Home / Browse projects / Pune, Maharashtra / Vaarivana Phase A - 1
Vaarivana Phase A - 1
By Sanjivani Integrated Township LLP
RG-MH-80381 · RERA P52100018391 · Last updated on MahaRERA portal: 22 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 4 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
- Rs 275.00 crore secured on the land, in favour of Catalyst Trusteeship Limited
Clear
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vaarivana Phase A - 1 is a Residential / Group Housing project by Sanjivani Integrated Township LLP in Pune, Maharashtra, registered with MahaRERA as P52100018391 on 29 Oct 2018. Possession is promised by 30 Dec 2027. The completion date has moved by 24 months from the original filing. 276 of the 284 units on this registration are recorded sold or booked, and 1934 of 3124 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameVaarivana Phase A - 1
- TypeResidential / Group Housing
- Location
- Aadhe and Urse
- Urse
- Mawal
- Pune
- 410506
- Pincode410506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100018391
- ReraGenie IDRG-MH-80381
Builder
- NameSanjivani Integrated Township LLP
- Entity typePartnership
- PartnersAnil Jayram Pharande, Pharande Township Private Limited, Nitin Govind Sable, Surekha Rajeev Sable, Ramesh Jayram Pharande
- Other registrations9 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Oct 2018
- Promised completion30 Dec 2027
- Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2025)
- Buildings284 building records
- Documents filed85 files
Current status
Figures as on 22 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUNGALOW NO A79 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A80 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A81 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A82 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A83 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A84 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A85 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A86 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A87 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A88 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A89 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A90 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A91 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A92 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A93 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A94 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A95 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A96 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A97 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A98 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A99 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A100 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A101 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A102 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A103 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A104 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A105 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A106 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A107 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A108 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A109 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A110 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A111 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A112 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A113 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A114 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A115 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A116 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A117 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A118 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A119 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A120 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A121 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A122 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A123 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A124 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A125 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A126 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A127 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A128 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A129 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A130 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A131 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A132 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A133 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A134 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A135 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A136 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A137 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A138 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A139 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A140 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A141 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A142 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A143 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A144 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A145 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A146 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A147 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A148 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A149 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A150 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A151 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A152 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A153 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A154 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A155 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A156 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A157 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A158 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A159 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A160 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A161 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A162 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A163 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A164 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A165 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A166 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A167 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A168 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A169 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A170 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A171 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A172 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A173 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A174 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A175 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A176 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A177 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A178 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A179 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A180 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A181 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A182 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A183 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A184 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A185 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A186 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A187 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A188 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A189 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A190 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A191 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A192 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A193 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A194 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A195 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A196 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A197 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A198 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A199 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A200 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A201 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A202 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A203 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A204 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A205 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A206 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A207 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A208 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A209 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A210 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A211 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A212 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A213 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A214 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A215 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A216 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A217 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A218 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A219 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A220 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A221 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A222 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A223 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A224 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A225 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A226 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A227 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A228 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A229 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A230 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A231 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A232 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A233 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A234 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A235 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A236 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A237 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A238 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A239 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A240 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A241 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A242 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A243 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A244 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A245 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A246 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A247 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A248 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A249 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A250 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A251 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A252 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A253 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A254 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A255 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A256 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A257 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A258 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A259 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A260 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A261 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A358 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A359 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A360 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A361 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A362 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A363 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A364 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A365 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A366 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A367 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A368 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A369 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A370 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A371 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A372 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A373 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A374 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A375 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A376 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A377 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A378 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A379 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A380 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A381 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A382 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A383 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A384 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A385 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A386 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A387 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A388 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A389 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A390 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A391 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A392 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A393 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A394 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A395 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A396 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A397 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A398 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A399 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A400 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A401 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A402 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A403 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A404 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A405 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A406 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A407 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A408 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A409 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A410 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A411 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A412 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A413 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A414 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A415 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A416 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A417 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A418 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A419 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A420 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A421 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A422 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A423 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A424 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A425 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A426 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A427 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A428 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A429 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A430 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A431 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A432 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A433 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A434 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A435 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A436 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A437 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A438 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A439 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A440 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A441 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A442 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A443 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A444 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A445 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A446 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A447 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A448 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A449 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A450 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A451 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A452 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A453 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A454 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A455 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A456 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A457 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW NO A458 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 284 buildings; the table lists the first 20.
