Home / Browse projects / Thane, Maharashtra / VEDANT NAKSHATRA WING J PHASE VI

Completed No litigation declared Residential / Group Housing project

VEDANT NAKSHATRA WING J PHASE VI

By MOHAN HARDASMAL THARWANI

RG-MH-30709 · RERA P51700031084 · Last updated on MahaRERA portal: 9 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 2 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Feb 2025Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

VEDANT NAKSHATRA WING J PHASE VI is a Residential / Group Housing project by MOHAN HARDASMAL THARWANI in Thane, Maharashtra, registered with MahaRERA as P51700031084 on 5 Oct 2021. The registration is recorded completed; possession was promised by 21 Feb 2025. The completion date has moved by 2 months from the original filing.

At a glance

Project

  • NameVEDANT NAKSHATRA WING J PHASE VI
  • TypeResidential / Group Housing
  • Location
    • BADLAPUR
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • RERA no.P51700031084
  • ReraGenie IDRG-MH-30709

Builder

  • NameMOHAN HARDASMAL THARWANI
  • Entity typeIndividual
  • Other registrations18 more →
  • Completed10 of 19
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2021First promiseDec 2024Revised toFeb 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Oct 2021
  • Promised completion21 Feb 2025
  • Revised completionRevised to 21 Feb 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VEDANT NAKSHATRA WING J PHASE VINA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

VEDANT NAKSHATRA WING J PHASE VI: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 9 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area415 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6644.1
Proposed, not sanctioned6,644 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUlhasnagar-421003

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT INC
EngineerAVANISH & ASSOCIATES
Chartered AccountantASL & ASSOCIATES
Chartered AccountantVerhani & Co
PartnerRole in project
MOHAN HARDASMAL THARWANI-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025855Dec 2024 → Jan 2025

Reason as filed by the promoterPROJECT IS COMPLETED AND WE HAVE APPLIED OF FOR OC AND COPY OF APPLICATION OF ACKNOWLEGMENT IS ATTACHED WITH THE SAME AND SO WE REQUIORED EXTENSION FOR 1 MONTH, TILL DATE WE WILL GET OC OF WING J.

EXT51700027356Dec 2024 → Feb 2025

Reason as filed by the promoterThis is to inform you that our completion date of the above mentioned project was 31.01.2025. We have completed our project in all aspects and we have also received the occupation certificate for building name Vedant Nakshatra Wing J Phase VI for 18th Floors as mentioned registration application on 21.02.2025 As per the order no 24/2021 A (ii) promoter has to apply for an extension which will be valid upto the date of the occupation certificate, post facto extension may be granted. Hence we have applied for a Post facto extension, we request you to approve our Post facto extension upto the dat

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Feb 2025

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: UPDATED FORM B.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC J wing.pdf25 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf7 Oct 2024
Copy of the legal title reportFile: ilovepdf_merged (1)_compressed.pdf25 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf20 Apr 2024
Proforma of Agreement for saleFile: Nak J (1).pdf15 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report APR J WING.pdf15 Apr 2024
OtherFile: Other Dec_compressed.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed (1).pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Sol Unsold_compressed.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf17 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Scan_20231110_142458_compressed.pdf10 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration_compressed.pdf10 Nov 2023
Disclosure of sold/ booked inventoryFile: sold booked inventory_compressed.pdf27 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf27 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2 (A).pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Nak J wing .pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: disclosure of sold wing j.pdf26 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf5 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3_compressed.pdf5 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: J WING.PDF21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 WNG J.PDF20 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate J Wing_compressed.pdf28 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A J WING 31 MARCH 22_compressed.pdf10 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (1).pdf10 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: J WING FORM 2_compressed.pdf27 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 J-WING.pdf17 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 j wing_compressed.pdf17 May 2022
Layout approvalFile: layout_compressed_compressed_compressed_compressed_compressed.pdf25 Apr 2022
Building plan approvalFile: Floor Plan-compressed_compressed (1)_compressed.pdf25 Apr 2022
Building plan approvalFile: Floor plan 1_compressed.pdf25 Apr 2022
Copy of Layout Approval (in case of layout)File: layout_compressed_compressed_compressed_compressed_compressed.pdf25 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: Floor Plan-compressed_compressed (1)_compressed.pdf25 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: Floor plan 1_compressed.pdf25 Apr 2022
OtherFile: J-WING 25-4-2022.pdf25 Apr 2022
OtherFile: J WING REVISED AREA_compressed (1).pdf25 Apr 2022
OtherFile: ENCUMBRANCE CERTIFICATE WING J.PDF7 Apr 2022
Declaration about Commencement CertificateFile: DECLARATION OF CC_compressed.pdf26 Mar 2022
OtherFile: DECLARATION WING J_compressed.pdf26 Mar 2022
Layout approvalFile: LAYOUT PLAN SHEET 1_compressed (1)-compressed - Copy.pdf30 Sep 2021
Building plan approvalFile: WING J SHEET.pdf30 Sep 2021
Building plan approvalFile: WING J SHEET 3 (1).pdf30 Sep 2021
Building plan approvalFile: WING J SHEET 4 (1).pdf30 Sep 2021
Copy of the legal title reportFile: Title Certificate and Flow of the Titile Said Property_compressed (1).pdf30 Sep 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN SHEET 1_compressed (1)-compressed - Copy.pdf30 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: WING J SHEET.pdf30 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: WING J SHEET 3 (1).pdf30 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: WING J SHEET 4 (1).pdf30 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: VEDANT NAKSHATRA J K WING CC.pdf30 Sep 2021
Declaration about Commencement CertificateFile: Declaration Of Commencement Certificate.pdf30 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 J Wing_compressed.pdf22 Sep 2021
Proforma of Allotment letterFile: Allotment of Flat J_compressed (1).pdf22 Sep 2021
Proforma of Allotment letterFile: NAKSHATRA-j.pdf22 Sep 2021
PAN CardFile: PAN Card.pdf21 Sep 2021
Details of encumbrancesFile: Declaration Of Non-Encumbrance (J).pdf21 Sep 2021
Declaration in FORM BFile: Form B(3 (4)_compressed.pdf21 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate J Wing_compressed (1).pdf21 Sep 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VEDANT MILLENIA PHASE 1BEHIND MAHAGANPATI MANDIR TITWALA WEST402CompletedMar 2016Late, Jul 2016

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 2 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VEDANT NAKSHATRA WING J PHASE VI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BADLAPUR7,600+ in Thane

Builder: MOHAN HARDASMAL THARWANI

MOHAN HARDASMAL THARWANI has 19 registrations on MahaRERA, including vedant nakshatra ABC phase 1 and vedant nakshatra M phase 2. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if VEDANT NAKSHATRA WING J PHASE VI is delayed beyond 21 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VEDANT NAKSHATRA WING J PHASE VI?

The registered promoter entity is MOHAN HARDASMAL THARWANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VEDANT NAKSHATRA WING J PHASE VI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VEDANT NAKSHATRA WING J PHASE VI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VEDANT NAKSHATRA WING J PHASE VI?

The professionals named in the filing: Architect: ARCHITECT INC; Engineer: AVANISH & ASSOCIATES; Chartered Accountant: ASL & ASSOCIATES; Chartered Accountant: Verhani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VEDANT NAKSHATRA WING J PHASE VI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VEDANT NAKSHATRA WING J PHASE VI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VEDANT NAKSHATRA WING J PHASE VI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.