Home / Browse projects / Pune, Maharashtra / ABHIMAAN HOMES PHASE 3
ABHIMAAN HOMES PHASE 3
RG-MH-22682 · RERA P52100032485 · Last updated on MahaRERA portal: 23 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 4 months
- 1 extension taken
- Rs 500.00 crore secured on the land, in favour of ICICI BANK LTD
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ABHIMAAN HOMES PHASE 3 is a Residential / Group Housing project by RISING PROPCON LLP in Pune, Maharashtra, registered with MahaRERA as P52100032485 on 10 Jan 2022. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months from the original filing. 448 of the 521 units on this registration are recorded sold or booked, and 55 of 55 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameABHIMAAN HOMES PHASE 3
- TypeResidential / Group Housing
- Location
- GAT NO 8 12 16 18 TO 20 AT POST SHIRGAON
- OPP PRATI SHIRDI TEMPLE TAL MAVAL DIST PUNE
- Shirgaon
- Mawal
- Pune
- 410506
- Pincode410506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032485
- ReraGenie IDRG-MH-22682
Builder
- NameRISING PROPCON LLP
- Entity typePartnership
- PartnersMANOJKUMAR VIRENDRAKUMAR GUPTA, VINEET KRISHNAKUMAR GOYAL
- Other registrations2 more →
- Completed2 of 3
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Jan 2022
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
- Buildings5 building records
- Documents filed146 files
Current status
Figures as on 23 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 15 | 14 | 110 | 0 | 110 |
| A2 | NA | 14 | 14 | 110 | 0 | 110 |
| A3 | NA | 14 | 14 | 110 | 0 | 110 |
| B1 | NA | 15 | 14 | 110 | 0 | 110 |
| B2 | NA | 14 | 11 | 81 | 0 | 81 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 23 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
55 of 55 construction stages are filed complete across 5 buildings.
A1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed375
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A1 | 55 | 20 | 75 |
| A2 | 55 | 20 | 75 |
| A3 | 55 | 20 | 75 |
| B1 | 55 | 20 | 75 |
| B2 | 55 | 20 | 75 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B1 | NA | Rs 22.78 cr | Rs 17.27 cr |
| B2 | NA | Rs 18.98 cr | Rs 17.27 cr |
| A2 | NA | Rs 18.03 cr | Rs 17.27 cr |
| A3 | NA | Rs 18.03 cr | Rs 17.27 cr |
| A1 | NA | Rs 17.08 cr | Rs 17.27 cr |
| - | NA | Rs 5.00 cr | Rs 7.93 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK ARCHITECTURE |
| Engineer | Planedge Consultants Pvt. Ltd. |
| Chartered Accountant | JAYESH JAIN & ASSOCIATES |
| Chartered Accountant | BHANDARI S A A J & ASSOCIATES |
| Partner | Role in project |
|---|---|
| RISING PROPCON LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501856 | Adv Shreya Anup Hadgaonkar | Arvind Kumar Bhardwaj | 06/06/2025 |
| SM12500245 | Ram Gawali | RISING PROPCON LLP | 29/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2027
Documents filed146
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 146 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A-Abhiman.pdf | 23 Sep 2026 |
| Form 5 (FY 2025-2026)File: Form 05_Abhiman..pdf | 7 Sep 2026 |
| Withdrawal Update Form 1File: Abhiman 3.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 02_Abhiman.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 03_Abhiman.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1_ABHIMAAN HOMES III.pdf | 23 Apr 2026 |
| Withdrawal Update Form 2File: Form 02_Abhimaan Homes III.pdf | 23 Apr 2026 |
| Withdrawal Update Form 3File: Form 03_ Abhimaan Homes.pdf | 23 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1_ABHIMAAN HOMES III.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 02_Abhiman.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 21 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ABHIMAAN HOMES III.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 02_Abhiman.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 03_Abhiman.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1- K ABHIMAAN HOMES.pdf | 3 Jan 2026 |
| Withdrawal Update Form 2File: Form 02_Abhimaan.pdf | 3 Jan 2026 |
| Withdrawal Update Form 3File: Form 03_Abhiman.pdf | 3 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A_abhiman.pdf | 15 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 05_Abhiman Homes III.pdf | 8 Nov 2025 |
| Withdrawal Update Form 1File: FORM 1- K ABHIMAAN HOMES.pdf | 19 Oct 2025 |
| Withdrawal Update Form 2File: Form 02_Abhimaan.pdf | 19 Oct 2025 |
| Withdrawal Update Form 3File: Form 03_Abhiman.pdf | 19 Oct 2025 |
| Withdrawal Update Form 1File: Abhiman 3.pdf | 2 Aug 2025 |
| Withdrawal Update Form 2File: Form 02_Abhiman III.pdf | 2 Aug 2025 |
