Home / Browse projects / Pune, Maharashtra / SURABHI CITY PHASE 1

Registered No litigation declared Residential / Group Housing project

SURABHI CITY PHASE 1

By Surabhi Group

RG-MH-45904 · RERA P52100054701 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedmoved 24 months from the original
2 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
372 of 382Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

SURABHI CITY PHASE 1 is a Residential / Group Housing project by Surabhi Group in Pune, Maharashtra, registered with MahaRERA as P52100054701 on 6 Feb 2024. Possession is promised by 31 Dec 2030. The completion date has moved by 24 months from the original filing. 10 of the 382 units on this registration are recorded sold or booked, and 2 of 33 construction stages are filed complete.

At a glance

Project

  • NameSURABHI CITY PHASE 1
  • TypeResidential / Group Housing
  • Location
    • Somatane
    • Mawal
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054701
  • ReraGenie IDRG-MH-45904

Builder

  • NameSurabhi Group
  • Entity typeOthers
  • Named personPramod Bhimaji Narsale
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2024First promiseDec 2028Revised toDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Feb 2024
  • Promised completion31 Dec 2030
  • Revised completionRevised to 31 Dec 2030 (originally 31 Dec 2028)
  • Buildings3 building records
  • Documents filed122 files

Current status

3%10 of 382 units booked
2.6%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BuildingNA171696096
B BuildingNA17161280128
C BuildingNA17161580158

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

A Building18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Building0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Building0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered128
BuildingClosed/CoveredTotal
A Building3232
B Building3232
C Building6464

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,467 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Sep 2025
LandownerVillageDistrict
M/s Skyway Dream Homemakers through its partnersPimple NilakhPune

Approvals and building plan

Sanctioning authoritySURABHI CITY
Permissible FSI36906.29
Proposed, not sanctioned26,906 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNav Vrushali Society, Plot No 7, Aundh, Pune
Estimated costRs 50.00 cr
Cost incurredRs 1.31 cr
Work done2.63%
BuildingWingEstimatedIncurred
A BuildingNARs 16.00 crRs 40.32 lakh
B BuildingNARs 16.00 crRs 40.32 lakh
C BuildingNARs 16.00 crRs 40.32 lakh
-NARs 2.00 crRs 10.49 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshitosh Shinde
ArchitectCmetrica Designers LLP
EngineerVijay Gadade
EngineerASWINI POL
Chartered AccountantSuhas Sathe
PartnerRole in project
SURABHI GROUP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16012619468Dec 2028 → Dec 2030

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred primarily due to prolonged heavy rains in the region. As the project site is located in a mountainous and forested area, the terrain becomes highly challenging during the monsoon season. Continuous rainfall led to unstable soil conditions, restricted access for machinery, and unsafe working conditions for labour, resulting in unavoidable suspension and slowdown of construction activities. Additionally, due to the difficult topography and environmental sensitivity of the area,

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1- Surbhi city phase -1 as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2 - Surbhi city phase -1 as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 3File: Form 3 - Surbhi city phase -1 as on June 2026.pdf16 Jul 2026
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on March 2026.pdf7 May 2026
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on March 2026.pdf7 May 2026
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on March 2026.pdf7 May 2026
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on March 2026.pdf29 Apr 2026
Building plan approvalFile: PLAN 10_compressed.pdf23 Mar 2026
Building plan approvalFile: PLAN 11.pdf23 Mar 2026
Building plan approvalFile: PLAN 12_compressed.pdf23 Mar 2026
Building plan approvalFile: PLAN 13.pdf23 Mar 2026
Building plan approvalFile: PLAN 14.pdf23 Mar 2026
Building plan approvalFile: PLAN 15.pdf23 Mar 2026
Building plan approvalFile: PLAN 16.pdf23 Mar 2026
Building plan approvalFile: PLAN 17.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Dec 2025.pdf18 Jan 2026
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Dec 2025.pdf18 Jan 2026
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Dec 2025.pdf18 Jan 2026
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf10 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf10 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf10 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf3 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf3 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf3 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2025.pdf28 Oct 2025
Form 1File: Form 1 - Surabhi City Phase I as on March 2024.pdf27 Oct 2025
Form 2File: Form 2 - Surabhi City Phase I as on March 2024.pdf27 Oct 2025
Form 3File: Form 3 - Surabhi City Phase I as on March 2024.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Surabhi City Phase I as on March 2024.pdf27 Oct 2025
Form 1File: Form 1 - Surabhi City Phase 1 as on June 2024.pdf27 Oct 2025
Form 2File: Form 2 - Surabhi City Phase 1 as on June 2024.pdf27 Oct 2025
Form 3File: Form 3 - Surabhi City Phase 1 as on June 2024.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Surabhi City Phase 1 as on June 2024.pdf27 Oct 2025
Form 1File: Form 1 - Surabhi City Phase 1 as on Sep 2024.pdf27 Oct 2025
Form 2File: Form 2 - Surabhi City Phase 1 as on Sep 2024.pdf27 Oct 2025
Form 3File: Form 3 - Surabhi City Phase 1 as on Sep 2024.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Surabhi City Phase 1 as on Sep 2024.pdf27 Oct 2025
Form 1File: Form 1 - Surabhi City Phase 1 as on Dec 2024.pdf27 Oct 2025
Form 2File: Form 2 - Surabhi City Phase 1 as on Dec 2024.pdf27 Oct 2025
Form 3File: Form 3 - Surabhi City Phase 1 as on Dec 2024.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Surabhi City Phase 1 as on Dec 2024.pdf27 Oct 2025
Form 1File: Form 1 - Surabhi City Phase 1 as on March 2025.pdf27 Oct 2025
Form 2File: Form 2 - Surabhi City Phase 1 as on March 2025.pdf27 Oct 2025
Form 3File: Form 3 - Surabhi City Phase 1 as on March 2025.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Surabhi City Phase 1 as on March 2025.pdf27 Oct 2025
Form 1File: Surabhi City Phase I - Form 1 - 30-06-2025.pdf7 Aug 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SURABHI SHREEP52100015268SUS GAON, Pune36Feb 2018CompletedDec 2024Registered original: Dec 2019Dec 2024

How this compares with Pune

3%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SURABHI CITY PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Somatane13,700+ in Pune

2 kmSURABHI CITY PHASE 1Completed 14Lapsed / revoked 9Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: Surabhi Group

Surabhi Group has 1 registration on MahaRERA, including SURABHI CITY PHASE 1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SURABHI CITY PHASE 1 is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SURABHI CITY PHASE 1?

The registered promoter entity is Surabhi Group, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SURABHI CITY PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SURABHI CITY PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SURABHI CITY PHASE 1?

The professionals named in the filing: Architect: Ashitosh Shinde; Architect: Cmetrica Designers LLP; Engineer: Vijay Gadade; Engineer: ASWINI POL; Chartered Accountant: Suhas Sathe. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SURABHI CITY PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SURABHI CITY PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SURABHI CITY PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.