Vama Park
By Vama Realty
RG-MH-00471 · RERA P49500000044 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 2 months past the filed date
- Completion date moved by 5 months
- 1 extension taken
- Rs 3.50 crore secured on the land, in favour of State Bank of India
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Daman registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vama Park is a Residential / Group Housing project by Vama Realty in Daman, Daman & Diu, registered with MahaRERA as P49500000044 on 6 Mar 2023. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 5 months from the original filing. 34 of the 35 units on this registration are recorded sold or booked, and 37 of 44 construction stages are filed complete.
At a glance
Project
- NameVama Park
- TypeResidential / Group Housing
- Location
- Vama Parks Survey No. 324/1 and 324/3
- Opposite Dunetha Gram Panchayat
- Nani Daman
- Daman
- 396210
- Pincode396210
- RERA no.P49500000044
- ReraGenie IDRG-MH-00471
Builder
- NameVama Realty
- Entity typePartnership
- PartnersHimadri Priyank Patel, Mikhil Natvarbhai Tandel, Shiwani Rathi
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Mar 2023
- Promised completion31 Aug 2026
- Revised completionRevised to 31 Aug 2026 (originally 31 Mar 2026)
- Buildings4 building records
- Documents filed110 files
Current status
Figures as on 6 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vama Park Unit 2 | NA | 2 | 2 | 15 | 0 | 15 |
| Vama Park Unit 1 | NA | 2 | 2 | 3 | 0 | 3 |
| Vama Park Unit 3 | NA | 2 | 2 | 10 | 0 | 10 |
| Vama Park Unit 4 | NA | 2 | 2 | 7 | 0 | 7 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
37 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
Vama Park Unit 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Vama Park Unit 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Vama Park Unit 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Vama Park Unit 464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed35
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Vama Park Unit 2 | 15 | 15 |
| Vama Park Unit 1 | 3 | 3 |
| Vama Park Unit 3 | 10 | 10 |
| Vama Park Unit 4 | 7 | 7 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Priyank Jayesh | - | Daman |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Vama Park Unit 2 | NA | Rs 3.39 cr | Rs 3.39 cr |
| Vama Park Unit 3 | NA | Rs 2.26 cr | Rs 2.26 cr |
| Vama Park Unit 4 | NA | Rs 1.55 cr | Rs 1.55 cr |
| - | NA | Rs 1.15 cr | Rs 1.15 cr |
| Vama Park Unit 1 | NA | Rs 67.39 lakh | Rs 67.39 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manish Doshi |
| Engineer | Rajesh Tandel |
| Chartered Accountant | Rajesh Katariya |
| Chartered Accountant | Kakaria and Associates LLP |
| Partner | Role in project |
|---|---|
| Vama Realty | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAll the work for our said project are complete and we have applied for the OC. However, due to procedural delay at the end of competent authority, OC for the same is not received, hence we have applied for the extension.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed110
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect certificate 311225.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 1 Nov 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 1 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 1 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 signed.pdf | 30 Sep 2025 |
| Form 2A (FY 2022-2023)File: Form 2A-23.pdf | 22 Jul 2025 |
| Form 2A (FY 2023-2024)File: Form 2A-24.pdf | 22 Jul 2025 |
| Form 2A (FY 2024-2025)File: Form 2A-25.pdf | 22 Jul 2025 |
| Form 5 (FY 2022-2023)File: Form 5 Scanned.pdf | 22 Jul 2025 |
| Form 5 (FY 2023-2024)File: Form 5 signed.pdf | 22 Jul 2025 |
| Form 1File: form 1 Compressed.pdf | 9 Jul 2025 |
| Form 2File: form 2 final.pdf | 9 Jul 2025 |
| Form 3File: Form 3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: Form 1.pdf | 9 Jul 2025 |
| Form 2File: Form 2_compressed.pdf | 9 Jul 2025 |
| Form 3File: Form 3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: architect 300923compressed.pdf | 9 Jul 2025 |
| Form 2File: engineer 300923_compressed.pdf | 9 Jul 2025 |
| Form 3File: Form 3_compressed.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: Form 1.pdf | 9 Jul 2025 |
| Form 2File: Form 2.pdf | 9 Jul 2025 |
| Form 3File: Form 3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: _Architect certificate .pdf | 9 Jul 2025 |
| Form 2File: Engineers certificate .pdf | 9 Jul 2025 |
| Form 3File: Form 3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf | 9 Jul 2025 |
| Form 1File: architect certificate_compressed.pdf | 9 Jul 2025 |
| Form 2File: ENGINEER CERTIFICATE_compressed.pdf | 9 Jul 2025 |
| Form 3File: Form 3_compressed.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: architect certificate.pdf | 9 Jul 2025 |
| Form 2File: engineer certificate.pdf | 9 Jul 2025 |
| Form 3File: Form 3_compressed.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: Form 1.pdf | 9 Jul 2025 |
| Form 2File: Form 2.pdf | 9 Jul 2025 |
| Form 3File: Form 3.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Form 1File: Architect certificate.pdf | 9 Jul 2025 |
| Form 2File: engineers certificate 2025.pdf | 9 Jul 2025 |
| Form 3File: form 3 vama 31325.pdf | 9 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 9 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1.pdf | 30 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2.pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: architect certificate.pdf | 28 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3_compressed.pdf | 28 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: engineer certificate.pdf | 28 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 signed.pdf | 16 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: architect certificate_compressed.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: ENGINEER CERTIFICATE_compressed.pdf | 31 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3_compressed.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: _Architect certificate .pdf | 1 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Engineers certificate .pdf | 1 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3.pdf | 1 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A)File: FORM 2A .pdf | 1 May 2024 |
| Other - FinanceFile: Sold-Unsold.pdf | 1 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1.pdf | 20 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2.pdf | 20 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3.pdf | 20 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: architect 300923compressed.pdf | 31 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: engineer 300923_compressed.pdf | 31 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3_compressed.pdf | 31 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Scanned.pdf | 30 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1.pdf | 5 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2_compressed.pdf | 5 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3.pdf | 5 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: form 1 Compressed.pdf | 13 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: form 2 final.pdf | 13 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3.pdf | 13 Jun 2023 |
| Declaration in FORM BFile: FORM B Mikhil.pdf | 24 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Daman
Computed across the 59 Daman projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 110 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vama Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Opposite Dunetha Gram Panchayat, Nani Daman59 in Daman
Fortune DP Nano-2 Phase - 2
G B AND ASSOCIATES
FORTUNE WORLD - 2
FORTUNE DREAM - CON PVT LTD
NEO PARK
MS DARSHAN REALITY
TULSI RESIDENCY
OM ENTERPRISE
Shree Hari Commercial Building Phase 1
ASHOKKUMAR HARIBHAI TANDEL
EXOTICA RESIDENCY
R THREE DEVELOPERS
See every Daman project, with the district possession charts
Builder: Vama Realty
Vama Realty has 1 registration on MahaRERA, including Vama Park. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Daman district page.
Frequently asked questions
What are my rights if Vama Park is delayed beyond 31 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vama Park?
The registered promoter entity is Vama Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vama Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vama Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vama Park?
The professionals named in the filing: Architect: Manish Doshi; Engineer: Rajesh Tandel; Chartered Accountant: Rajesh Katariya; Chartered Accountant: Kakaria and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vama Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback