ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / VARDHAMAN BHOOMI RESIDENCY

Registration lapsed No litigation declared Others project

VARDHAMAN BHOOMI RESIDENCY

By GANDHI & SAMANI ASSOCIATES

RG-MH-45783 · RERA P51700014916 · Last updated on MahaRERA portal: 19 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

VARDHAMAN BHOOMI RESIDENCY is a Others project by GANDHI & SAMANI ASSOCIATES in Thane, Maharashtra, registered with MahaRERA as P51700014916 on 11 Jan 2018. Possession was promised by 15 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVARDHAMAN BHOOMI RESIDENCY
  • TypeOthers
  • Location
    • NARPOLI
    • BHIWANDI
    • Bhiwandi (M Corp.)
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700014916
  • ReraGenie IDRG-MH-45783

Builder

  • NameGANDHI & SAMANI ASSOCIATES
  • Entity typePartnership
  • PartnersCHENSINGH TULSIRAMJI RAJPUROHIT, DAYALAL HARIDAS SAMANI, MAHENDRA DALICHAND GANDHI

Key dates

22 months past promisethis monthRegisteredJan 2018First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Jan 2018
  • Promised completion15 Dec 2024
  • Revised completionRevised to 15 Dec 2024 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VARDHAMAN BHOOMI RESIDENCYNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

VARDHAMAN BHOOMI RESIDENCY: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered11
Open Space10

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,620 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
GORDHANSINH CHUNILALJI PUROHITKakadpadaThane
GORDHAN CHUNILAL PUROHIT HUFKakadpadaThane

Approvals and building plan

Permissible FSI5424.42
Proposed, not sanctioned5,424 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHIWANDI KALYAN ROAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKK AND ASSOCIATES
EngineerKK AND ASSOCIATES
PartnerRole in project
GANDHI & SAMANI ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018413Dec 2023 → Dec 2024

Reason as filed by the promoterDUE TO SLOW SALES AND RISING COST OF CONSTRUCTION THE PROJECT WAS DELAYED, WE REQUIRE TIME TILL 15 DECEMBER 2024 TO COMPLETE IT 100% AND GET THE OCCUPATION CERTIFICATE FROM THE SANCTIONING AUTHORITY.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Feb 2025

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GSA FORM-1 ARCH CERTIFICATE OCT-24.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GSA FORM-1 ARCH CERTIFICATE NOV-24.pdf19 Feb 2025
Certificates of CA (Form 3)File: FORM 3 GSA SEPT 24.pdf19 Feb 2025
Certificates of CA (Form 3)File: FORM 3 GGA DEC 24.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GSA FORM-2 ENG CERTIFICATE OCT-24.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GSA FORM-2 ENG CERTIFICATE NOV-24.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM-4 (GSA).pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: gandhi samani ASSOCIATES oc (1).pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE 24 GSA.pdf14 Nov 2024
Certificates of CA (Form 3)File: FORM 3 GANDHI SAMANI AND ENTERPRISES JUNE 24_11zon.pdf14 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE GSA.pdf14 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GGA-2024.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 GSA MARCH 24.pdf12 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GSA MARCH 24.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A GSA MARCH 24.pdf12 Jul 2024
Certificates of CA (Form 3)File: FORM 3 MARCH 24 GSA.pdf12 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 GANDHI SAMANI ASSOCIATES DEC 2023.pdf15 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GANDHI SAMANI ASSOCIATES DEC 2023.pdf15 Feb 2024
Certificates of CA (Form 3)File: FORM 3 GANDHI SAMANI ASSOCIATES DEC 2023.pdf15 Feb 2024
Declaration about Commencement CertificateFile: format d.pdf8 Jan 2024
Declaration in FORM BFile: FORM B LAND LORD_11zon.pdf8 Jan 2024
Declaration in FORM BFile: FORM B PROMOTER_11zon.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DISCLOSURE GGA.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GGA FORM 1 MARCH 23.pdf22 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GGA FORM 1 JUNE 23.pdf22 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GGA FORM 1 SEPT 23.pdf22 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GGA FORM 2 MARCH 23.pdf22 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GGA FORM 2 JUNE 23.pdf22 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GGA FORM 2 SEPT 23.pdf22 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GGA FORM 2A MARCH 23.pdf22 Dec 2023
Certificates of CA (Form 3)File: GGA FORM 3 MARCH 23_11zon.pdf22 Dec 2023
Certificates of CA (Form 3)File: GGA FORM 3 JUNE 23_11zon.pdf22 Dec 2023
Certificates of CA (Form 3)File: GGA FORM 3 SEPT 23_11zon.pdf22 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GGA FORM 5 MARCH 23.pdf22 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA MARCH 18_3_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA MARCH 19_4_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA MARCH 20_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA MARCH 21_5_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA MARCH 22_6_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA JUNE 22_2_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 GSA SEPT 22_7_11zon.pdf1 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 GSA DEC 22_1_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA MARCH 18_2_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GSA JUNE 18_2_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA SEPT 18_6_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA DEC 18_4_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA MARCH 19_3_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA JUUNE 19_1_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA SEPT 19_7_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA DEC 19_5_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA JUNE 20_9_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA SEPT 20_8_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA DEC 20_6_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA MARCH 21_4_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA JUNE 21_10_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GSA SEPT 21_3_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA DEC 21_7_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA MARCH 22_5_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA JUNE 22_11_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA SEPT 22_9_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA DEC 22_8_11zon.pdf1 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 GSA MARCH 20_8_11zon.pdf1 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FROM 2A MARCH 19_4_11zon.pdf1 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FROM 2A GSA MARCH 20_2_11zon.pdf1 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FROM 2A GSA MARCH 21_3_11zon.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA SEP 2018.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA DEC 2018.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA MARCH 2019.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA JUNE 2019.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA SEPT 2019.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA DEC 2019.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA MARCH 2020.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA JUNE 2020.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA SEPT 2020.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA DEC 2020.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA MARCH 2021.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA JUNE 2021.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA SEPT 2021.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA DEC 2021.pdf1 May 2023
Certificates of CA (Form 3)File: FORM 3 GSA MARCH 2022.pdf1 May 2023

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VARDHAMAN BHOOMI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHIWANDI7,600+ in Thane

2 kmVARDHAMAN BHOOMI RESIDENCompleted 29Lapsed / revoked 23Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: GANDHI & SAMANI ASSOCIATES

GANDHI & SAMANI ASSOCIATES has 1 registration on MahaRERA, including VARDHAMAN BHOOMI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that VARDHAMAN BHOOMI RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VARDHAMAN BHOOMI RESIDENCY is delayed beyond 15 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VARDHAMAN BHOOMI RESIDENCY?

The registered promoter entity is GANDHI & SAMANI ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VARDHAMAN BHOOMI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VARDHAMAN BHOOMI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VARDHAMAN BHOOMI RESIDENCY?

The professionals named in the filing: Architect: KK AND ASSOCIATES; Engineer: KK AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VARDHAMAN BHOOMI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VARDHAMAN BHOOMI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VARDHAMAN BHOOMI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.