Registration lapsed No litigation declared Residential / Group Housing project

NEO PARK

By MS DARSHAN REALITY

RG-MH-00388 · RERA P49500000031 · Last updated on MahaRERA portal: 12 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Daman registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
14 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 75%
116 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

NEO PARK is a Residential / Group Housing project by MS DARSHAN REALITY in Daman, Daman & Diu, registered with MahaRERA as P49500000031 on 23 Apr 2021. Possession was promised by 31 Dec 2023 and is now 34 months past that date. 22 of the 138 units on this registration are recorded sold or booked, and 14 of 44 construction stages are filed complete.

At a glance

Project

  • NameNEO PARK
  • TypeResidential / Group Housing
  • Location
    • BHENSROAD
    • SURVEY NO 209/1 AND 209/2
    • Daman
    • 396210
  • Pincode396210
  • RERA no.P49500000031
  • ReraGenie IDRG-MH-00388

Builder

  • NameMS DARSHAN REALITY
  • Entity typePartnership
  • PartnersRAJNIKANT GANPATBHAI KAMLI, RINKU RAJNIKANT KAMLI

Key dates

34 months past promisethis monthRegisteredApr 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Apr 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed19 files

Current status

16%22 of 138 units booked

Figures as on 12 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA5535035
A2NA5035035
A3NA5535035
DNA5533033

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 12 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

A155%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor1%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A234%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor1%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A339%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor1%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor1%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered4
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
A1112
A2112
A3112
D112

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DARSHAN REALITY-Daman

Approvals and building plan

Sanctioning authorityJunior town planner daman
Permissible FSI3319.45
Proposed, not sanctioned3,319 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOTI DAMAN DAMAN

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHINTESH G BARDOLIWALA
ArchitectSubhadradevi Sojitra
EngineerCHIRAG K WANKAWALA
EngineerBHAUTIK SOJITRA
Chartered AccountantSALMAN ARIFBHAI MEMON(
Chartered AccountantAnupama Shetty
PartnerRole in project
MS DARSHAN REALITY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: 0 (11).pdf12 Jul 2025
Form 5 (FY 2023-2024)File: 0 (12).pdf12 Jul 2025
Form 1File: FORM 1.pdf5 Jul 2025
Form 2File: FORM 2.pdf5 Jul 2025
Form 3File: form 3_11zon.pdf5 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf5 Jul 2025
Copy of the legal title reportFile: Neo park U.pdf3 Apr 2021
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: ITR.pdf3 Apr 2021
PAN CardFile: FIRM PAN.pdf9 Mar 2021
Details of encumbrancesFile: NEO ENCRUMBRANCE.pdf9 Mar 2021
Layout approvalFile: plan compress 1.pdf8 Mar 2021
Building plan approvalFile: plan compress 2.pdf8 Mar 2021
Copy of Layout Approval (in case of layout)File: plan compress 1.pdf8 Mar 2021
Building Plan Approval (IOD)File: plan compress 2.pdf8 Mar 2021
Commencement CertificatesFile: rajachhithi_compressed.pdf8 Mar 2021
Declaration in FORM BFile: Form B.pdf8 Mar 2021
Certificates of CA (Form 3) (UT)File: FORM 3.pdf8 Mar 2021
Proforma of Allotment letterFile: AGREEMENT FORMAT.pdf8 Mar 2021
Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf8 Mar 2021

How this compares with Daman

16%of this project is bookeddistrict median 32%
18%of Daman projects moved their completion datethis one has not
35%of Daman registrations have lapsed or been cancelledthis one is among them

Computed across the 59 Daman projects on ReraGenie, from their own filings.

Keep NEO PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SURVEY NO 209/1 AND 209/259 in Daman

Builder: MS DARSHAN REALITY

MS DARSHAN REALITY has 1 registration on MahaRERA, including NEO PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Daman district page.

Frequently asked questions

What does it mean that NEO PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEO PARK is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEO PARK?

The registered promoter entity is MS DARSHAN REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEO PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NEO PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEO PARK?

The professionals named in the filing: Architect: CHINTESH G BARDOLIWALA; Architect: Subhadradevi Sojitra; Engineer: CHIRAG K WANKAWALA; Engineer: BHAUTIK SOJITRA; Chartered Accountant: SALMAN ARIFBHAI MEMON(; Chartered Accountant: Anupama Shetty. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEO PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEO PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEO PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.