Home / Browse projects / Pune, Maharashtra / Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II

Registration lapsed No litigation declared Residential / Group Housing project

Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II

By VAISHNAVI MAHILA UNNATI SANSTHA

RG-MH-25602 · RERA P52100013110 · Last updated on MahaRERA portal: 22 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 35 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2023Possession promised35 months past this date
65 of 77Construction stages doneacross 7 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II is a Residential / Group Housing project by VAISHNAVI MAHILA UNNATI SANSTHA in Pune, Maharashtra, registered with MahaRERA as P52100013110 on 14 Sep 2017. Possession was promised by 30 Nov 2023 and is now 35 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameVaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II
  • TypeResidential / Group Housing
  • Location
    • URULI DEVACHI
    • Haveli
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100013110
  • ReraGenie IDRG-MH-25602

Builder

  • NameVAISHNAVI MAHILA UNNATI SANSTHA
  • Entity typeTrust
  • TrusteesDHANSHREE DHAIRSHEEL PATIL, APARNA SUKHDEV NAGANE, JAYSHREE TANAJI BABAR, SHUBHANGI BALASAHEB NAGANE, Bhagyashree Changdev Babar, SHWETAL DATTATRAYA NAGANE
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

35 months past promisethis monthRegisteredSep 2017First promiseMay 2022Revised toNov 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Sep 2017
  • Promised completion30 Nov 2023
  • Revised completionRevised to 30 Nov 2023 (originally 30 May 2022)
  • Buildings7 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A1NA110000
Building A2NA110000
Building B1NA100000
Building B2NA100000
Building C1NA100000
Building C2NA80000
Building DNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 22 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

65 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of Lifts, at 95%.

Building A1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building A2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building C1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building C20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 22 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes50%
Street LightingYes95%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed815

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots815
Closed/Covered704
Open Space111
BuildingClosed/CoveredOpen SpaceTotal
Building A19414108
Building A29415109
Building B19318111
Building B29314107
Building C112223145
Building C212215137
Building D861298

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI19897.89
Proposed, not sanctioned16,617 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMarket Yard

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRavindra Danve
EngineerShivkumar Arjun Puri
Chartered AccountantSuyash Pazare
PartnerRole in project
VAISHNAVI MAHILA UNNATI SANSTHA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011909May 2022 → May 2023

Reason as filed by the promoterWe required the extension to complete the work of common area and club house, construction of all the buildings in our project has already been completed upto 98% and received the NOC from the fire department but, the development of club house and common area is pending due to the COVID-19 and lockdown.

EXT52100016695May 2022 → Nov 2023

Reason as filed by the promoterOur project has been completed to the extent where we can apply for the completion certificate but the Pune municipal corporation has issued a draft notification No. PMC-2022/C.R.468/UD-22 Dated 31/03/2023 in which they have proposed to exclude the area of Uruli Devachi from the Pune Municipal Corporation limit. Because of the decision of the Pune Municipal Corporation limit the department is not accepting the application for completion of the project. We request you to consider the fact and allow us an extension of 6 month till 30/11/2023. Project details are updated which includes Updated bo

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Jan 2025

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Document 82.pdf22 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OccupancyCertificate.pdf22 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Document 82.pdf19 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Document 82.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Document 294.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate (1).pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf14 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A.pdf14 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf29 Mar 2023
Copy of the legal title reportFile: Phase-II-Land-Agreement-1.pdf6 Sep 2017
Copy of the legal title reportFile: Phase-II-Land-Agreement-2.pdf6 Sep 2017
Copy of the legal title reportFile: Phase-II-Land-Agreement-3.pdf6 Sep 2017
Copy of the legal title reportFile: Phase-II-Land-Agreement-4.pdf6 Sep 2017
Proforma of Allotment letterFile: Agr_-_RERA_-_Vaishnavi_City_Phase_II.pdf6 Sep 2017
Details of encumbrancesFile: Encumbrances.pdf1 Sep 2017
Declaration in FORM BFile: Declearation B.pdf1 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annex.pdf1 Sep 2017
Building plan approvalFile: 15.pdf31 Aug 2017
Layout approvalFile: 1.pdf31 Aug 2017
Layout approvalFile: 2.pdf31 Aug 2017
Layout approvalFile: 12.pdf31 Aug 2017
Building plan approvalFile: 3.pdf31 Aug 2017
Building plan approvalFile: 4.pdf31 Aug 2017
Building plan approvalFile: 5.pdf31 Aug 2017
Building plan approvalFile: 6.pdf31 Aug 2017
Building plan approvalFile: 7.pdf31 Aug 2017
Building plan approvalFile: 8.pdf31 Aug 2017
Building plan approvalFile: 9.pdf31 Aug 2017
Building plan approvalFile: 10.pdf31 Aug 2017
Building plan approvalFile: 11.pdf31 Aug 2017
Building plan approvalFile: 13.pdf31 Aug 2017
Building plan approvalFile: 14.pdf31 Aug 2017
PAN CardFile: PAN.pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: 1.pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: 2.pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: 12.pdf31 Aug 2017
Building Plan Approval (IOD)File: 3.pdf31 Aug 2017
Building Plan Approval (IOD)File: 4.pdf31 Aug 2017
Building Plan Approval (IOD)File: 5.pdf31 Aug 2017
Building Plan Approval (IOD)File: 6.pdf31 Aug 2017
Building Plan Approval (IOD)File: 7.pdf31 Aug 2017
Building Plan Approval (IOD)File: 8.pdf31 Aug 2017
Building Plan Approval (IOD)File: 9.pdf31 Aug 2017
Building Plan Approval (IOD)File: 10.pdf31 Aug 2017
Building Plan Approval (IOD)File: 11.pdf31 Aug 2017
Building Plan Approval (IOD)File: 13.pdf31 Aug 2017
Building Plan Approval (IOD)File: 14.pdf31 Aug 2017
Building Plan Approval (IOD)File: 15.pdf31 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf31 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate.pdf31 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf31 Aug 2017
Certificates of CA (Form 3)File: Form 3.pdf31 Aug 2017
Certificates of CA (Form 3)File: Form 3 Annexure.pdf31 Aug 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Vaishnavi Mahila Housing Group Vaishnavi City Phase ISr. no 21 1 Uruli devachi handiwadi road Pune 412308380CompletedJan 2016Jan 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vaishnavi Mahila Unnati Sanstha Vaishnavi Ci on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near URULI DEVACHI13,700+ in Pune

2 kmVaishnavi Mahila Unnati Completed 4Lapsed / revoked 6Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: VAISHNAVI MAHILA UNNATI SANSTHA

VAISHNAVI MAHILA UNNATI SANSTHA has 2 registrations on MahaRERA, including Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II and VAISHNAVI CITY PHASE 2 SECTOR 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II is delayed beyond 30 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II?

The registered promoter entity is VAISHNAVI MAHILA UNNATI SANSTHA, a trust as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II?

The professionals named in the filing: Architect: Ravindra Danve; Engineer: Shivkumar Arjun Puri; Chartered Accountant: Suyash Pazare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vaishnavi Mahila Unnati Sanstha Vaishnavi Ci to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.