residential / Group Housing project by Vira Realty India Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800076751 on 25 Jun 2024. Possession is promised by 31 Dec 2026. 28 of the 85 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameVira Avenue
  • TypeResidential / Group Housing
  • Location
    • Ram Mandir Road & Tilak Road
    • Vile Parle (E)
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800076751
  • ReraGenie IDRG-MH-18365

Builder

  • NameVira Realty India Private Limited
  • Entity typeCompany
  • CINU70100MH2018PTC312996
  • GSTIN27AAGCV5477P1ZD
  • DirectorsJash Praful Vira, Ashwin Lakamshi Satra

Key dates

this monthRegisteredJun 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jun 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed49 files

Current status

33%28 of 85 units booked
65.0%Work done, per cost certificate

Figures as on 15 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vira Avenue Wing ANA3238139
Vira Avenue Wing BNA111046046

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

Vira Avenue Wing A59%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Vira Avenue Wing B50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 15 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes32%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed54

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots54
Closed/Covered54
BuildingClosed/CoveredTotal
Vira Avenue Wing A99
Vira Avenue Wing B4545

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area776 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024
LandownerVillageDistrict
Trimurti Krupa Co-operative Housing Society LimiteVileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI5271.07
Proposed, not sanctioned2,059 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1 and 2, Palai Plaza, CHS, Mumbai Maharashtra-400 014
Estimated costRs 19.72 cr
Cost incurredRs 12.83 cr
Work done65.04%
BuildingWingEstimatedIncurred
Vira Avenue Wing ANARs 9.86 crRs 6.41 cr
Vira Avenue Wing BNARs 9.86 crRs 6.41 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectH. M. Jhaveri & Sons
EngineerM/s Unisteps Consulting Pvt. Ltd
Chartered AccountantCA Amug Ghule
Chartered AccountantSachin K. Mishra & Co
Chartered AccountantAniruddha Sonar & Associates
Chartered AccountantR H Pothiwal & Associates
PartnerRole in project
Vira Realty India Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Mar 26.pdf15 May 2026
Withdrawal Update Form 2File: Form 2_Mar 26.pdf15 May 2026
Withdrawal Update Form 3File: Form 3_Mar 26.pdf15 May 2026
Withdrawal Update Form 1File: Architect Certificate_Vira Avenue_SEP 2025.pdf14 Mar 2026
Withdrawal Update Form 1File: Architect Certificate_Vira Avenue_Dec 25.pdf14 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate_Vira Avenue_SEPT - 2025.pdf14 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate_Vira Avenue_Dec 25.pdf14 Mar 2026
Withdrawal Update Form 3File: CA Certificate_Vira Realty_Sept 2025 sign.pdf14 Mar 2026
Withdrawal Update Form 3File: CA Certificate_Vira Realty_Dec 25 sign.pdf14 Mar 2026
Withdrawal Update Form 1File: Architect Certificate_Vira Avenue_June 25.PDF15 Oct 2025
Withdrawal Update Form 1File: Architect Certificate_Vira Avenue_June 25.PDF15 Oct 2025
Withdrawal Update Form 1File: Architect Certificate_Vira Avenue_June 25.PDF15 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate_Vira Avenue_June 25.pdf15 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate_Vira Avenue_June 25.pdf15 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate_Vira Avenue_June 25.pdf15 Oct 2025
Withdrawal Update Form 3File: CA Certificate_Vira Avenue_Jun 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: CA Certificate_Vira Avenue_Jun 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: CA Certificate_Vira Avenue_Jun 2025.pdf15 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Vira Avenue - Jun 24.pdf13 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Vira Avenue - Sep 24.pdf13 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Vira Avenue - Jun 24.pdf13 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Vira Avenue - Sep 24.pdf13 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Vira Realty_30 June.pdf11 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Vira Realty_30 Sept.pdf11 Dec 2024
Details of encumbrances concerned to FinanceFile: EC-Finance_ Legal.pdf19 Jun 2024
Details of encumbrances concerned to LegalFile: EC-Finance_ Legal.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Vira Realty.pdf16 Jun 2024
Other - TechnicalFile: Annexure A_Declaration-cum -Undertaking.pdf16 Jun 2024
CERSAI detailsFile: CERSAI Details.pdf5 Jun 2024
Layout approvalFile: IOD Sancation Letter.pdf19 May 2024
Layout approvalFile: IOD Sancation plan - converted.pdf19 May 2024
Building plan approvalFile: IOD Sancation plan - converted.pdf19 May 2024
PAN CardFile: Company Pan.pdf19 May 2024
Copy of the legal title reportFile: Legal Title Report Trimurti.pdf19 May 2024
Details of encumbrances concerned to FinanceFile: EC-Legal.pdf19 May 2024
Details of encumbrances concerned to LegalFile: EC-Legal.pdf19 May 2024
Copy of Layout Approval (in case of layout)File: IOD Sancation Letter.pdf19 May 2024
Copy of Layout Approval (in case of layout)File: IOD Sancation plan - converted.pdf19 May 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Sancation plan - converted.pdf19 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC_signed.pdf19 May 2024
Declaration about Commencement CertificateFile: D Format.pdf19 May 2024
Declaration in FORM BFile: vira realty india pvt lit B Form.pdf19 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Intrest-Jash.pdf19 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Intrest-Ashwin.pdf19 May 2024
Proforma of Allotment letterFile: Allotment Letter.pdf19 May 2024
Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf19 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf19 May 2024
Deviation Report with respect to Allotment letterFile: Devetion Report of Allotment Letter.pdf19 May 2024
Deviation Report with respect to model copy of AgreementFile: Devetion Report of AFS.pdf19 May 2024

How this compares with Mumbai Suburban

33%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vira Avenue on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle (E)6,700+ in Mumbai Suburban

2 kmVira AvenueCompleted 137Lapsed / revoked 79Other 214Dot size: filed unitsN

Filed coordinates, straight-line distance. 430 registered projects within 2 km.

Builder: Vira Realty India Private Limited

Vira Realty India Private Limited has 1 registration on MahaRERA, including Vira Avenue. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Vira Avenue is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vira Avenue?

The registered promoter entity is Vira Realty India Private Limited, a company as per the filing. Its CIN U70100MH2018PTC312996 and GSTIN 27AAGCV5477P1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vira Avenue?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vira Avenue?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vira Avenue?

The professionals named in the filing: Architect: H. M. Jhaveri & Sons; Engineer: M/s Unisteps Consulting Pvt. Ltd; Chartered Accountant: CA Amug Ghule; Chartered Accountant: Sachin K. Mishra & Co; Chartered Accountant: Aniruddha Sonar & Associates; Chartered Accountant: R H Pothiwal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vira Avenue?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vira Avenue. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vira Avenue to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.