Home / Browse projects / Pune, Maharashtra / Urban Life Phase 1

Registered No litigation declared Residential / Group Housing project

Urban Life Phase 1

By Kakade Vtp Associates

RG-MH-08466 · RERA P52100001269 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 16 complaints at MahaRERA
  • Completion date moved by 60 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 60 months from the original
30 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
135 of 343Units unsoldnot recorded sold or booked
16Complaints at MahaRERAon this registration
Jump to the 182 documents Report an error

Urban Life Phase 1 is a Residential / Group Housing project by Kakade Vtp Associates in Pune, Maharashtra, registered with MahaRERA as P52100001269 on 27 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 60 months from the original filing. 208 of the 343 units on this registration are recorded sold or booked, and 30 of 44 construction stages are filed complete. 16 complaints are on record with the regulator.

At a glance

Project

  • NameUrban Life Phase 1
  • TypeResidential / Group Housing
  • Location
    • 81 Part
    • Talegaon Dabhade (R)
    • Mawal
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001269
  • ReraGenie IDRG-MH-08466

Builder

  • NameKakade Vtp Associates
  • Entity typePartnership
  • PartnerNilesh Vilas Palresha
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2017First promiseDec 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2021)
  • Buildings4 building records
  • Documents filed182 files

Current status

61%208 of 343 units booked
76.9%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C wingNA131284084
D WingNA131284084
H WingNA171068270
I WingNA17151050105

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

C wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed378

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots378
Closed/Covered87
Open Space291
BuildingClosed/CoveredOpen SpaceTotal
C wing206484
D Wing206484
H Wing1887105
I Wing2976105

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,205 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Oct 2025
LandownerVillageDistrict
Purnanand Co operative Housing Society Ltd-Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority, Pune (PMRDA)
Permissible FSI21007.8
Proposed, not sanctioned19,066 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPune Nagar Road, Pune 14
Estimated costRs 62.22 cr
Cost incurredRs 47.82 cr
Work done76.86%
BuildingWingEstimatedIncurred
I WingNARs 16.55 crRs 16.55 cr
H WingNARs 16.28 crRs 1.88 cr
C wingNARs 13.33 crRs 13.33 cr
D WingNARs 12.06 crRs 12.06 cr
-NARs 4.00 crRs 4.00 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkur Associates
ArchitectMINOTI PATIL
ArchitectMINOTI SAWANT
ArchitectReza Kabul
ArchitectMinal Firake
EngineerJ W Consultants
EngineerVINOD TALELE
Chartered AccountantSAC & CO LLP
Chartered AccountantSUNIL SHAH
PartnerRole in project
Kakade Vtp Associates-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002289Dec 2021 → Dec 2022

Reason as filed by the promoterMigration of project from PMRDA to nagar panchayat .Due to this project sanction and progress delayed

EXT52100018662Dec 2021 → Dec 2024

Reason as filed by the promoterThe project is delayed due to (1) the Land under project was moved from Pune Metropolitan Region Development Authority (PMRDA) to Vadagon Nagara Panchayat and later further moved to Vadagaon Maval Nagar Panchayat, this transition delayed procedural aspect in approvals (2) Due to Pandemic COVID-19, the operations of the project were substantially affected in the absence of material and unavailability of labour, hence the operations were severally affected for long time, hence the construction activities were affected and delayed the completion of project (3) The Occupancy Certificate for Tower

EXT52100027120Dec 2021 → Dec 2025

Reason as filed by the promoter1. Project Details: The promoter has registered the project ‘Urban Life Phase 1’ with the Maharashtra Real Estate Regulatory Authority vide no P52100001269. 2. The project is delayed due to: i)There is huge unsold stock in the project for which sale and banking, extension is required ii) The Land under project was moved from Pune Metropolitan Region Development Authority (PMRDA) to Vadagon Nagara Panchayat and later further moved to Vadagaon Maval Nagar Panchayat, this transition delayed procedural aspect in approvals. iii) Delay Due to Pandemic: The COVID-19 pandemic significantly disrupted t

EA30052621167Dec 2021 → Dec 2026

Reason as filed by the promoter1. The project stands at 95% completion. 2. The consent of 58.99% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- The delay in completion of the project is primarily due to the pending Part Occupancy Certificate for the balance portion of the project. The Promoter has already obtained Part Occupancy Certificate dated 09/01/2026 from Vadgaon Maval Nagar Panchayat for C, D & I Wings, and possession of the respective units has

Complaints filed with MahaRERA16

Case no.ComplainantRespondentFiled
CC005000000022430Shweta Dattatray UplanchiwarKakade VTP Associates14/01/2019
CC005000000054217KAKADE VTP ASSOCIATESKAKADE VTP ASSOCIATES23/05/2020
CC005000000054216KAKADE VTP ASSOCIATESKAKADE VTP ASSOCIATES23/05/2020
CC005000000064227SHYAM SUBHAHS SONARurban vtp life and associates08/08/2021
CC005000000064654VINAY SHARMAKakade VTP Associates24/09/2020
CC005000000064737GAURAV GOVINDKRISHNA SONARKakade VTP Associates21/10/2020
CC005000000340889Gaurav GovindKrishna SonarKakade VTP associates07/05/2024
CC005000000095871JITENDRA V SHINDEKAKADE VTP ASSOCIATES09/08/2021
CC005000000258990KRISHNAPRASAD GOPINATHAN NAIRKAKADE VTP ASSOCIATES25/06/2023
CC005000000106763Ms. Sumitra Pradeep Kamble Alias Mrs. Sumitra Kapil MoreKAKADE VTP ASSOCIATES Through its Partner Mr. Anil Balasaheb Kakade15/03/2022
CC12400053Kakade Vtp AssociatesVIJENDER SHOKAND06/09/2024
CC12500845Akshay Siddeshwar TodkarKakade Vtp Associates11/03/2025
CC12503799Akshay Siddeshwar TodkarKakade Vtp Associates30/10/2025
CC12504018Ankur Sham LalKakade Vtp Associates14/11/2025
CC12602467HEERAL MILAN MADANIKakade Vtp Associates27/04/2026
CC12605191Kakade Vtp AssociatesHeeral Milan Mandani (Allottee)14/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Mar 2023

