Vainta Residency
RG-MH-82054 · RERA P52900007947 · Last updated on MahaRERA portal: 15 Oct 2021
Source: official MahaRERA filing
Red flags
- Completion date moved by 47 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vainta Residency is a Residential / Group Housing project by Sthapatya Realtors in Sindhudurg, Maharashtra, registered with MahaRERA as P52900007947 on 18 Aug 2017. The registration is recorded completed; possession was promised by 5 May 2022. The completion date has moved by 47 months from the original filing.
At a glance
Project
- NameVainta Residency
- TypeResidential / Group Housing
- Location
- Kankavali
- Kankavli
- Sindhudurg
- 416602
- Pincode416602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52900007947
- ReraGenie IDRG-MH-82054
Builder
- NameSthapatya Realtors
- Entity typePartnership
- PartnersAmit Sahadeo Rane, Prashant Vasudev Mayekar, Siddhesh Dattatray Pednekar, Prashant Vasant Bhoi
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 Aug 2017
- Promised completion5 May 2022
- Revised completionRevised to 5 May 2022 (originally 30 Jun 2018)
- Buildings1 building record
- Documents filed17 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vanita Residency | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Vanita Residency: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Neha Rumade |
| Engineer | Gireesh Rajadhyaksha |
| Partner | Role in project |
|---|---|
| Sthapatya Realtors | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed construction work of our building but we have not obtained OC from Nagar Panchayat as we are waiting for clearance of Unified Development Control and Promotion Regulations; and for Registration of agreements and sell of unsold flats we need further extension.
Reason as filed by the promoterProject delivery dates are getting delayed because of non availability of building material (Especially Sand) and skilled labors. Also lack of finances due to declining real estate market was a major reason for the delay. Overall building structure is ready on site and internal and external plaster complete. Only finishing work is pending (Flooring, plumbing and door window installation)
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Oct 2021
Documents filed17
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 15 Oct 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf | 15 Oct 2021 |
| Declaration in FORM BFile: Form B.pdf | 1 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vanita Residency_Architect's Certificate.pdf | 1 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Engineers's Certificate) Vanita Residency.pdf | 1 Aug 2017 |
| Certificates of CA (Form 3)File: Vanita Residency - CA Certificate.pdf | 1 Aug 2017 |
| OtherFile: Declaration on Plot Area.pdf | 1 Aug 2017 |
| Layout approvalFile: Approval Dwg_01.pdf | 31 Jul 2017 |
| Building plan approvalFile: Approval Dwg_02.pdf | 31 Jul 2017 |
| Building plan approvalFile: Approval Dwg_01.pdf | 31 Jul 2017 |
| PAN CardFile: PAN CARD.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: NON ENCUMBRANCE CERTIFICATE.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Approval Dwg_01.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Approval Dwg_01.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Approval Dwg_02.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Declaration - Agreement For Sale.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 17 filed documents as one ZIP, foldered, with a manifest
Keep Vainta Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kankavali530+ in Sindhudurg
Filed coordinates, straight-line distance. 40 registered projects within 2 km.
KANAK PARADISE
TRIVENI BUILDERS AND DEVELOPERS
MAITRI GARDEN
MAITRI DEVELOPERS
SINDHU PRATAP COMPLEX
AMEY HOMES
RADHA-KRUSHNA NAGARI
MAYURESH DEVELOPERS
Adinath Residency
DS Ventures
Shiv-Shankar Plaza
Chintamani Dasharath Kalyankar
See every Sindhudurg project, with the district possession charts
Builder: Sthapatya Realtors
Sthapatya Realtors has 1 registration on MahaRERA, including Vainta Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What are my rights if Vainta Residency is delayed beyond 5 May 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vainta Residency?
The registered promoter entity is Sthapatya Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vainta Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vainta Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vainta Residency?
The professionals named in the filing: Architect: Neha Rumade; Engineer: Gireesh Rajadhyaksha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vainta Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback