ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / VIP RESIDENCY I

Registered No litigation declared Residential / Group Housing project

VIP RESIDENCY I

By V DAS INFRA PROJECTS

RG-MH-30455 · RERA P50500049523 · Last updated on MahaRERA portal: 1 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
7 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
6 of 15Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

VIP RESIDENCY I is a Residential / Group Housing project by V DAS INFRA PROJECTS in Nagpur, Maharashtra, registered with MahaRERA as P50500049523 on 15 Feb 2023. Possession is promised by 31 Dec 2027. 9 of the 15 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameVIP RESIDENCY I
  • TypeResidential / Group Housing
  • Location
    • Nagpur Road
    • Vihirgaon Nagpur
    • Vihirgaon
    • Nagpur (Rural)
    • Nagpur
    • 441204
  • Pincode441204
  • RERA no.P50500049523
  • ReraGenie IDRG-MH-30455

Builder

  • NameV DAS INFRA PROJECTS
  • Entity typePartnership
  • PartnerSanjay Yashawantrao Dhawale

Key dates

this monthRegisteredFeb 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed119 files

Current status

60%9 of 15 units booked
99.1%Work done, per cost certificate

Figures as on 1 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIP RESIDENCY INA6515015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

VIP RESIDENCY I: 86% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 1 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,020 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Nov 2025
LandownerVillageDistrict
Sanjay DhawaleNagpur (M Corp.)Nagpur
Hemant GawandeNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityOffice of The Nagpur Metropolitan Region Development Authority
Permissible FSI1020.45
Proposed, not sanctioned1,020 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNandanwan Nagpur
Estimated costRs 4.03 cr
Cost incurredRs 3.99 cr
Work done99.09%
BuildingWingEstimatedIncurred
VIP RESIDENCY INARs 2.01 crRs 2.00 cr
-NARs 2.01 crRs 2.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVinit Shrivastava
EngineerVinit Shrivastava
EngineerRavindra G Gharde
Chartered AccountantB K Sindhwani
Chartered AccountantRishi Lashkare
Chartered AccountantRavindra Lashkare
PartnerRole in project
V DAS INFRA PROJECTS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: VIP Residency form 1 march 2026.pdf1 May 2026
Withdrawal Update Form 2File: VIP Residency form2 march 2026..pdf1 May 2026
Withdrawal Update Form 3File: VIP Residency form 3 march 2026.pdf1 May 2026
Withdrawal Update Form 1File: Form 1 - Architects cwertificate - Dec 25 (2).pdf6 Mar 2026
Withdrawal Update Form 2File: VIP Residency 1 - Form 2 - sept 2025.pdf6 Mar 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - Dec 25.pdf6 Mar 2026
Form 2A (FY 2022-2023)File: Form 2A - 2022 - 2023.pdf6 Mar 2026
Form 2A (FY 2023-2024)File: Form 2A - VIP 2023 - 2024.pdf6 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A - VIP 2024 - 2025.pdf6 Mar 2026
Form 5 (FY 2022-2023)File: Form 5 2022-23.pdf25 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24.pdf25 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 2024-25.pdf25 Feb 2026
Form 2File: VIP Residency 1 - Form 2 - march 2025.pdf24 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - March 2025.pdf24 Feb 2026
Form 3File: VIP Residency 1 - Form 3 - march 2025_compressed.pdf24 Feb 2026
Form 1File: VIP Residency 1 - Form 1 - march 2025.pdf24 Feb 2026
Withdrawal Update Form 1File: VIP RESIDENCY -1 Form 1 - june 25.pdf24 Feb 2026
Withdrawal Update Form 1File: Form 1 - Architects certificate - Sept 25.pdf24 Feb 2026
Withdrawal Update Form 1File: VIP RESIDENCY -1 Form 1 - june 25.pdf24 Feb 2026
Withdrawal Update Form 1File: VIP Residency 1 - Form 1 - sept 2025.pdf24 Feb 2026
Withdrawal Update Form 2File: VIP RESIDENCY -1 Form 2 - june 25.pdf24 Feb 2026
Withdrawal Update Form 2File: VIP RESIDENCY -1 Form 2 - june 25.pdf24 Feb 2026
Withdrawal Update Form 2File: VIP RESIDENCY -1 Form 2 - june 25.pdf24 Feb 2026
Withdrawal Update Form 2File: VIP Residency 1 - Form 2 - sept 2025.pdf24 Feb 2026
Withdrawal Update Form 3File: VIP RESIDENCY -1 Form 3 - june 25.pdf24 Feb 2026
Withdrawal Update Form 3File: VIP RESIDENCY -1 Form 3 - june 25.pdf24 Feb 2026
Withdrawal Update Form 3File: VIP RESIDENCY -1 Form 3 - june 25.pdf24 Feb 2026
Withdrawal Update Form 3File: VIP Residency 1 - Form 3 - sept 2025.pdf24 Feb 2026
Form 1File: Form 1 - Arch Certificate - March 2023.pdf24 Dec 2025
Form 2File: Form 2 Engineer Certificate - March 2023.pdf24 Dec 2025
Form 3File: Form 3 CA Certificate - March 2023.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - March 2023.pdf24 Dec 2025
