Home / Browse projects / Thane, Maharashtra / VAIBHAV
VAIBHAV
RG-MH-21817 · RERA P51700023656 · Last updated on MahaRERA portal: 13 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 30 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VAIBHAV is a Residential / Group Housing project by GAVDEVI SHELTER in Thane, Maharashtra, registered with MahaRERA as P51700023656 on 24 Dec 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 30 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameVAIBHAV
- TypeResidential / Group Housing
- Location
- BAJARPETH
- SURVODAYA NAGAR
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700023656
- ReraGenie IDRG-MH-21817
Builder
- NameGAVDEVI SHELTER
- Entity typePartnership
- GSTIN27AAUFG2798K1ZG
- PartnerSACHIN VILAS SAHANE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Dec 2019
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed106 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VAIBHAV | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 6%.
VAIBHAV: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 6% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 13 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed48
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VAIBHAV CHS LTD | Badlapur (M Cl) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SACHIN VILAS SAHANE |
| Engineer | MANGESH S DEORUKHAKAR |
| Engineer | DARSHAN KASTURE SAAD CONSULTANT |
| Chartered Accountant | PRADEEP MEHTA |
| Chartered Accountant | VINEET DUBEY & ASSOCIATES |
| Chartered Accountant | SHIVANI KHAICHA & CO |
| Partner | Role in project |
|---|---|
| GAVDEVI SHELTER | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSuch as Weather, Equipment failures, and Labour shortages.
Reason as filed by the promoterLIFT SANCTION WORK PENDING.
Reason as filed by the promoterFINANCE RELATED ISSUE
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000396733 | HARSHADA VASANT KONDILKAR | MS GAVDEVI SHELTER | 23/07/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed106
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 13 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf | 13 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 S.pdf | 11 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 S.pdf | 11 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHELTER.pdf | 11 May 2025 |
| Disclosure of sold/ booked inventoryFile: SHELTER SOLD UNSOLD.pdf | 7 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 SHEL OCT 24.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1 SHEL JAN 25.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 23-12 infra.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-1 infra_compressed.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 23-12 gavdevi vaibhav_compressed.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-1 gavdevi vaibhav_compressed.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F 2 SHEL` OCT 24.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F 2 SHEL JAN 25.pdf | 22 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F 2A SHEL OCT 24.pdf | 22 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F 2A SHEL JAN 25.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: pdf2.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate Form 1.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate Form 2.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SHELTER APRIL 2024.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 APRIL.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JULY.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A APRIL.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A JULY.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A JULY.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 APRILLL.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JULYYY.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 APRIL.pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JULY.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD JULY.pdf | 18 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 -SHELTER.pdf | 18 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 -SHELTER.pdf | 18 Dec 2023 |
| Declaration in FORM BFile: AFFIDAVIT CUM DECLATATION (FORM B)-SHELTER.pdf | 14 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTRY.pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A JAN.pdf | 13 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A APR-S.pdf | 13 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A OCT -S.pdf | 13 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHELTER NEW_compressed.pdf | 8 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FOR SHELTER NEW.pdf | 8 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (07-10-2023).pdf | 23 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (07-04-2023).pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (15-11-2019)_compressed.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (13-07-2021)_compressed.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (24-11-2022).pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (07-01-2023)_compressed.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (07-04-2023)_compressed.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (07-07-2023)_compressed.pdf | 23 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 (7-10-2023).pdf | 23 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-1.pdf | 16 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-5.pdf | 16 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-6.pdf | 16 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-6.pdf | 16 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 .pdf | 13 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate FORM 2A (2023) NEW.pdf | 13 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 (2019-2020).pdf | 25 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 (2020-2021).pdf | 25 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 (2021-2022).pdf | 25 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf | 19 Jan 2023 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf | 19 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE1.pdf | 18 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Interest in Other Real Estate Organization SHELTER.pdf | 18 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE1.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTRY.pdf | 12 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement 1.pdf | 12 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement 2.pdf | 12 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement 3.pdf | 12 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement 4.pdf | 12 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA_11024_1.pdf | 17 Dec 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200255109801_For_Debtor_Based_Search_17_12_2022_15_49_30_756.pdf | 17 Dec 2022 |
| Deviation Report with respect to Allotment letterFile: ANNEXURE 1 VAIBHAV CHSL.pdf | 17 Dec 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account - SHELTER.pdf | 7 Dec 2022 |
| Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf | 22 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventry.pdf | 28 Dec 2021 |
| Building plan approvalFile: BLUE PRINT1_.pdf | 25 Dec 2021 |
| Building plan approvalFile: BLUE PRINT2_-compressed_compressed (1).pdf | 25 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: BLUE PRINT1_.pdf | 25 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: BLUE PRINT2_-compressed_compressed (1).pdf | 25 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION REVISED.pdf | 25 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 106 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VAIBHAV on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SURVODAYA NAGAR7,600+ in Thane
Filed coordinates, straight-line distance. 422 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: GAVDEVI SHELTER
GAVDEVI SHELTER has 1 registration on MahaRERA, including VAIBHAV. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that VAIBHAV shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VAIBHAV is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VAIBHAV?
The registered promoter entity is GAVDEVI SHELTER, a partnership as per the filing. Its GSTIN 27AAUFG2798K1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VAIBHAV?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VAIBHAV?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VAIBHAV?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VAIBHAV?
The professionals named in the filing: Architect: SACHIN VILAS SAHANE; Engineer: MANGESH S DEORUKHAKAR; Engineer: DARSHAN KASTURE SAAD CONSULTANT; Chartered Accountant: PRADEEP MEHTA; Chartered Accountant: VINEET DUBEY & ASSOCIATES; Chartered Accountant: SHIVANI KHAICHA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VAIBHAV?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback