Home / Browse projects / Mumbai Suburban, Maharashtra / Veena Smart Homes

Registration lapsed No litigation declared Others project

Veena Smart Homes

By V.D. Infratech Private Limited

RG-MH-29848 · RERA P51800029400 · Last updated on MahaRERA portal: 17 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

Veena Smart Homes is a Others project by V.D. Infratech Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029400 on 29 May 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameVeena Smart Homes
  • TypeOthers
  • Location
    • Babrekar Nagar
    • Charkop
    • Kandivali west
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800029400
  • ReraGenie IDRG-MH-29848

Builder

  • NameV.D. Infratech Private Limited
  • Entity typeCompany
  • DirectorsNikunj Haresh Sanghavi, Haresh Natvarlal Sanghavi
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

16 months past promisethis monthRegisteredMay 2021First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 May 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed90 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing A - Building 2NA240000
Wing B - Building 2NA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.

Wing A - Building 247%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Wing B - Building 263%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 17 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,728 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Sai Construction CompanyBorivaliMumbai Suburban
Tanna Infra Developers LLPBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI9322.24
Proposed, not sanctioned9,322 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEverest Square bldg Shraddhanand RD Vile Parle East Mumbai 400057

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJitendra B Patel
EngineerRajeev Ranjan
Chartered AccountantThar & Co
Chartered AccountantJignesh Goradia
Chartered AccountantThar & Co.
PartnerRole in project
V.D. Infratech Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025434Dec 2024 → Jun 2025

Reason as filed by the promoterWe, the promoters of the project "Smart Homes" (MahaRERA Registration No. P51800029400), kindly request an extension of 6 months for the project completion date. The project is 95% complete, with only minor finishing work pending. We have applied for the Occupation Certificate (OC) and anticipate it will be granted within the next 3 to 6 months. An Architect's Certificate confirming the current status has been uploaded on the MahaRERA portal. To further support our submission, we have attached site photographs and declarations as annexures, providing visual and documentary evidence of the adva

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Apr 2025

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sale BLD Part OC 04042025.pdf17 Apr 2025
Declaration in FORM BFile: ACD_SMART.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventory Letter A B wing Smart Home Finalopt.pdf27 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf1 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 AB Wing Q3.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WorkComplationCertificateWingABQ32425.pdf20 Feb 2025
Declaration in FORM BFile: Extension 6m.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold unsold inventory.pdf23 Dec 2024
Declaration in FORM BFile: Affidavit Cum Declaration Rera Extension.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Smart Home A AND B Wing Q2.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf21 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 17122024 - V D Infratech Form 5 - Wing A and B.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Smart Homes Form-3 A and B Wing Q2FY2425compressed.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Certificate Wing A and B Q1FY2425.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Certificate Wing A and B Q2FY2425.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Smart Homes Form-3 A and B Wing Q1FY2425_compressed.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Smart Home A andB Wing Q1FY2425.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Smart Home A andB Wing Q1FY2425.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A and B wing Q4 VDIPL.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Certificate Wing A and B Q4.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Wing A and B Wing Q4.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Certificate Wing A and B Q4.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A and B wing Q4 VDIPL.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Wing A and B Wing Q4.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 A and b.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf2 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VDIPL FORM 5 WING A and B.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 AB Wing (Smart Home) 25 10 2023.pdf11 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 AB Wing (Smart Home) 25 10 2023.pdf11 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate A B 30 09 2023.pdf11 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Smart Home A and B Wing 16 11 2023.pdf11 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Work Completion Certificate Smart Home A B Wing 07 07 2023 0001.pdf4 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (form 2) Wing A B 30 08 2023.pdf4 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate ( Form 3) Wing A B 02 09 2023.pdf4 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate A B 31 12 2022 Q3.pdf3 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate A B 31 12 2022 Q3.pdf3 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate A B 31 12 2022 Q3.pdf3 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2 A B Wing 16 05 2023 F4.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A Certificate Smart Home A B Wing 16032023.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 A B Wing 20 05 2023 F4 11zon.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 A B Wing 20 05 2023 F4 11zon.pdf3 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Smart Home C Wing 04 04 2023.pdf19 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Smart Home A B Wing 31 12 2022.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate A and B.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Wing A and B form 5.pdf2 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect Certificate Smart Homes Wing A B_sep_22_compressed.pdf1 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form- 2 Engineer Certificate A B Wing 31-10-2022.pdf1 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Thar Co Form-3_CA Certificate - A B Wing compressed.pdf1 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Thar Co Form-3_CA Certificate - A B Wing compressed.pdf1 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate A B Wing.pdf22 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architect Certificate A B Wing.pdf22 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE A B Wing _compressed (1).pdf22 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Work Completion Certificate - Wing AB.pdf29 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Wing AB.pdf29 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Wing AB compressed.pdf29 Jun 2022
Declaration about Commencement CertificateFile: CC Declaration.pdf10 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate AB wing.pdf10 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate AB wing.pdf10 Feb 2022
CERSAI detailsFile: Cersai Undertaking.pdf10 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate AB wing.pdf10 Feb 2022
Declaration about Commencement CertificateFile: FormdreraVSH.pdf4 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf24 Aug 2021
Proforma of Allotment letterFile: ALLOTMENT DRAFT - SHOP.pdf13 Aug 2021
Proforma of Allotment letterFile: SMART HOMES -ALLOTMENT LETTER-Residential.pdf13 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 05-07-2021.pdf12 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf12 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf12 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf12 Aug 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE FINAL-SMART HOMES.pdf12 Aug 2021
Disclosure of sold/ booked inventoryFile: inventory declaration.pdf20 May 2021
Building plan approvalFile: Approved Building Plan 4 (1).pdf19 May 2021
Building plan approvalFile: Approved Building Plan 6 (1).pdf19 May 2021
Copy of the legal title reportFile: Self Declaration Legal Title Report.pdf19 May 2021
Details of encumbrancesFile: Self declaration encumbrances.pdf19 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Approved Building Plan 4 (1).pdf19 May 2021
Building Plan Approval / NA Order for plotted developmentFile: Approved Building Plan 6 (1).pdf19 May 2021
Commencement Certificates / NA Order for plotted developmentFile: CC Sale Building no 2.pdf19 May 2021
Declaration in FORM BFile: Self Declaration other land promoters.pdf19 May 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Veena Smart HomesP51800032966Kandivali, Mumbai Suburban172Feb 2022OngoingDec 2026Registered original: Dec 2025Not due yet

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Veena Smart Homes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali west6,700+ in Mumbai Suburban

Builder: V.D. Infratech Private Limited

V.D. Infratech Private Limited has 3 registrations on MahaRERA, including Veena Smart Homes and Veena Smart Homes. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Veena Smart Homes shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Veena Smart Homes is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Veena Smart Homes?

The registered promoter entity is V.D. Infratech Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Veena Smart Homes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Veena Smart Homes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Veena Smart Homes?

The professionals named in the filing: Architect: Jitendra B Patel; Engineer: Rajeev Ranjan; Chartered Accountant: Thar & Co; Chartered Accountant: Jignesh Goradia; Chartered Accountant: Thar & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Veena Smart Homes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Veena Smart Homes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Veena Smart Homes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.