1934 of 3124 construction stages are filed complete across 284 buildings. The stage furthest along is Internal walls, at 96%.
BUNGALOW NO A7982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW NO A8081%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
BUNGALOW NO A8181%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
BUNGALOW NO A8291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW NO A8381%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
BUNGALOW NO A8481%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
BUNGALOW NO A8581%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
BUNGALOW NO A8668%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 93% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
BUNGALOW NO A8782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW NO A8849%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 57% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 33% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A8982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW NO A9081%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
BUNGALOW NO A9152%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 77% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9253%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 38% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9350%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 13% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 57% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9451%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 13% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 67% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9549%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 13% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9660%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 47% |
| Sanitary Fittings within the flats / premises | 44% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 93% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 77% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9750%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 13% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 57% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW NO A9852%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 38% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 65% |
| Community Buildings | Yes | 80% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 75% |
| Open Parking | No | Not applicable |
Parking filed568
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUNGALOW NO A79 | 2 | 2 |
| BUNGALOW NO A80 | 2 | 2 |
| BUNGALOW NO A81 | 2 | 2 |
| BUNGALOW NO A82 | 2 | 2 |
| BUNGALOW NO A83 | 2 | 2 |
| BUNGALOW NO A84 | 2 | 2 |
| BUNGALOW NO A85 | 2 | 2 |
| BUNGALOW NO A86 | 2 | 2 |
| BUNGALOW NO A87 | 2 | 2 |
| BUNGALOW NO A88 | 2 | 2 |
| BUNGALOW NO A89 | 2 | 2 |
| BUNGALOW NO A90 | 2 | 2 |
| BUNGALOW NO A91 | 2 | 2 |
| BUNGALOW NO A92 | 2 | 2 |
| BUNGALOW NO A93 | 2 | 2 |
| BUNGALOW NO A94 | 2 | 2 |
| BUNGALOW NO A95 | 2 | 2 |
| BUNGALOW NO A96 | 2 | 2 |
| BUNGALOW NO A97 | 2 | 2 |
| BUNGALOW NO A98 | 2 | 2 |
| BUNGALOW NO A99 | 2 | 2 |
| BUNGALOW NO A100 | 2 | 2 |
| BUNGALOW NO A101 | 2 | 2 |
| BUNGALOW NO A102 | 2 | 2 |
| BUNGALOW NO A103 | 2 | 2 |
| BUNGALOW NO A104 | 2 | 2 |
| BUNGALOW NO A105 | 2 | 2 |
| BUNGALOW NO A106 | 2 | 2 |
| BUNGALOW NO A107 | 2 | 2 |
| BUNGALOW NO A108 | 2 | 2 |
| BUNGALOW NO A109 | 2 | 2 |
| BUNGALOW NO A110 | 2 | 2 |
| BUNGALOW NO A111 | 2 | 2 |
| BUNGALOW NO A112 | 2 | 2 |
| BUNGALOW NO A113 | 2 | 2 |
| BUNGALOW NO A114 | 2 | 2 |
| BUNGALOW NO A115 | 2 | 2 |
| BUNGALOW NO A116 | 2 | 2 |
| BUNGALOW NO A117 | 2 | 2 |
| BUNGALOW NO A118 | 2 | 2 |
| BUNGALOW NO A119 | 2 | 2 |
| BUNGALOW NO A120 | 2 | 2 |
| BUNGALOW NO A121 | 2 | 2 |
| BUNGALOW NO A122 | 2 | 2 |
| BUNGALOW NO A123 | 2 | 2 |
| BUNGALOW NO A124 | 2 | 2 |
| BUNGALOW NO A125 | 2 | 2 |
| BUNGALOW NO A126 | 2 | 2 |
| BUNGALOW NO A127 | 2 | 2 |
| BUNGALOW NO A128 | 2 | 2 |
| BUNGALOW NO A129 | 2 | 2 |
| BUNGALOW NO A130 | 2 | 2 |
| BUNGALOW NO A131 | 2 | 2 |
| BUNGALOW NO A132 | 2 | 2 |
| BUNGALOW NO A133 | 2 | 2 |
| BUNGALOW NO A134 | 2 | 2 |
| BUNGALOW NO A135 | 2 | 2 |
| BUNGALOW NO A136 | 2 | 2 |
| BUNGALOW NO A137 | 2 | 2 |
| BUNGALOW NO A138 | 2 | 2 |
| BUNGALOW NO A139 | 2 | 2 |
| BUNGALOW NO A140 | 2 | 2 |
| BUNGALOW NO A141 | 2 | 2 |
| BUNGALOW NO A142 | 2 | 2 |
| BUNGALOW NO A143 | 2 | 2 |
| BUNGALOW NO A144 | 2 | 2 |
| BUNGALOW NO A145 | 2 | 2 |
| BUNGALOW NO A146 | 2 | 2 |
| BUNGALOW NO A147 | 2 | 2 |
| BUNGALOW NO A148 | 2 | 2 |
| BUNGALOW NO A149 | 2 | 2 |
| BUNGALOW NO A150 | 2 | 2 |
| BUNGALOW NO A151 | 2 | 2 |
| BUNGALOW NO A152 | 2 | 2 |
| BUNGALOW NO A153 | 2 | 2 |
| BUNGALOW NO A154 | 2 | 2 |
| BUNGALOW NO A155 | 2 | 2 |
| BUNGALOW NO A156 | 2 | 2 |
| BUNGALOW NO A157 | 2 | 2 |
| BUNGALOW NO A158 | 2 | 2 |
| BUNGALOW NO A159 | 2 | 2 |
| BUNGALOW NO A160 | 2 | 2 |
| BUNGALOW NO A161 | 2 | 2 |
| BUNGALOW NO A162 | 2 | 2 |
| BUNGALOW NO A163 | 2 | 2 |
| BUNGALOW NO A164 | 2 | 2 |
| BUNGALOW NO A165 | 2 | 2 |
| BUNGALOW NO A166 | 2 | 2 |
| BUNGALOW NO A167 | 2 | 2 |
| BUNGALOW NO A168 | 2 | 2 |
| BUNGALOW NO A169 | 2 | 2 |
| BUNGALOW NO A170 | 2 | 2 |
| BUNGALOW NO A171 | 2 | 2 |
| BUNGALOW NO A172 | 2 | 2 |
| BUNGALOW NO A173 | 2 | 2 |
| BUNGALOW NO A174 | 2 | 2 |
| BUNGALOW NO A175 | 2 | 2 |
| BUNGALOW NO A176 | 2 | 2 |
| BUNGALOW NO A177 | 2 | 2 |
| BUNGALOW NO A178 | 2 | 2 |
| BUNGALOW NO A179 | 2 | 2 |
| BUNGALOW NO A180 | 2 | 2 |
| BUNGALOW NO A181 | 2 | 2 |
| BUNGALOW NO A182 | 2 | 2 |
| BUNGALOW NO A183 | 2 | 2 |
| BUNGALOW NO A184 | 2 | 2 |
| BUNGALOW NO A185 | 2 | 2 |
| BUNGALOW NO A186 | 2 | 2 |
| BUNGALOW NO A187 | 2 | 2 |
| BUNGALOW NO A188 | 2 | 2 |
| BUNGALOW NO A189 | 2 | 2 |
| BUNGALOW NO A190 | 2 | 2 |
| BUNGALOW NO A191 | 2 | 2 |
| BUNGALOW NO A192 | 2 | 2 |
| BUNGALOW NO A193 | 2 | 2 |
| BUNGALOW NO A194 | 2 | 2 |
| BUNGALOW NO A195 | 2 | 2 |
| BUNGALOW NO A196 | 2 | 2 |
| BUNGALOW NO A197 | 2 | 2 |
| BUNGALOW NO A198 | 2 | 2 |
| BUNGALOW NO A199 | 2 | 2 |
| BUNGALOW NO A200 | 2 | 2 |
| BUNGALOW NO A201 | 2 | 2 |
| BUNGALOW NO A202 | 2 | 2 |
| BUNGALOW NO A203 | 2 | 2 |
| BUNGALOW NO A204 | 2 | 2 |
| BUNGALOW NO A205 | 2 | 2 |
| BUNGALOW NO A206 | 2 | 2 |
| BUNGALOW NO A207 | 2 | 2 |
| BUNGALOW NO A208 | 2 | 2 |
| BUNGALOW NO A209 | 2 | 2 |
| BUNGALOW NO A210 | 2 | 2 |
| BUNGALOW NO A211 | 2 | 2 |
| BUNGALOW NO A212 | 2 | 2 |
| BUNGALOW NO A213 | 2 | 2 |
| BUNGALOW NO A214 | 2 | 2 |
| BUNGALOW NO A215 | 2 | 2 |
| BUNGALOW NO A216 | 2 | 2 |
| BUNGALOW NO A217 | 2 | 2 |
| BUNGALOW NO A218 | 2 | 2 |
| BUNGALOW NO A219 | 2 | 2 |
| BUNGALOW NO A220 | 2 | 2 |
| BUNGALOW NO A221 | 2 | 2 |
| BUNGALOW NO A222 | 2 | 2 |
| BUNGALOW NO A223 | 2 | 2 |
| BUNGALOW NO A224 | 2 | 2 |
| BUNGALOW NO A225 | 2 | 2 |
| BUNGALOW NO A226 | 2 | 2 |
| BUNGALOW NO A227 | 2 | 2 |
| BUNGALOW NO A228 | 2 | 2 |
| BUNGALOW NO A229 | 2 | 2 |
| BUNGALOW NO A230 | 2 | 2 |
| BUNGALOW NO A231 | 2 | 2 |
| BUNGALOW NO A232 | 2 | 2 |
| BUNGALOW NO A233 | 2 | 2 |
| BUNGALOW NO A234 | 2 | 2 |
| BUNGALOW NO A235 | 2 | 2 |
| BUNGALOW NO A236 | 2 | 2 |
| BUNGALOW NO A237 | 2 | 2 |
| BUNGALOW NO A238 | 2 | 2 |
| BUNGALOW NO A239 | 2 | 2 |
| BUNGALOW NO A240 | 2 | 2 |
| BUNGALOW NO A241 | 2 | 2 |
| BUNGALOW NO A242 | 2 | 2 |
| BUNGALOW NO A243 | 2 | 2 |
| BUNGALOW NO A244 | 2 | 2 |
| BUNGALOW NO A245 | 2 | 2 |
| BUNGALOW NO A246 | 2 | 2 |
| BUNGALOW NO A247 | 2 | 2 |
| BUNGALOW NO A248 | 2 | 2 |
| BUNGALOW NO A249 | 2 | 2 |
| BUNGALOW NO A250 | 2 | 2 |
| BUNGALOW NO A251 | 2 | 2 |
| BUNGALOW NO A252 | 2 | 2 |
| BUNGALOW NO A253 | 2 | 2 |
| BUNGALOW NO A254 | 2 | 2 |
| BUNGALOW NO A255 | 2 | 2 |
| BUNGALOW NO A256 | 2 | 2 |
| BUNGALOW NO A257 | 2 | 2 |
| BUNGALOW NO A258 | 2 | 2 |
| BUNGALOW NO A259 | 2 | 2 |
| BUNGALOW NO A260 | 2 | 2 |
| BUNGALOW NO A261 | 2 | 2 |
| BUNGALOW NO A358 | 2 | 2 |
| BUNGALOW NO A359 | 2 | 2 |
| BUNGALOW NO A360 | 2 | 2 |
| BUNGALOW NO A361 | 2 | 2 |
| BUNGALOW NO A362 | 2 | 2 |
| BUNGALOW NO A363 | 2 | 2 |
| BUNGALOW NO A364 | 2 | 2 |
| BUNGALOW NO A365 | 2 | 2 |
| BUNGALOW NO A366 | 2 | 2 |
| BUNGALOW NO A367 | 2 | 2 |
| BUNGALOW NO A368 | 2 | 2 |
| BUNGALOW NO A369 | 2 | 2 |
| BUNGALOW NO A370 | 2 | 2 |
| BUNGALOW NO A371 | 2 | 2 |
| BUNGALOW NO A372 | 2 | 2 |
| BUNGALOW NO A373 | 2 | 2 |
| BUNGALOW NO A374 | 2 | 2 |
| BUNGALOW NO A375 | 2 | 2 |
| BUNGALOW NO A376 | 2 | 2 |
| BUNGALOW NO A377 | 2 | 2 |
| BUNGALOW NO A378 | 2 | 2 |
| BUNGALOW NO A379 | 2 | 2 |
| BUNGALOW NO A380 | 2 | 2 |
| BUNGALOW NO A381 | 2 | 2 |
| BUNGALOW NO A382 | 2 | 2 |
| BUNGALOW NO A383 | 2 | 2 |
| BUNGALOW NO A384 | 2 | 2 |
| BUNGALOW NO A385 | 2 | 2 |
| BUNGALOW NO A386 | 2 | 2 |
| BUNGALOW NO A387 | 2 | 2 |
| BUNGALOW NO A388 | 2 | 2 |
| BUNGALOW NO A389 | 2 | 2 |
| BUNGALOW NO A390 | 2 | 2 |
| BUNGALOW NO A391 | 2 | 2 |
| BUNGALOW NO A392 | 2 | 2 |
| BUNGALOW NO A393 | 2 | 2 |
| BUNGALOW NO A394 | 2 | 2 |
| BUNGALOW NO A395 | 2 | 2 |
| BUNGALOW NO A396 | 2 | 2 |
| BUNGALOW NO A397 | 2 | 2 |
| BUNGALOW NO A398 | 2 | 2 |
| BUNGALOW NO A399 | 2 | 2 |
| BUNGALOW NO A400 | 2 | 2 |
| BUNGALOW NO A401 | 2 | 2 |
| BUNGALOW NO A402 | 2 | 2 |
| BUNGALOW NO A403 | 2 | 2 |
| BUNGALOW NO A404 | 2 | 2 |
| BUNGALOW NO A405 | 2 | 2 |
| BUNGALOW NO A406 | 2 | 2 |
| BUNGALOW NO A407 | 2 | 2 |
| BUNGALOW NO A408 | 2 | 2 |
| BUNGALOW NO A409 | 2 | 2 |
| BUNGALOW NO A410 | 2 | 2 |
| BUNGALOW NO A411 | 2 | 2 |
| BUNGALOW NO A412 | 2 | 2 |
| BUNGALOW NO A413 | 2 | 2 |
| BUNGALOW NO A414 | 2 | 2 |
| BUNGALOW NO A415 | 2 | 2 |
| BUNGALOW NO A416 | 2 | 2 |
| BUNGALOW NO A417 | 2 | 2 |
| BUNGALOW NO A418 | 2 | 2 |
| BUNGALOW NO A419 | 2 | 2 |
| BUNGALOW NO A420 | 2 | 2 |
| BUNGALOW NO A421 | 2 | 2 |
| BUNGALOW NO A422 | 2 | 2 |
| BUNGALOW NO A423 | 2 | 2 |
| BUNGALOW NO A424 | 2 | 2 |
| BUNGALOW NO A425 | 2 | 2 |
| BUNGALOW NO A426 | 2 | 2 |
| BUNGALOW NO A427 | 2 | 2 |
| BUNGALOW NO A428 | 2 | 2 |
| BUNGALOW NO A429 | 2 | 2 |
| BUNGALOW NO A430 | 2 | 2 |
| BUNGALOW NO A431 | 2 | 2 |
| BUNGALOW NO A432 | 2 | 2 |
| BUNGALOW NO A433 | 2 | 2 |
| BUNGALOW NO A434 | 2 | 2 |
| BUNGALOW NO A435 | 2 | 2 |
| BUNGALOW NO A436 | 2 | 2 |
| BUNGALOW NO A437 | 2 | 2 |
| BUNGALOW NO A438 | 2 | 2 |
| BUNGALOW NO A439 | 2 | 2 |
| BUNGALOW NO A440 | 2 | 2 |
| BUNGALOW NO A441 | 2 | 2 |
| BUNGALOW NO A442 | 2 | 2 |
| BUNGALOW NO A443 | 2 | 2 |
| BUNGALOW NO A444 | 2 | 2 |
| BUNGALOW NO A445 | 2 | 2 |
| BUNGALOW NO A446 | 2 | 2 |
| BUNGALOW NO A447 | 2 | 2 |
| BUNGALOW NO A448 | 2 | 2 |
| BUNGALOW NO A449 | 2 | 2 |
| BUNGALOW NO A450 | 2 | 2 |
| BUNGALOW NO A451 | 2 | 2 |
| BUNGALOW NO A452 | 2 | 2 |
| BUNGALOW NO A453 | 2 | 2 |
| BUNGALOW NO A454 | 2 | 2 |
| BUNGALOW NO A455 | 2 | 2 |
| BUNGALOW NO A456 | 2 | 2 |
| BUNGALOW NO A457 | 2 | 2 |
| BUNGALOW NO A458 | 2 | 2 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 17.18 cr | Rs 11.87 cr |
| BUNGALOW NO A249 | NA | Rs 1.24 cr | Rs 54.47 lakh |
| BUNGALOW NO A250 | NA | Rs 1.24 cr | Rs 60.79 lakh |
| BUNGALOW NO A372 | NA | Rs 1.24 cr | Rs 54.47 lakh |
| BUNGALOW NO A373 | NA | Rs 1.24 cr | Rs 54.47 lakh |
| BUNGALOW NO A374 | NA | Rs 1.24 cr | Rs 51.28 lakh |
| BUNGALOW NO A375 | NA | Rs 1.24 cr | Rs 51.28 lakh |
