Home / Browse projects / Sindhudurg, Maharashtra / KANAK PARADISE
KANAK PARADISE
By TRIVENI BUILDERS AND DEVELOPERS
RG-MH-04491 · RERA P52900021858 · Last updated on MahaRERA portal: 9 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KANAK PARADISE is a Others project by TRIVENI BUILDERS AND DEVELOPERS in Sindhudurg, Maharashtra, registered with MahaRERA as P52900021858 on 5 Aug 2019. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 68 of the 150 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete.
At a glance
Project
- NameKANAK PARADISE
- TypeOthers
- Location
- KANKAVLI
- Kankavali
- Sindhudurg
- 416602
- Pincode416602
- RERA no.P52900021858
- ReraGenie IDRG-MH-04491
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2019
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 30 Dec 2022)
- Buildings4 building records
- Documents filed109 files
Current status
Figures as on 9 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 5 | 5 | 30 | 0 | 30 |
| B | NA | 5 | 4 | 48 | 10 | 58 |
| C | NA | 5 | 4 | 32 | 0 | 32 |
| D | NA | 5 | 5 | 30 | 0 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 33 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
A40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 80% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 30% |
| Water conservation /Rain water harvesting | Yes | 60% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed287
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| A | 82 | 82 |
| B | 82 | 82 |
| C | 52 | 52 |
| D | 71 | 71 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VIJAY RAMCHANDRA PATKAR | Ratnagiri (M Cl) | Ratnagiri |
| SAMIR HUSSENALI ESSANI | - | North Goa |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRATHMESH ARUN SAMANT |
| Engineer | UTTAM D MANKAR |
| Chartered Accountant | SUDHIR GANESH NAIK |
| Chartered Accountant | Amol Gajanan Khanolkar |
| Chartered Accountant | Girish Suresh Tirodkar |
| Partner | Role in project |
|---|---|
| TRIVENI BUILDERS AND DEVELOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTHERE IS MAJOR CHANGE IN EARLIER BUILDING APPROVED PLAN. THE SAID CHANGE IS APPROVED BY RESPECTIVE GOVERNMENT AUTHORITY ON DATED 10.05.2022, COPY OF WHICH ENCLOSED HEREWITH. SINCE PLAN IS CHANGED, TO INCORPORATE THIS CHANGES WE REQUIRED SOME TIME. SO PLEASE EXTENT OUR PROJECT EXPIRY DATE FROM 30.12.2022 TO 31.12.2023.
Reason as filed by the promoterWE HEREBY APPLIED FOR EXTENTION U/S 7(3) FOR OUR RESPECTIVE PROJECT AS PRESCRIBE UNDER CIRCULAR 07/2019 DATED 08/02/2019.
Reason as filed by the promoterAs per local authority i got increased FSI for which i have taken the correction certificate from RERA on 17/07/2024. so want few more time to complete my project with completion certificate which is in process.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 Mar 2023
Documents filed109
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Triveni Form-5.pdf | 9 Jul 2026 |
| Form 1File: Form 1 March2025.pdf | 17 Feb 2026 |
| Form 2File: FORM 2 March 2025.pdf | 17 Feb 2026 |
| Form 3File: Form-3 March 2025.pdf | 17 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory.pdf | 17 Feb 2026 |
| Form 1File: Form 1 March2025.pdf | 17 Feb 2026 |
| Form 2File: FORM 2 March 2025.pdf | 17 Feb 2026 |
| Form 3File: Form-3 March 2025.pdf | 17 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory.pdf | 17 Feb 2026 |
| Form 1File: Form 1 March2025.pdf | 17 Feb 2026 |
| Form 2File: FORM 2 March 2025.pdf | 17 Feb 2026 |
| Form 3File: Form-3 March 2025.pdf | 17 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory.pdf | 17 Feb 2026 |
| Form 1File: Form 1 March2025.pdf | 17 Feb 2026 |
| Form 2File: FORM 2 March 2025.pdf | 17 Feb 2026 |
| Form 3File: Form-3 March 2025.pdf | 17 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory.pdf | 17 Feb 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A - Quality Assurance (1).pdf | 17 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form-5 Triveni.pdf | 13 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form-5 Triveni.pdf | 13 Feb 2026 |
| Declaration in FORM BFile: NEW FORM-B TRIVENI_compressed.pdf | 17 Mar 2025 |
| CERSAI detailsFile: CERSAI UNDERTAKING (1).pdf | 10 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf | 10 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser of intrest 1ST PARTNER.pdf | 10 Feb 2025 |
