ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VEESITA RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

VEESITA RESIDENCY

By RITE DEVELOPERS

RG-MH-36841 · RERA P51800010335 · Last updated on MahaRERA portal: 25 Sep 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 48 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2022Possession promised48 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 0%
4Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

VEESITA RESIDENCY is a Residential / Group Housing project by RITE DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010335 on 24 Aug 2017. Possession was promised by 31 Oct 2022 and is now 48 months past that date. The completion date has moved by 6 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameVEESITA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Azad Road
    • Gundavali
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010335
  • ReraGenie IDRG-MH-36841

Builder

  • NameRITE DEVELOPERS
  • Entity typePartnership
  • PartnersNARPATRAJ MEHTA, RAJEEV SURANA, SANJAY BAFNA

Key dates

48 months past promisethis monthRegisteredAug 2017First promiseApr 2022Revised toOct 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Oct 2022
  • Revised completionRevised to 31 Oct 2022 (originally 30 Apr 2022)
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VEESITA RESIDENCYNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

VEESITA RESIDENCY: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 25 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes95%
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered30
Open Space2

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,924 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
THE BOMBAY POSTAL EMPLOYEES CO-OP HSG. SOC. LTD.AndheriMumbai Suburban

Approvals and building plan

Permissible FSI4385.23
Proposed, not sanctioned4,385 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVEENA CHAMBERS, 21, DALAL STREET, MUMBAI 400023

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH BHATT
PartnerRole in project
RITE DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011581Apr 2022 → Oct 2022

Reason as filed by the promoterThe construction of the building is complete. OC and BCC has been applied for. This is a Society Redevelopment and 3-4 non co-operative members have filed false complaints with the MCGM. The MCGM has returned the application for further requisitions, specifically the status of Agreements of these 3-4 non-co-operative Members who are to be rehabilitated in the new building. We have submitted our say with the specific court orders passed against the said society members. We are hopeful that the OC and BCC will be issued shortly.

Litigation declared1

CaseCourtStatus
2872/2010BOMBAY HIGH COURTPENDING

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000056322Mukesh RaneRite Developers25/10/2018
CC006000000056326Sagar Sunderrao SangekarRite Developers25/10/2018
CC006000000194390BHALACHANDRA BHURKESANJAY BAFNA13/10/2020
CC006000000302941MEENU UDHARAM SAMTANIM/S. RITE DEVELOPERS06/10/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 May 2023

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: Details of encumbrances.pdf25 Sep 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A March 20.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A March 21.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A March 22.pdf25 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A March 23.pdf25 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 2023.pdf22 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Rera Cerifcate CA FY 21 22.pdf22 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Rera Cerifcate CA FY 22 23.pdf22 Sep 2023
Disclosure of sold/ booked inventoryFile: MahaRERA Format Disclosure of Sold Booked Inventory.pdf18 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Completion Plan.pdf4 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC CERTIFICATE.pdf4 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FINAL OC PLAN part 1.pdf5 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FINAL OC PLAN part 2.pdf5 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC CERTIFICATE.pdf5 Nov 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Formation of Soc and Conveyance.pdf11 Oct 2022
Status of ConveyanceFile: Formation of Soc and Conveyance.pdf11 Oct 2022
Disclosure of sold/ booked inventoryFile: MahaRERA Format Disclosure of Sold Booked Inventory Oct.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: MahaRERA Format Disclosure of Sold Booked Inventory Oct.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- RERA 1 Apr 21 to 31 Mar 22.pdf29 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC CERTIFICATE.pdf27 Aug 2022
Other - FinanceFile: Form 5- RERA.pdf27 Aug 2022
Building plan approvalFile: final approved plan 1.pdf23 Mar 2022
Building plan approvalFile: final approved plan 3.pdf23 Mar 2022
Building Plan Approval (IOD)File: final approved plan 1.pdf23 Mar 2022
Building Plan Approval (IOD)File: final approved plan 3.pdf23 Mar 2022
Layout approvalFile: final approved plan 2.pdf22 Mar 2022
Building plan approvalFile: final approved plan 2.pdf22 Mar 2022
Building plan approvalFile: final approved plan 4.pdf22 Mar 2022
Building plan approvalFile: final approved plan 5.pdf22 Mar 2022
Copy of Layout Approval (in case of layout)File: final approved plan 2.pdf22 Mar 2022
Building Plan Approval (IOD)File: final approved plan 2.pdf22 Mar 2022
Building Plan Approval (IOD)File: final approved plan 4.pdf22 Mar 2022
Building Plan Approval (IOD)File: final approved plan 5.pdf22 Mar 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf22 Mar 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf22 Mar 2022
CERSAI detailsFile: CERSAI UNDERTAKING.pdf22 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 March 2019.pdf15 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019-20.pdf15 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2019-20.pdf15 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21.pdf15 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Final Full CC.pdf30 Oct 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -BOOKED INVENTORY.pdf25 May 2021
Building plan approvalFile: Amendment letter_signed.pdf14 Apr 2021
Building Plan Approval (IOD)File: Amendment letter_signed.pdf14 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 dec 2018.pdf21 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: Form 5 March 2019.pdf21 Sep 2019
Declaration in FORM BFile: FORM B PROMOTER PG 2.pdf7 Oct 2017
Layout approvalFile: Plans 5.pdf30 Jul 2017
Building plan approvalFile: IOD.pdf30 Jul 2017
PAN CardFile: Rite Developers Pancard.pdf30 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf30 Jul 2017
Details of encumbrancesFile: No Encumbrance.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Plans 5.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: furthercc_signed.pdf30 Jul 2017
Declaration in FORM BFile: FORM ‘B’.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate WING B.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT-WING-B_PHASE_UPLOAD.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE RERA.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale proforma.pdf30 Jul 2017
OtherFile: DEVELOPMENT AGREEMENT_3.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VEESITA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gundavali6,700+ in Mumbai Suburban

2 kmVEESITA RESIDENCYCompleted 129Lapsed / revoked 79Other 162Dot size: filed unitsN

Filed coordinates, straight-line distance. 370 registered projects within 2 km.

Builder: RITE DEVELOPERS

RITE DEVELOPERS has 1 registration on MahaRERA, including VEESITA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VEESITA RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VEESITA RESIDENCY is delayed beyond 31 Oct 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VEESITA RESIDENCY?

The registered promoter entity is RITE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VEESITA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VEESITA RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VEESITA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VEESITA RESIDENCY?

The professionals named in the filing: Architect: UMESH BHATT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VEESITA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VEESITA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VEESITA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.