Documents filed182

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 182 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 URBAN LIFE PHASE JUN26.pdf20 Jul 2026
Withdrawal Update Form 2File: form 2 urban life phase 1.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3_URBAN LIFE COMPRESSED.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A- URBAN LIFE PHASE 1.pdf20 Jun 2026
Withdrawal Update Form 1File: FORM 1 Urban Life phase 1.pdf5 Jun 2026
Withdrawal Update Form 2File: FORM 2 31032026.pdf5 Jun 2026
Withdrawal Update Form 3File: Form 3 31032026 f.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM-1 urban life phase 1 20012026.pdf6 Feb 2026
Withdrawal Update Form 2File: Form-2 Engineer Certificate Urban Life 31-12-2025.pdf6 Feb 2026
Withdrawal Update Form 3File: Form-3 Kakade VTP Associates (VTP Urbanlife)_11zon.pdf6 Feb 2026
Withdrawal Update Form 1File: FORM 1 URBAN LIFE PHASE 1.pdf17 Oct 2025
Withdrawal Update Form 1File: FORM 1 URBAN LIFE PHASE 1.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM 2 URBAN LIFE PHASE 1.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM 2 URBAN LIFE PHASE 1.pdf17 Oct 2025
Withdrawal Update Form 3File: FORM 3 URBAN LIFE PHASE 1_11zon (1).pdf17 Oct 2025
Withdrawal Update Form 3File: FORM 3 URBAN LIFE PHASE 1_11zon (1).pdf17 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 URBAN LIFE PHASE 1.pdf28 Aug 2025
Certificates of CA (Form 3)File: FORM 3 Urban Life.pdf23 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Urban life phase 1.pdf23 Apr 2025
Certificates of CA (Form 3)File: Form 3 Kakade - Urban life 18022025_compressed.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM- 5 -KAKADE VTP-Urban Life Phase 1.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: URBAN LIFE INVENTORY 17022025.pdf17 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec-24 Kakade VTP Associates.pdf16 Jan 2025
Certificates of CA (Form 3)File: Form 3 Urban Life 31122024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: URBAN LIFE 31122024.pdf14 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 URBAN LIFE PHASE 1 31122024.pdf13 Jan 2025
Declaration in FORM BFile: FORM B- URBAN LIFE PHASE 1.pdf10 Jan 2025
Declaration in FORM BFile: urban life form b.pdf10 Jan 2025
Certificates of CA (Form 3)File: FORM 3 URBAN LIFE PHASE 1.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 URBAN LIFE PHASE 1 30092024.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Urban Life phase1 300624.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: URBAN LIFE PH1 30092024.pdf16 Oct 2024
Certificates of CA (Form 3)File: Form-3 _kakade VTP Associates(Urban Life) _30-09-2024.pdf15 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_kakade VTP Associates (Urban Life)_30-09-2024.pdf15 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Urban life Phase 1 30062024.pdf20 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 urban life.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: URBANLIFE PHASE 1 30062024.pdf17 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A URBAN LIFE 31032024.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: INVENTORY URBAN LIFE PHASE 1 31032024.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 URBANLIFE PHASE 1 31032024.pdf6 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 URBAN LIFE PHASE 1 31032024.pdf6 May 2024
Certificates of CA (Form 3)File: FORM 3 URBAN LIFE PHASE 1 31032024.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: 13 INVENTORY 31032021.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 12 INVENTORY 30062021.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 11 INVENTORY 30092021.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 10 INVENTORY 31122021.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 9 INVENTORY 31032022.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 8 INVENTORY 30062022.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 7 INVENTORY 30092022.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 6 INVENTORY 31122022.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 5 INVENTORY 31032023.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 4 INVENTORY 30062023.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 3 INVENTORY 30092023.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 2 INVENTORY 31122023.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: 1 INVENTORY 11032024.pdf22 Mar 2024
Certificates of CA (Form 3)File: FORM 3 URBANLIFE PHASE 1 15032024.pdf22 Mar 2024
Layout approvalFile: Sanction layout Buildng.pdf13 Mar 2024
Layout approvalFile: 08-24.pdf13 Mar 2024
Layout approvalFile: 09-24.pdf13 Mar 2024
Layout approvalFile: 11-24.pdf13 Mar 2024
Layout approvalFile: 12-24.pdf13 Mar 2024
Layout approvalFile: 18-24.pdf13 Mar 2024
Layout approvalFile: 19-24.pdf13 Mar 2024
Layout approvalFile: 21-24.pdf13 Mar 2024
Layout approvalFile: 22-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: Sanction layout Buildng.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 08-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 09-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 11-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 12-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 18-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 19-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 21-24.pdf13 Mar 2024
Copy of Layout Approval (in case of layout)File: 22-24.pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: INVENTORY 11032024.pdf12 Mar 2024
Layout approvalFile: 11 - D Wing.pdf31 Jan 2024
Layout approvalFile: 12.pdf31 Jan 2024
Layout approvalFile: 13.pdf31 Jan 2024
Layout approvalFile: 18 - H Wing.pdf31 Jan 2024
Layout approvalFile: 19.pdf31 Jan 2024

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Urban Life Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Talegaon Dabhade (R)13,700+ in Pune

2 kmUrban Life Phase 1Completed 55Lapsed / revoked 36Other 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 138 registered projects within 2 km.

Builder: Kakade Vtp Associates

Kakade Vtp Associates has 2 registrations on MahaRERA, including Urban Life Phase 1 and Urbanlife plotting. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Urban Life Phase 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Urban Life Phase 1?

The registered promoter entity is Kakade Vtp Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Urban Life Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Urban Life Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Urban Life Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Urban Life Phase 1?

The professionals named in the filing: Architect: Ankur Associates; Architect: MINOTI PATIL; Architect: MINOTI SAWANT; Architect: Reza Kabul; Architect: Minal Firake; Engineer: J W Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Urban Life Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Urban Life Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Urban Life Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.