ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VARDHMAN PEARL

Registration revoked No litigation declared Others project

VARDHMAN PEARL

By DIWALI DEVELOPERS

RG-MH-30793 · RERA P51800032809 · Last updated on MahaRERA portal: 18 Jan 2022

Source: official MahaRERA filing

Red flags

  • Registration revoked
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
0 of 11Construction stages donefurthest along: Excavation, 80%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

VARDHMAN PEARL is a Others project by DIWALI DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032809 on 29 Jan 2022. Possession was promised by 31 Dec 2024 and is now 22 months past that date.

At a glance

Project

  • NameVARDHMAN PEARL
  • TypeOthers
  • Location
    • MARVE ROAD
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800032809
  • ReraGenie IDRG-MH-30793

Builder

  • NameDIWALI DEVELOPERS
  • Entity typePartnership
  • PartnersDIPESH RAMESH VARDHAN, BABULAL MISHRIMAL VARDHAN, MANJU RAMESH VARDHAN, VISHAL RAMESH VARDHAN, AKASH RAJESH VARDHAN, DILIP BABULAL VARDHAN, RAJESH BABULAL VARDHAN
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredJan 2022PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration revoked
  • Registered on29 Jan 2022
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VARDHMAN PEARLNA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 80%.

VARDHMAN PEARL: 36% average across the applicable activities

ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor80%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed232

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots232
Closed/Covered232

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,914 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MUMBADEVI MALAD CHSL-Mumbai City

Approvals and building plan

Permissible FSI12101.35
Proposed, not sanctioned3,364 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR JEHANGIR BUILDING M G ROAD FORT

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTARUN MOTTA
EngineerSHANKEY BAFNA
Chartered AccountantSHRAVAN GANDHI
PartnerRole in project
DIWALI DEVELOPERS-

Litigation declared2

CaseCourtStatus
L 314/2021BOMBAY HIGH COURTHEARING AD INTERIM
NA/2019BEFORE THE SOLE ARBITRAL TRIBUNAL JUSTICE DR S RADHAKRISHNAN RETIREDPLEADING STAGE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: Re endrosed CC.pdf18 Jan 2022
Declaration about Commencement CertificateFile: Declaration for CC- diwali developers.pdf18 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: REVALIDATION ISSUE LETTER.pdf5 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: ccUT.pdf16 Dec 2021
CERSAI detailsFile: CERSAI REPORT.PDF16 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Revalidation Fee Letter.pdf6 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: 0702092072397_signed.pdf6 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: ActiveReport.pdf6 Dec 2021
CERSAI detailsFile: Cersai.pdf6 Dec 2021
Proforma of Allotment letterFile: Final AFS Clean Diwali Developers 2311.pdf23 Nov 2021
Copy of the legal title reportFile: title.PDF22 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 4.pdf20 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 5.pdf20 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 6.pdf20 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 7.pdf20 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 8.pdf20 Nov 2021
Building plan approvalFile: AMENDED ISSUE LETTER and PLAN 9.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 4.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 5.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 6.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 7.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 8.pdf20 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER and PLAN 9.pdf20 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised Vardhman Pearl.pdf11 Nov 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf11 Nov 2021
Layout approvalFile: LAYOUT.PDF21 Oct 2021
Details of encumbrancesFile: NO ENCUMBRANCE.pdf21 Oct 2021
Copy of Layout Approval (in case of layout)File: LAYOUT.PDF21 Oct 2021
Declaration about Commencement CertificateFile: DEC CC.pdf21 Oct 2021
Declaration in FORM BFile: promoter.PDF18 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-1.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-2.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-3.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-4.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-5.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-6.pdf15 Oct 2021
Building plan approvalFile: Corrected 8144 Plans-7.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-1.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-2.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-3.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-4.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-5.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-6.pdf15 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Corrected 8144 Plans-7.pdf15 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Oct 2021
Building plan approvalFile: AMENDED ISSUE LETTER.pdf1 Oct 2021
PAN CardFile: PAN CARD.pdf1 Oct 2021
Copy of the legal title reportFile: TITLE.pdf1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: AMENDED ISSUE LETTER.pdf1 Oct 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VARDHMAN VATIKA E BUILDINGGHODBUNDER ROAD28CompletedDec 2019Late, Dec 2020

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDHMAN PEARL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

2 kmVARDHMAN PEARLCompleted 159Lapsed / revoked 95Other 176Dot size: filed unitsN

Filed coordinates, straight-line distance. 430 registered projects within 2 km.

Builder: DIWALI DEVELOPERS

DIWALI DEVELOPERS has 2 registrations on MahaRERA, including VARDHMAN VATIKA and VARDHMAN PEARL. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VARDHMAN PEARL shows as registration revoked on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VARDHMAN PEARL is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHMAN PEARL?

The registered promoter entity is DIWALI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHMAN PEARL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VARDHMAN PEARL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHMAN PEARL?

The professionals named in the filing: Architect: TARUN MOTTA; Engineer: SHANKEY BAFNA; Chartered Accountant: SHRAVAN GANDHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHMAN PEARL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHMAN PEARL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHMAN PEARL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.