Home / Browse projects / Mumbai Suburban, Maharashtra / Vaidya Cottage CHS Ltd

Completed No litigation declared Residential / Group Housing project

Vaidya Cottage CHS Ltd

By Shamik Enterprises Pvt Ltd.

RG-MH-19908 · RERA P51800001902 · Last updated on MahaRERA portal: 23 Aug 2021

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 16 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2021Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Vaidya Cottage CHS Ltd is a Residential / Group Housing project by Shamik Enterprises Pvt Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001902 on 29 Jul 2017. The registration is recorded completed; possession was promised by 30 Oct 2021. The completion date has moved by 16 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameVaidya Cottage CHS Ltd
  • TypeResidential / Group Housing
  • Location
    • Park Road
    • Vile Parle (east)
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001902
  • ReraGenie IDRG-MH-19908

Builder

  • NameShamik Enterprises Pvt Ltd.
  • Entity typeCompany
  • ChairpersonHaresh Sankalchand Hirani
  • Other registrations7 more →
  • Completed4 of 8
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2017First promiseJun 2020Revised toOct 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2017
  • Promised completion30 Oct 2021
  • Revised completionRevised to 30 Oct 2021 (originally 29 Jun 2020)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shamik Crimson BayNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Shamik Crimson Bay: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered43

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area960 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2589.58
Proposed, not sanctioned2,590 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManek Smruti, TPS II, Nehru Road, Vile Parle East, Mumbai-400057

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHMJ Architects
EngineerSura and Associates
PartnerRole in project
Shamik Enterprises Pvt Ltd.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001937Jun 2020 → Jun 2020

Reason as filed by the promoterThe project is registered in MahaRERA vide registration No. P51800001902. The proposed date of completion as per RERA registration is 30/06/2019. The development work of "Vaidya Cottage Chs Ltd" project is in progress and the entire RCC work is completed. The brick work and plastering of walls is in progress. The promoter could not complete the work due to site constrains and various other reasons. But now the major RCC work is completed and rest work will be completed in a extended time. Therefore, the promoter requesting the Hon. Authority to extend the time to complete the project upto 29/0

EXT51800009127Jun 2020 → Apr 2021

Reason as filed by the promoterThe letter is been drafted after taking into consideration all the requirements and this is out sincere request to maharashtra real estate regulatory authority and development Act, 2016 to kindly grant us the extension for the same

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000195212ROHAN RYAN DSILVASHAMIK ENTERPRISES PVT LTD11/12/2020
CC006000000197973ROHAN RYAN DSILVASHAMIK ENTERPRISES PVT LTD16/08/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Aug 2021

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Vaidya cottage OC.pdf23 Aug 2021
Certificates of CA (Form 5)File: Vaidya Cottage Form 5.PDF4 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certif Vaidya Cottage H_New.PDF23 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certif form 2 Vaidya cottage_ Crimson Bay.PDF23 May 2018
Certificates of CA (Form 3)File: Vaidya Cottage_CA_M-2018.pdf23 May 2018
Details of encumbrancesFile: Vaidya ecumbrances certificate piramal.PDF7 May 2018
Declaration in FORM BFile: Vaidya Cottage Form-B Affidavit cum Declaration Piramal.PDF7 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Vaidya Cottage 2018.pdf7 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Vaidya Cottage 2018.pdf7 Mar 2018
Certificates of CA (Form 3)File: CA Certif Form 3 Vaidya Cottage 2018.pdf7 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: vaidya cottage furthercc signed.pdf24 Nov 2017
Building plan approvalFile: AMENDED ISSUE LETTER .pdf1 Nov 2017
Building plan approvalFile: Drawing 1.pdf1 Nov 2017
Building plan approvalFile: Drawing 2.pdf1 Nov 2017
Building plan approvalFile: Drawing 3.pdf1 Nov 2017
Building plan approvalFile: Drawing 4.pdf1 Nov 2017
Building plan approvalFile: Drawing 5.pdf1 Nov 2017
Building Plan Approval (IOD)File: AMENDED ISSUE LETTER .pdf1 Nov 2017
Building Plan Approval (IOD)File: Drawing 1.pdf1 Nov 2017
Building Plan Approval (IOD)File: Drawing 2.pdf1 Nov 2017
Building Plan Approval (IOD)File: Drawing 3.pdf1 Nov 2017
Building Plan Approval (IOD)File: Drawing 4.pdf1 Nov 2017
Building Plan Approval (IOD)File: Drawing 5.pdf1 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC- Vaidya Cottage.pdf1 Nov 2017
Proforma of Allotment letterFile: RERA AGREEMENT FINAL VAIDYA COTTAGE.pdf1 Nov 2017
Proforma of Allotment letterFile: RERA AGREEMENT FINAL VAIDYA COTTAGE Updated.pdf1 Nov 2017
Proforma of Allotment letterFile: Declaration for Agreement-Vaidya Cottage.pdf25 Jul 2017
Building plan approvalFile: IOD.pdf24 Jul 2017
Building plan approvalFile: IOD Plan 1 .pdf24 Jul 2017
Building plan approvalFile: IOD Plan 2.pdf24 Jul 2017
Building plan approvalFile: IOD Plan 3.pdf24 Jul 2017
Building plan approvalFile: IOD Plan 4.pdf24 Jul 2017
Building plan approvalFile: IOD Plan 5.pdf24 Jul 2017
Layout approvalFile: IOD Plan 1 .pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Plan 1 .pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Plan 1 .pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Plan 2.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Plan 3.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Plan 4.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Plan 5.pdf24 Jul 2017
Certificates of CA (Form 3)File: CA Cert for RERA Vaidya Cottage.pdf24 Jul 2017
PAN CardFile: SHAMIK PAN NEW (1).pdf22 Jul 2017
Copy of the legal title reportFile: Title Report.pdf22 Jul 2017
Details of encumbrancesFile: Encumbrances Certificate- Vaidya Cottage.pdf22 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: First CC.pdf22 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Vaidyacottage Further CC.pdf22 Jul 2017
Declaration in FORM BFile: Affidavit Cum Declaration- Vaidya Cottage.pdf22 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-I_Architect Certificate_Vaidya Cottage.pdf22 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 _ Engineers Certificate Vaidaya cottage.PDF22 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Parle Trupti CHS LtdM G Road Vile Parle East25CompletedSep 2016Late, Jun 2017
Rupani Baug CHS LtdNanda Patkar road Vile Parle East14CompletedApr 2015Mar 2015
Shivalaya CHS LtdNanda Patkar Road Vile Parle East15CompletedDec 2014Late, Mar 2015
Shiv Krupa CHS LtdNanda Patkar Road Vile Parle East17CompletedDec 2014Late, Sep 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 16 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vaidya Cottage CHS Ltd on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle (east)6,700+ in Mumbai Suburban

2 kmVaidya Cottage CHS LtdCompleted 135Lapsed / revoked 66Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 337 registered projects within 2 km.

Builder: Shamik Enterprises Pvt Ltd.

Shamik Enterprises Pvt Ltd. has 8 registrations on MahaRERA, including Vaidya Cottage CHS Ltd and Besant Arti CHS Ltd. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Vaidya Cottage CHS Ltd is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vaidya Cottage CHS Ltd?

The registered promoter entity is Shamik Enterprises Pvt Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vaidya Cottage CHS Ltd?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vaidya Cottage CHS Ltd?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vaidya Cottage CHS Ltd?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vaidya Cottage CHS Ltd?

The professionals named in the filing: Architect: HMJ Architects; Engineer: Sura and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vaidya Cottage CHS Ltd?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vaidya Cottage CHS Ltd. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vaidya Cottage CHS Ltd to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.