| Declaration in FORM BFile: FORM-B.pdf | 22 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE T.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE (2).pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Triveni Builders FORM 1.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Triveni builders FORM 2.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 TRIVENI.pdf | 21 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Triveni builders SOLD BOOK.pdf | 21 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Triveni Builders FORM 1.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 TRIVENI.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Triveni builders FORM 2.pdf | 21 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Triveni builders SOLD BOOK.pdf | 21 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Triveni Builders.pdf | 17 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 2 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Engineer Certificate - DONE (1).pdf | 2 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A (1).pdf | 2 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: sold inventory.pdf | 2 Jul 2024 |
| Certificates of CA (Form 3)File: form3_compressed.pdf | 2 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate TRI.pdf | 28 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate TRI.pdf | 28 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate TRI.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Ca certificate tri.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Ca certificate tri.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Ca certificate tri.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: Ca certificate tri.pdf | 28 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: File0022.PDF | 29 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: File0023.PDF | 29 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: File0024.PDF | 29 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: self Certification Bank.pdf | 31 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: self Certification Bank.pdf | 31 Jan 2024 |
| Certificates of CA (Form 3)File: self Certification Bank.pdf | 31 Jan 2024 |
| Declaration in FORM BFile: FORM B TRI.pdf | 25 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Triveni.pdf | 6 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold info.pdf | 26 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT.pdf | 11 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ENGIN.pdf | 11 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Triven.pdf | 11 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA FORM 5.pdf | 7 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHI CERTIFICATE.pdf | 18 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 18 Jul 2023 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 18 Jul 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B- building oc.pdf | 13 Mar 2023 |
| Declaration about Commencement CertificateFile: FORMAT D.pdf | 2 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 2 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 2 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: BOOK SOLD DATA.pdf | 2 Dec 2022 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 2 Dec 2022 |
| OtherFile: EXTENTION APPLICATION.pdf | 2 Dec 2022 |
| OtherFile: FORMAT C.pdf | 2 Dec 2022 |
| Building plan approvalFile: CHANGE PLAN.pdf | 3 Nov 2022 |
| Building Plan Approval (IOD)File: CHANGE PLAN.pdf | 3 Nov 2022 |
| Building plan approvalFile: CHANGE PLAN APPROVAL.pdf | 22 Oct 2022 |
| Building Plan Approval (IOD)File: CHANGE PLAN APPROVAL.pdf | 22 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM V.pdf | 22 Oct 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: C BUILDING COMPLETION.pdf | 22 Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 109 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KANAK PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KANKAVLI530+ in Sindhudurg
MAITRI GARDEN
MAITRI DEVELOPERS
SINDHU PRATAP COMPLEX
AMEY HOMES
RADHA-KRUSHNA NAGARI
MAYURESH DEVELOPERS
Adinath Residency
DS Ventures
Shiv-Shankar Plaza
Chintamani Dasharath Kalyankar
Shree Bhairee Ganesh Sankul- Phase 1
ATUL SURESH RAORANE
See every Sindhudurg project, with the district possession charts
Builder: TRIVENI BUILDERS AND DEVELOPERS
TRIVENI BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including TRIVENI HEIGHTS and KANAK PARADISE. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What does it mean that KANAK PARADISE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KANAK PARADISE is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KANAK PARADISE?
The registered promoter entity is TRIVENI BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KANAK PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KANAK PARADISE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KANAK PARADISE?
The professionals named in the filing: Architect: PRATHMESH ARUN SAMANT; Engineer: UTTAM D MANKAR; Chartered Accountant: SUDHIR GANESH NAIK; Chartered Accountant: Amol Gajanan Khanolkar; Chartered Accountant: Girish Suresh Tirodkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KANAK PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback