Home / Browse projects / Mumbai Suburban, Maharashtra / VICINIA

Registration lapsed No litigation declared Residential / Group Housing project

VICINIA

By FORBES & COMPANY LIMITED

RG-MH-12507 · RERA P51800002564 · Last updated on MahaRERA portal: 9 Oct 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 58 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
60 of 88Construction stages doneacross 8 buildings; furthest along: Installation of Lifts, 97%
58Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

VICINIA is a Residential / Group Housing project by FORBES & COMPANY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002564 on 1 Aug 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 12 months from the original filing. 58 complaints are on record with the regulator.

At a glance

Project

  • NameVICINIA
  • TypeResidential / Group Housing
  • Location
    • Powai Vihar Road
    • Chandivali Andheri East
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002564
  • ReraGenie IDRG-MH-12507

Builder

  • NameFORBES & COMPANY LIMITED
  • Entity typeCompany
  • Managing DirectorMAHESH CHELARAM TAHILYANI
  • Company SecretoryPANKAJ KHATTAR

Key dates

40 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2022)
  • Buildings8 building records
  • Documents filed120 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA250000
WING BNA250000
WING CNA260000
WING DNA260000
WING FNA260000
WING ENA260000
WING GNA260000
WING HNA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

60 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Installation of Lifts, at 97%.

WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
WING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
WING D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.96%
WING F90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.91%
WING E66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises56%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.61%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.38%
WING G67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises58%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.73%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.33%
WING H62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.54%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.29%

Progress on shared amenities17

As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes76%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes83%
Storm Water DrainsYes63%
Landscaping & Tree PlantingYes60%
Street LightingYes0%
Community BuildingsYes35%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes77%
Fire protection and fire safety requirementsYes63%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes62%
Open ParkingYes100%
Community Buildings Club HouseYes35%
Covered car parkingsYes100%

Parking filed1124

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,124
Closed/Covered955
Open Space169
BuildingClosed/CoveredOpen SpaceTotal
WING A9817115
WING B9817115
WING C12622148
WING D12623149
WING F14926175
WING E14526171
WING G10719126
WING H10619125

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,264 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
VIDEOCON REALTYAND INFRASTRUCTURES LTDMumbai CityMumbai City
PAIKAR REAL ESTATE PRIVATE LIMITEDMumbai CityMumbai City
PAIKAR REAL ESTATE PRIVATE LTDMumbai CityMumbai City

Approvals and building plan

Permissible FSI60669.0
Proposed, not sanctioned31,929 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJeevan Prakash Building Sir P M Road Fort Mumbai 01

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBRIGHTON ARCHITECTS INDIA PVT LTD
EngineerASCENT STRUCTURAL ENGINEERS PVT LTD
Chartered AccountantVindochandra R. Shah & Co.
PartnerRole in project
FORBES & COMPANY LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012132Jun 2022 → Jun 2023

Reason as filed by the promoterWe are hereby submitting following documents for consideration of the Authority: (a) Commencement Certificate is enclosed under Tab No. 1 i.e., "Copy of the permission/ approval of competent authority". (b) Approval Letter along with project approved plans is enclosed under Tab No. 2 i.e., i.e., "Copy of the permission/ approval of competent authority". (c) 'Form E' Extension Application along with 'Annexure A' (State of existing development works), and Annexure 'C' (Existing RERA Registration Certificate). The said document is enclosed under Tab No. 3 i.e., "Others". (d) Annexure 'B' (Explana

Complaints filed with MahaRERA58

Case no.ComplainantRespondentFiled
CC006000000396420ASHWIN SADASHIVA POOJARIFORBES & COMPANY LIMITED25/06/2023
CC006000000197165Messers Soumya through Proprietor Mrs. Sonal Shukla and Mr. Santosh ShuklaM/s. Shapoorji Pallonji Real Estate and M/s. Forbes & Co Ltd & M/s. Paikar Real Estates Pvt Ltd06/06/2021
CC006000000210251Hemang Ramesh Oza & Preeti Hemang OzaForbes & Co Ltd04/03/2022
CC006000000195085Ravee DattaVideocon Realty & Infrastructure Ltd30/11/2020
CC006000000195235Mr. Anuj NigamVideocon Realty & Infrastructure ltd16/12/2020
CC006000000196395Moon Moon BasuVideocon Realty and Infrastructure Ltd.18/03/2021
CC006000000196706Vineet SamuelVideocon Realty and Infrastructure Limited13/04/2021
CC006000000196777Faiyaz Wajid KhanVideocon Realty and Infrastructure Limited21/04/2021
CC006000000196781Mr. Kunal KrishnaVideocon Realty and Infrastructure Limited21/04/2021
CC006000000196934Rajesh SadaranganiVideocon Realty and Infrastructure Limited10/05/2021
CC006000000195107Nitin AgrawalForbes and Co02/12/2020
CC006000000195226Chandrashekar S ChilweriForbes and Co14/12/2020
CC006000000195296Vishal Katkoria and AnrForbes and Co21/12/2020
CC006000000195326Shreeshkumar R Bubna and AnrForbes and Co31/12/2020
CC006000000195329Sandeep BhattForbes and Co21/12/2020
CC006000000198138P P PillaiPAIKAR REAL ESTATES PRIVATE LIMITED07/09/2021
CC006000000210419Pravin BaidVideocon Realty and Infrastructure Limited19/03/2022
CC006000000210420Seema BaidVideocon Realty and Infrastructure Limited19/03/2022
CC006000000241298Amit ChaudharyVideocon Realty and Infrastructure Limited04/06/2022
CC006000000251511Karan KeswaniForbes & Company Limited19/06/2022
CC006000000408215Deepti KapoorAkash Khanwalkar02/08/2024
CC006000000334059Partha PainVideocon Realty and Infrastructure Ltd21/01/2023
CC006000000408315Nikita UnawaneForbes and Company Limited02/12/2023
CC006000000428956Shivji Bhachu BhushanForbes & Company Ltd29/01/2024
CC006000000428980MALLIKA JAYANT KESHKAMATFORBES & COMPANY LIMITED01/02/2024
CC006000000429421Ketaki Manohar NarkarShapoorji PallonGroup12/03/2024
CC12401000Gaurav KurhadeFORBES & COMPANY LIMITED03/12/2024
CC12503397Laltu PoreFORBES & COMPANY LIMITED23/09/2025
CC12503591Vivek SonejaFORBES & COMPANY LIMITED08/10/2025
CC12503927Sumit AgarwalFORBES & COMPANY LIMITED08/11/2025
CC12600080Ralph Antony DragoFORBES & COMPANY LIMITED05/01/2026
CC12600093Rahul PramanickFORBES & COMPANY LIMITED06/01/2026
CC12600111Prasenjit Pramil DebFORBES & COMPANY LIMITED07/01/2026
CC12600262Yojana Dayanand DhabadeFORBES & COMPANY LIMITED15/01/2026
CC12600346Utsav MistryFORBES & COMPANY LIMITED18/01/2026
CC12600501Eshan ahluwaliaFORBES & COMPANY LIMITED28/01/2026
CC12600747Gaurish KarekarFORBES & COMPANY LIMITED09/02/2026
CC12600970Fadia Meher RaquibFORBES & COMPANY LIMITED22/02/2026
CC12601125Vikas YadavFORBES & COMPANY LIMITED02/03/2026
CC12601141Pooja Harshit KunderFORBES & COMPANY LIMITED02/03/2026
CC12601282Shubham Narayan GuptaFORBES & COMPANY LIMITED09/03/2026
CC12601286Mithil SrivastavaFORBES & COMPANY LIMITED09/03/2026
CC12601448Bhavesh K RabadiyaFORBES & COMPANY LIMITED15/03/2026
CC12601530Kalyankumar Chanabasappa KubsadFORBES & COMPANY LIMITED20/03/2026
CC12601683Krishna Vasudeo PatilFORBES & COMPANY LIMITED24/03/2026
CC12601961Shanice Sunil ShresthaFORBES & COMPANY LIMITED03/04/2026
CC12601963Gopal SinghFORBES & COMPANY LIMITED03/04/2026
CC12602016Vemuri Venkata RamanaFORBES & COMPANY LIMITED05/04/2026
CC12602435Abhijit BangudeFORBES & COMPANY LIMITED26/04/2026
CC12602796Mufaddal Khozema TinmakerFORBES & COMPANY LIMITED13/05/2026
CC12603080Anil Kumar PandeyFORBES & COMPANY LIMITED24/05/2026
CC12603206Surendra Pratap ShuklaFORBES & COMPANY LIMITED28/05/2026
CC12603237Rajesh Raghunath KhanvilkarFORBES & COMPANY LIMITED29/05/2026
CC12603240Md Rafik Abdul Ajij ShaikhFORBES & COMPANY LIMITED29/05/2026
CC12603422Vikas BhasinFORBES & COMPANY LIMITED03/06/2026
CC12603647Ganesh Anant ShetyeFORBES & COMPANY LIMITED12/06/2026
CC12603739Pallavi PathakFORBES & COMPANY LIMITED17/06/2026
CC12603871Anup Kumar AgrawalFORBES & COMPANY LIMITED22/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Jul 2024

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Vicinia (Forbes)- Form 5- FY 2023-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Vicinia (Paikar)- Form 5- FY 2023-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Vicinia (Forbes)- Form 5- FY 2023-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Vicinia (Paikar)- Form 5- FY 2023-24.pdf9 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Vicinia OC- Phase 1.pdf12 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Vicinia OC- Phase 2.pdf12 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Paikar- Form 5 (FY 22-23).pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Forbes- Form 5 (FY 22-23).pdf30 Sep 2023
Details of encumbrancesFile: Paikar_ Encumbrance Certificate.pdf9 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PAIKAR - Physical progress - 31 - 12 - 2022.pdf21 Jul 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Vicnia- Status of Society Formation- May 2023.pdf11 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Vicinia- Revalidated CC upto 27 Feb 2024.pdf19 Apr 2023
Declaration about Commencement CertificateFile: Declaration under CC- Vicinia.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PAIKAR - Physical progress - 30 - 09 - 2022.pdf14 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PAIKAR - Physical progress - 31 - 12 - 2022.pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: Forbes- Inventory Report- Sept 2022 (reduced).pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: PAIKAR - Inventory data - 30-09-2022.pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: Forbes- Inventory Report- Dec 2022 (reduced).pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: PAIKAR - Inventory data - 31 -12 - 2022.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Paikar RERA Certificate FY2020-21 - Final.pdf3 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Vicinia- Sept 2022 (reduced).pdf2 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Vicinia- Sept 2022.pdf2 Jan 2023
Certificates of CA (Form 3)File: Form 3- Vicinia- Sept 2022 (reduced).pdf2 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Vicinia- June 2022.pdf30 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Vicinia- June 2022.pdf30 Sep 2022
Certificates of CA (Form 3)File: Form-3 VICINIA Consolidated Jun'2022.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Forbes- Form 5- FY 21-22.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Paikar- Form 5- FY 21-22.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Paikar Physical Report- June 2022.pdf20 Jul 2022
Disclosure of sold/ booked inventoryFile: Paikar- Inventory Data 30-06-2022 (reduced).pdf20 Jul 2022
Declaration about Commencement CertificateFile: Format-D- Declaration under CC- Vicinia.pdf27 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Vicinia- Mar'22-compressed.pdf27 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Vicinia- Mar'22-compressed.pdf27 Jun 2022
Disclosure of sold/ booked inventoryFile: Forbes- Disclosure of sold inventory (reduced).pdf27 Jun 2022
Certificates of CA (Form 3)File: CA_RERA Consolidated Q4-Mar 22_compressed.pdf27 Jun 2022
Certificates of CA (Form 3)File: Vicinia- Financial Progress Report- Mar'22.pdf27 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Vicinia- CC valid upto 27th Feb 2022.pdf7 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Vicinia- Revalidated CC upto 27th Feb 2023.pdf7 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vicinia- Physical Progress Report- Mar'22.pdf7 Jun 2022
Disclosure of sold/ booked inventoryFile: Paikar- Disclosure of sold Inventory- Mar 22 (reduced).pdf7 Jun 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Vicnia- Status of Society Formation- Mar'22.pdf14 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vicinia- Form 1- Dec 21 (signed) - reduced size.pdf10 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vicinia- Form 2- Dec 21 (signed) - reduced size.pdf10 Mar 2022
CERSAI detailsFile: Paikar- CERSAI Report (latest).pdf10 Mar 2022
Certificates of CA (Form 3)File: Vicinia- CA Certificate-1.pdf18 Feb 2022
Certificates of CA (Form 3)File: Vicinia- CA Certificate-2.pdf18 Feb 2022
Certificates of CA (Form 3)File: Vicinia- CA Certificate-3.pdf18 Feb 2022
Details of encumbrancesFile: Paikar_ Encumbrance Certificate_signed.pdf17 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Paikar Physical Report- Dec 2021_signed.pdf17 Feb 2022
Disclosure of sold/ booked inventoryFile: Paikar - Inventory data 31-12-2021_signed.pdf17 Feb 2022
Certificates of CA (Form 3)File: Financial Report - Project Progress D21.pdf17 Feb 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Vicinia- Society Formation- Dec-21.pdf17 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Paikar Physical Report- June 2021_signed.pdf29 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Paikar Physical Report- Sept 2021_signed.pdf29 Dec 2021
Disclosure of sold/ booked inventoryFile: PAIKAR - Disclosure of Inventory- Sept 21_signed.pdf21 Dec 2021
Certificates of CA (Form 3)File: Vicinia- Financial Report- June 21.pdf21 Dec 2021
Certificates of CA (Form 3)File: Vicinia- Financial Report- Sept 21.pdf21 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Paikar- Form 5- 2018-19.pdf21 Dec 2021
Certificates of CA (Form 3)File: Vicnia- Submission of Revised Form 3- June 2021.pdf16 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vicinia_Form 1_Sept 21.pdf15 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vicnia- Submission of Revised Form 2- June 2021.pdf15 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vicinia_Form 2_Sept 2021.pdf15 Oct 2021
Certificates of CA (Form 3)File: Vicinia_Form 3_Sept 2021.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vicinia_Architect Certificate_Sept 21.pdf12 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Forbes_Form 5 with enclosures.pdf30 Sep 2021
Disclosure of sold/ booked inventoryFile: Paikar_Revised Data_30th June.pdf27 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vicinia- Form 2- June 2021.pdf15 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vicinia- Form 1- June 2021.pdf14 Aug 2021
Certificates of CA (Form 3)File: Vicinia- Form 3- June 2021.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: Paikar- Inventory Disclosure- 30th June 2021.pdf3 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Vicnia- Status of Society Formation.pdf21 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Forbes - RERA Report Cover Letter.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Forbes - Management Declaration 2020.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Forbes - Form 5 2020 Final.pdf30 Sep 2020
Certificates of CA (Form 5)File: Paikar- Form 5- FY 2019-20.pdf29 Sep 2020
OtherFile: Vicinia- List of Real Estate Agents.pdf19 Aug 2020
Details of Restarting of Construction work post lockdownFile: Vicinia.pdf1 Aug 2020
Certificates of CA (Form 5)File: Form 5 PREPL.pdf1 Oct 2019
Certificates of CA (Form 5)File: Forbes-Form 5-FY 19-20.pdf27 Sep 2019
OtherFile: Paikar-Board Resolution-Authorized Signatories.pdf24 May 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VICINIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chandivali Andheri East6,700+ in Mumbai Suburban

2 kmVICINIACompleted 53Lapsed / revoked 26Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 111 registered projects within 2 km.

Builder: FORBES & COMPANY LIMITED

FORBES & COMPANY LIMITED has 1 registration on MahaRERA, including VICINIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VICINIA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VICINIA is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VICINIA?

The registered promoter entity is FORBES & COMPANY LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VICINIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VICINIA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VICINIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VICINIA?

The professionals named in the filing: Architect: BRIGHTON ARCHITECTS INDIA PVT LTD; Engineer: ASCENT STRUCTURAL ENGINEERS PVT LTD; Chartered Accountant: Vindochandra R. Shah & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VICINIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VICINIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VICINIA to a free account