| Withdrawal Update Form 3File: Form 03_Abhiman Homes.pdf | 2 Aug 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02_Abhiman.pdf | 12 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 03_Abhiman.pdf | 9 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_K ABHIMAAN.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLSURE OF INVENTORY.pdf | 12 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ABHIMAN HOMES III.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ABHIMAN HOMES III.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Abhiman Homes 3.pdf | 20 Jan 2025 |
| Layout approvalFile: 01.pdf | 18 Dec 2024 |
| Building plan approvalFile: 02.pdf | 18 Dec 2024 |
| Building plan approvalFile: 03.pdf | 18 Dec 2024 |
| Building plan approvalFile: 07.pdf | 18 Dec 2024 |
| Building plan approvalFile: 04.pdf | 18 Dec 2024 |
| Building plan approvalFile: 05.pdf | 18 Dec 2024 |
| Building plan approvalFile: 06.pdf | 18 Dec 2024 |
| Building plan approvalFile: 08.pdf | 18 Dec 2024 |
| Building plan approvalFile: 09.pdf | 18 Dec 2024 |
| Building plan approvalFile: 10.pdf | 18 Dec 2024 |
| Building plan approvalFile: 11.pdf | 18 Dec 2024 |
| Building plan approvalFile: 12.pdf | 18 Dec 2024 |
| Building plan approvalFile: 13.pdf | 18 Dec 2024 |
| Building plan approvalFile: 14.pdf | 18 Dec 2024 |
| Building plan approvalFile: 15.pdf | 18 Dec 2024 |
| Building plan approvalFile: 16.pdf | 18 Dec 2024 |
| Building plan approvalFile: 17.pdf | 18 Dec 2024 |
| Building plan approvalFile: 18.pdf | 18 Dec 2024 |
| Building plan approvalFile: 19.pdf | 18 Dec 2024 |
| Building plan approvalFile: 20.pdf | 18 Dec 2024 |
| Building plan approvalFile: 21.pdf | 18 Dec 2024 |
| Building plan approvalFile: 22.pdf | 18 Dec 2024 |
| Building plan approvalFile: 23.pdf | 18 Dec 2024 |
| Building plan approvalFile: 23.pdf | 18 Dec 2024 |
| Building plan approvalFile: 25.pdf | 18 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: 01.pdf | 18 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Abhiman Form 3.pdf | 18 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 230927 - CC.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 15.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 11.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 16.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 17.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 18.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 19.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 20.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 21.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 22.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 23.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 23.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 25.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 14.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 13.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 12.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 10.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 09.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 08.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 06.pdf | 18 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 05.pdf | 18 Dec 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 146 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ABHIMAAN HOMES PHASE 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near OPP PRATI SHIRDI TEMPLE TAL MAVAL DIST PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Vaarivana Phase A - 1
Sanjivani Integrated Township LLP
Builder: RISING PROPCON LLP
RISING PROPCON LLP has 3 registrations on MahaRERA, including ABHIMAAN HOMES PHASE I and ABHIMAAN HOMES PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ABHIMAAN HOMES PHASE 3 is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ABHIMAAN HOMES PHASE 3?
The registered promoter entity is RISING PROPCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ABHIMAAN HOMES PHASE 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ABHIMAAN HOMES PHASE 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ABHIMAAN HOMES PHASE 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ABHIMAAN HOMES PHASE 3?
The professionals named in the filing: Architect: VK ARCHITECTURE; Engineer: Planedge Consultants Pvt. Ltd.; Chartered Accountant: JAYESH JAIN & ASSOCIATES; Chartered Accountant: BHANDARI S A A J & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ABHIMAAN HOMES PHASE 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback