Home / Browse projects / Pune, Maharashtra / Vaarivana Social Housing-1
Vaarivana Social Housing-1
By Sanjivani Integrated Township LLP
RG-MH-41400 · RERA P52100076646 · Last updated on MahaRERA portal: 25 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 6 cases
- Completion date moved by 21 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vaarivana Social Housing-1 is a Residential / Group Housing project by Sanjivani Integrated Township LLP in Pune, Maharashtra, registered with MahaRERA as P52100076646 on 18 Jun 2024. Possession is promised by 30 Dec 2027. The completion date has moved by 21 months from the original filing. 3 of the 131 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameVaarivana Social Housing-1
- TypeResidential / Group Housing
- Location
- Ambewadi
- Adhe & Urse
- Urse
- Mawal
- Pune
- 410506
- Pincode410506
- RERA no.P52100076646
- ReraGenie IDRG-MH-41400
Builder
- NameSanjivani Integrated Township LLP
- Entity typePartnership
- PartnersAnil Jayram Pharande, Pharande Township Private Limited, Nitin Govind Sable, Surekha Rajeev Sable, Ramesh Jayram Pharande
- Other registrations9 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jun 2024
- Promised completion30 Dec 2027
- Revised completionRevised to 30 Dec 2027 (originally 31 Mar 2026)
- Buildings1 building record
- Documents filed44 files
Current status
Figures as on 25 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 12 | 11 | 131 | 0 | 131 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.
Building A: 51% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 24% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 51% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed261
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Suvarna Sanjivani Agro Farms Private Limited | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A | NA | Rs 9.53 cr | Rs 8.03 cr |
| - | NA | Rs 3.55 cr | - |
Certifying professionals and partners11
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vivaan Associates |
| Architect | Landmark Design Group |
| Architect | Shivam Shubhash Ganore |
| Engineer | Bharatraj Kinagi |
| Engineer | Umesh Joshi Designated Partner JW Consultants LLP |
| Engineer | l l l |
| Chartered Accountant | FAA & Associates LLP |
| Chartered Accountant | CA Nikesh Sharma |
| Chartered Accountant | R. Devendra Kumar & Associates |
| Chartered Accountant | A N J K & CO LLP |
| Chartered Accountant | FAA & Associates LLP (CA Faiz Shaikh) |
| Partner | Role in project |
|---|---|
| Sanjivani Integrated Township LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, The MahaRERA Authority, Sub : Reason for the Extension to the Project Vaarivana Social Housing-1 bearing Registration No. P52100076646. Due to certain technical issues, the project could not be commenced within the originally scheduled timeline. At present, all works are being carried out strictly in accordance with the applicable rules and regulations, and the internal construction activities are in full progress. Upon completion of the construction, additional time will be required to obtain the Occupation Certificate from the concerned authority. We sincerely request your kind considera
Litigation declared6
| Case | Court | Status |
|---|---|---|
| 515/2022 Old Number 626/2017/2022 | Civil Judge Senior Division Pune | Evidence |
| 577/2022 Old Number 1533/2017/2022 | Civil Judge Senior Division at Vadgaon Pune | Awaiting summons |
| RTS Appeal /2A/896/2021/2021 | Additional Collector Pune | Filing Say |
| 415/2022/2022 | Civil Judge Junior Division at Vadgaon Pune | Awaiting summons |
| RCS/2023/2023 | Civil Judge Junior Division at Vadgaon Pune | Awaiting summons |
| RTS Appeal 324/2023/2023 | Sub Divisional Officer Maval | Filing Say |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Mar 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2027
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: VAARIVANA SOCIAL HOUSING-1 ARCHITECT CERTIFICATE JUNE-24 FORM-1.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA SOCIAL HOUSING-1 ARCHITECT CERTIFICATE JUNE-24 FORM-1.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA SOCIAL HOUSING-1 ARCHITECT CERTIFICATE JUNE-24 FORM-1.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA SOCIAL HOUSING-1 ARCHITECT CERTIFICATE JUNE-24 FORM-1.pdf | 25 Feb 2026 |
| Withdrawal Update Form 2 | 25 Feb 2026 |
| Withdrawal Update Form 2 | 25 Feb 2026 |
| Withdrawal Update Form 2 | 25 Feb 2026 |
| Withdrawal Update Form 2 | 25 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA SOCIAL HOUSING-1_CA CERTIFICATE.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA SOCIAL HOUSING-1_CA CERTIFICATE.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA SOCIAL HOUSING-1_CA CERTIFICATE.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA SOCIAL HOUSING-1_CA CERTIFICATE.pdf | 25 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA SOCIAL HOUSING-1_ARCHITECT CERTIFICATE_DECEMBER-24_ FORM-1.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA SOCIAL HOUSING-1_ARCHITECT CERTIFICATE_SEP-24_ FORM-1.pdf | 9 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA SOCIAL HOUSING-1 ARCHITECT CERTIFICATE JUNE-24 FORM-1.pdf | 30 Jul 2024 |
| Proforma of Allotment letterFile: 37_ALLOTMENT LETTER.pdf | 30 May 2024 |
| Copy of the legal title reportFile: 2) LEGAL TITLE REPORT.pdf | 29 Mar 2024 |
| Proforma of Agreement for saleFile: 32) AGREEMENT FOR SALE.pdf | 29 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE_R1.pdf | 17 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE_R1.pdf | 17 Feb 2024 |
| Declaration about Commencement CertificateFile: 10) DECLARATION ABOUT COMMENCEMENT CERTIFICATE_R1.pdf | 17 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 40) BANK NO ENCUMBRANCE CERTIFICATE_R1.pdf | 17 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20) CA CERTIFICATE.pdf | 8 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 21-4) NITIN SABLE DIRECTOR INTEREST IN REAL ESTATE ORGANIZATION.PDF | 4 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 21-4) SUREKHA SABLE DIRECTOR INTEREST IN REAL ESTATE ORGANIZATION.PDF | 4 Dec 2023 |
| Deviation Report with respect to model copy of AgreementFile: 42) DEVAITION REPORT DRAFT AGREEMENT.pdf | 20 Nov 2023 |
| CERSAI detailsFile: 19) CERSAI REGISTRATION CERTIFICATE.pdf | 18 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: 3) DETAILS OF ENCUMBRANCE CERTIFICATE FINANCE.pdf | 17 Nov 2023 |
| Details of encumbrances concerned to LegalFile: 3) DETAILS OF ENCUMBRANCE CERTIFICATE FINANCE.pdf | 17 Nov 2023 |
| Declaration in FORM BFile: 11) FORM B.pdf | 17 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 21-1) ANIL SIR DIRECTOR INTEREST IN REAL ESTATE ORGANIZATION.pdf | 17 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 21-2) PHARANDE TOWNSHIP DIRECTOR INTEREST IN REAL ESTATE ORGANIZATION.pdf | 17 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 21-3) RAMESH SIR DIRECTOR INTEREST IN REAL ESTATE ORGANIZATION.pdf | 17 Nov 2023 |
| Deviation Report with respect to Allotment letterFile: 41) DEVAITION REPORT ALLOTMENT LETTER.pdf | 17 Nov 2023 |
| Layout approvalFile: 5) COPY OF LAYOUT PLAN.pdf | 31 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 5) COPY OF LAYOUT PLAN.pdf | 31 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 9) COMMENCEMENT CERTIFICATE.pdf | 31 Oct 2023 |
| Building plan approvalFile: 6) COPY OF BUILDING PLAN-1.pdf | 2 Oct 2023 |
| Building plan approvalFile: 6) COPY OF BUILDING PLAN-2.pdf | 2 Oct 2023 |
| Building plan approvalFile: 6) COPY OF BUILDING PLAN-3.pdf | 2 Oct 2023 |
| PAN CardFile: 1) PANCARD.pdf | 2 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6) COPY OF BUILDING PLAN-1.pdf | 2 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6) COPY OF BUILDING PLAN-2.pdf | 2 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6) COPY OF BUILDING PLAN-3.pdf | 2 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vaarivana Social Housing-1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Adhe & Urse13,700+ in Pune
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
ABHIMAAN HOMES PHASE 3
RISING PROPCON LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Builder: Sanjivani Integrated Township LLP
Sanjivani Integrated Township LLP has 10 registrations on MahaRERA, including Vaarivana Phase A - 1 and Vaarivana Phase C. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Vaarivana Social Housing-1 is delayed beyond 30 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vaarivana Social Housing-1?
The registered promoter entity is Sanjivani Integrated Township LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vaarivana Social Housing-1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vaarivana Social Housing-1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vaarivana Social Housing-1?
The professionals named in the filing: Architect: Vivaan Associates; Architect: Landmark Design Group; Architect: Shivam Shubhash Ganore; Engineer: Bharatraj Kinagi; Engineer: Umesh Joshi Designated Partner JW Consultants LLP; Engineer: l l l. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vaarivana Social Housing-1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback