Vedaant Meadows

By VEDAANT BUILDERS

RG-MH-63132 · RERA P51700049153 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 89%
55 of 91Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Vedaant Meadows is a Residential / Group Housing project by VEDAANT BUILDERS in Thane, Maharashtra, registered with MahaRERA as P51700049153 on 1 Feb 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 36 of the 91 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVedaant Meadows
  • TypeResidential / Group Housing
  • Location
    • Varap
    • Kalyan
    • Thane
    • 421103
  • Pincode421103
  • RERA no.P51700049153
  • ReraGenie IDRG-MH-63132

Builder

  • NameVEDAANT BUILDERS
  • Entity typePartnership
  • PartnerRAHUL RAJKUMAR SHIVNANI

Key dates

this monthRegisteredFeb 2023First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Feb 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed77 files

Current status

40%36 of 91 units booked
75.4%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 2 B WingNA9742042
Building 2 A WingNA9749049

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 89%.

Building 2 B Wing77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises89%
Sanitary Fittings within the flats / premises62%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.71%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Building 2 A Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes72%
Water SupplyYes28%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes41%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered16
Open Space112
BuildingClosed/CoveredOpen SpaceTotal
Building 2 B Wing15015
Building 2 A Wing1112113

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,520 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Hardevi Omprakash LundUlhasnagar (M Corp.)Thane
Sunil Omprakash LundUlhasnagar (M Corp.)Thane
Rakesh Omprakash LundUlhasnagar (M Corp.)Thane
Asmita Gopal LalwaniUlhasnagar (M Corp.)Thane
Kailash Shankarlal SoniKalyanThane
Sitaram Satyanarayan KhairariUlhasnagar (M Corp.)Thane

Approvals and building plan

Sanctioning authorityKDMC
Permissible FSI7884.8
Proposed, not sanctioned7,885 sq m
Buildings approved3
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMharal, Kalyan
Estimated costRs 5.48 cr
Cost incurredRs 4.13 cr
Work done75.39%
BuildingWingEstimatedIncurred
Building 2 B WingNARs 5.18 crRs 3.93 cr
-NARs 30.44 lakhRs 19.79 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGuru Associates
EngineerGuru Associates
Chartered AccountantM R Motwani & Associates
Chartered AccountantCHETAN TALREJA
PartnerRole in project
VEDAANT BUILDERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20122518858Dec 2025 → Dec 2027

Reason as filed by the promoterDUE TO NON AVAILABILITY OF EFFICIENT STAFF & SOME FINANCIAL GLITCHES ONLY CONSTRUCTION OF WING B IS COMPLETED & WING A CONSTRUCTION HAD JUST BEGAN HENCE EXTENSION REQUIRED

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12605255Dilip Khandu ShindeVEDAANT BUILDERS18/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 vedaant builder .pdf20 Apr 2026
Withdrawal Update Form 2File: form 2 vedaant builder .pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Vedant Meadow.pdf20 Apr 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 (1) (1) (1).pdf7 Feb 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 (1).pdf7 Feb 2026
Withdrawal Update Form 3File: Vedaant Builders Q3 FY 25-26 (1).pdf7 Feb 2026
Form 5 (FY 2024-2025)File: form 5 vedaant builders .pdf31 Dec 2025
Withdrawal Update Form 1File: FORM 1.pdf7 Nov 2025
Withdrawal Update Form 2File: FORM 2.pdf7 Nov 2025
Withdrawal Update Form 3File: FORM 3.pdf7 Nov 2025
Form 1File: FORM 1.pdf23 Oct 2025
Form 2File: FORM 2.pdf23 Oct 2025
Form 3File: FORM 3.pdf23 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD V-BUILDER.pdf23 Oct 2025
Form 1File: Form 1 Vedaant Meadows.pdf19 Jul 2025
Form 2File: Form 2 Vedaant Meadows.pdf19 Jul 2025
Form 3File: Form 3 Vedaant Meadows.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: veedant_builder sold unsold june-2025.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vedaant form 1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vedaant form 3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vedaant form 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: vedaant sold-unsold.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: vedaant builders form 1.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vedaant builders form 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: vedaant builders sold-booked.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 vedaant builder.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 vedaant builder.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: vedaant builder sold unsold.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: vedaant builder form 2A.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 VEDAANT.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: vedaant form-2 till 30-06-2024.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: vedaant sold -unsold.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: vedaant sold -unsold.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_11zon.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DEC 23.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MAR 24.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DEC 23.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MAR 24.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD ANNEXURE SEP 23.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD ANNEXURE DEC 23.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD ANNEXURE MAR 24.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JUNE 2023.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SEP 23.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DEC 23.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MAR 24.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 (1).pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 (2).pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf26 Sep 2023
Disclosure of sold/ booked inventoryFile: Self declaration.pdf26 Sep 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf26 Sep 2023
Proforma of Agreement for saleFile: Vedant Builders Agreement Revised 23012023.pdf23 Jan 2023
Declaration in FORM BFile: DocScanner Jan 20, 2023 2-15 PM.pdf20 Jan 2023
Copy of the legal title reportFile: Circular 28 Format A.pdf18 Jan 2023
Copy of the legal title reportFile: Flow title format A.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE FORM 3.pdf18 Jan 2023
Layout approvalFile: Varap_Layout Copy.pdf15 Jan 2023
Building plan approvalFile: scan342300 (1).pdf15 Jan 2023
Building plan approvalFile: scan3422 (1).pdf15 Jan 2023
Building plan approvalFile: scan3424 (1).pdf15 Jan 2023
PAN CardFile: PAN (4).pdf15 Jan 2023
Copy of Layout Approval (in case of layout)File: Varap_Layout Copy.pdf15 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: scan342300 (1).pdf15 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: scan3422 (1).pdf15 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: scan3424 (1).pdf15 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Varap_PlanPass_NA_All_Papers (1)_compressed (1)-1-4.pdf15 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Varap_PlanPass_NA_All_Papers (1)_compressed (1)_compressed-5-9.pdf15 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200257585827_For_Asset_Based_Search_15_01_2023_15_54_07_053.pdf15 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: interest in other entities.pdf15 Jan 2023
Proforma of Allotment letterFile: Allotment Letter Vedaant.pdf15 Jan 2023
Details of encumbrances concerned to FinanceFile: Declaration Land Encumbrance.pdf14 Jan 2023
Details of encumbrances concerned to LegalFile: Declaration Land Encumbrance.pdf14 Jan 2023
Declaration about Commencement CertificateFile: Declaration Commencement.pdf14 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Bank Account.pdf14 Jan 2023
Deviation Report with respect to Allotment letterFile: Declaration Allotment.pdf14 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Declaration Agreement.pdf14 Jan 2023

How this compares with Thane

40%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vedaant Meadows on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Varap7,600+ in Thane

Builder: VEDAANT BUILDERS

VEDAANT BUILDERS has 1 registration on MahaRERA, including Vedaant Meadows. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Vedaant Meadows is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vedaant Meadows?

The registered promoter entity is VEDAANT BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vedaant Meadows?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vedaant Meadows?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vedaant Meadows?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vedaant Meadows?

The professionals named in the filing: Architect: Guru Associates; Engineer: Guru Associates; Chartered Accountant: M R Motwani & Associates; Chartered Accountant: CHETAN TALREJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vedaant Meadows?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vedaant Meadows. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vedaant Meadows to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.