Form 1File: Form 1 Arch Certificate - June 2023.pdf24 Dec 2025
Form 2File: Form 2 Engineer Certificate - June 2023.pdf24 Dec 2025
Form 3File: Form 3- CA Certificate June 2023.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discloser of Inventory - June 2023.pdf24 Dec 2025
Form 1File: FORM 1 - Arch Certificate - Sept 2023.pdf24 Dec 2025
Form 2File: FORM 2 - Engineer Certificate - Sept 2023.pdf24 Dec 2025
Form 3File: Form 3 - VIP - Sept 2023.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discloser of Inventory - Sept 2023.pdf24 Dec 2025
Form 1File: Architects certificate.pdf24 Dec 2025
Form 2File: Engineer certificate.pdf24 Dec 2025
Form 3File: Form-3 Q-3.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discloser.pdf24 Dec 2025
Form 1File: Form 1 Arch Certificate Scan.pdf24 Dec 2025
Form 2File: Engineer Certificate Scan.pdf24 Dec 2025
Form 3File: Form 3 CA certificate Scan.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discloser of Sold Inventory Scan.pdf24 Dec 2025
Form 1File: VIP Residency - Form 1 - June 2024.pdf24 Dec 2025
Form 2File: VIP Residency - Form 2 - June 2024.pdf24 Dec 2025
Form 3File: VIP Residency - Form 3 - June 2024.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: VIP Residency - Disclosure - June 2024.pdf24 Dec 2025
Form 1File: VIP Residency - Form 1 - September 2024.pdf24 Dec 2025
Form 2File: VIP Residency - Form 2 - September 2024.pdf24 Dec 2025
Form 3File: VIP Residency - Form 3 - September 2024.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: VIP Residency - Disclosure - September 2024.pdf24 Dec 2025
Form 1File: VIP Residency 1 - Form 1 - December 2024.pdf24 Dec 2025
Form 2File: VIP Residency 1 - Form 2 - December 2024.pdf24 Dec 2025
Form 3File: VIP Residency 1 - Form 3 - December 2024.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: VIP Residency 1 - Disclosure - December 2024.pdf24 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIP Residency 1 - Form 1 - December 2024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VIP Residency 1 - Form 3 - December 2024_compressed.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIP Residency 1 - Form 2 - December 2024.pdf25 Mar 2025
Disclosure of sold/ booked inventoryFile: VIP Residency 1 - Disclosure - December 2024.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIP Residency - Form 1 - June 2024.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIP Residency - Form 1 - September 2024.pdf5 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VIP Residency - Form 3 - June 2024_compressed.pdf5 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VIP Residency - Form 3 - September 2024_compressed.pdf5 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIP Residency - Form 2 - June 2024.pdf5 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIP Residency - Form 2 - September 2024.pdf5 Dec 2024
Disclosure of sold/ booked inventoryFile: VIP Residency - Disclosure - June 2024.pdf5 Dec 2024
Disclosure of sold/ booked inventoryFile: VIP Residency - Disclosure - September 2024.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate Scan.pdf25 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Scan.pdf25 May 2024
Disclosure of sold/ booked inventoryFile: Discloser of Sold Inventory Scan.pdf25 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate Scan 1.pdf25 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate June 2023.pdf20 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Arch Certificate - Sept 2023.pdf19 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf25 Jan 2024

How this compares with Nagpur

60%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIP RESIDENCY I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vihirgaon Nagpur2,800+ in Nagpur

Builder: V DAS INFRA PROJECTS

V DAS INFRA PROJECTS has 1 registration on MahaRERA, including VIP RESIDENCY I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if VIP RESIDENCY I is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIP RESIDENCY I?

The registered promoter entity is V DAS INFRA PROJECTS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIP RESIDENCY I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIP RESIDENCY I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIP RESIDENCY I?

The professionals named in the filing: Architect: Vinit Shrivastava; Engineer: Vinit Shrivastava; Engineer: Ravindra G Gharde; Chartered Accountant: B K Sindhwani; Chartered Accountant: Rishi Lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIP RESIDENCY I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIP RESIDENCY I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIP RESIDENCY I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.