| BUNGALOW NO A79 | NA | Rs 93.72 lakh | Rs 93.72 lakh |
| BUNGALOW NO A82 | NA | Rs 93.72 lakh | Rs 93.72 lakh |
| BUNGALOW NO A83 | NA | Rs 93.72 lakh | Rs 92.90 lakh |
| BUNGALOW NO A84 | NA | Rs 93.72 lakh | Rs 92.45 lakh |
| BUNGALOW NO A86 | NA | Rs 93.72 lakh | Rs 70.26 lakh |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sachin Funde |
| Architect | Landmark Design Group |
| Architect | Shivam Shubhash Ganore |
| Engineer | Umesh Joshi Designated Partner JW Consultants LLP |
| Engineer | l l l |
| Chartered Accountant | FAA & Associates LLP |
| Chartered Accountant | CA Nikesh Sharma |
| Chartered Accountant | R. Devendra Kumar & Associates |
| Chartered Accountant | A N J K & CO LLP |
| Partner | Role in project |
|---|---|
| Sanjivani Integrated Township LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, The MahaRERA Authority, Sub : Reason for the Extension to the Project Vaarivana Phase A1 bearing Registration No. P52100018391. Due to certain technical issues, the project could not be commenced within the originally scheduled timeline. At present, all works are being carried out strictly in accordance with the applicable rules and regulations, and the internal construction activities are in full progress. Upon completion of the construction, additional time will be required to obtain the Occupation Certificate from the concerned authority. We sincerely request your kind consideration in
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 515/2022 | Civil Judge Senior Division Pune | Argument on Exhibit Unready |
| 577/2022 | Civil Judge Senior Division Pune | Unready Board |
| RTS/2A/896/2021/2021 | Collector Pune | Awaiting Notice |
| 515/2022 (Old Case No Special Suit No. 626/2017)/2022 | Civil Judge, Vadgaon, Pune | Ongoing |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000085277 | Parag Bhalchandra Pandharipande | Sanjeevani Integrated Township LLP | 26/02/2021 |
| CC12501409 | Dinesh Kumar | Sanjivani Integrated Township LLP | 26/04/2025 |
| CC12604952 | Ajith Aravind Palleeri | Sanjivani Integrated Township LLP | 05/08/2026 |
| CC12604641 | Anil Kumar Addanky | Sanjivani Integrated Township LLP | 24/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Oct 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2027
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Vaarivana Phase A1.pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: Form 2_Vaarivana Phase A1.pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Vaarivana Phase A1 (1).pdf | 22 Apr 2026 |
| Form 5 (FY 2025-2026)File: CA Form 5_FY 2025-26_Vaarivana Phase A 1 Signed.pdf | 9 Apr 2026 |
| Form 2A (FY 2024-2025)File: Form 2A Vaarivana Phase A1 2024-25.pdf | 17 Mar 2026 |
| Withdrawal Update Form 1File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 24 Feb 2026 |
| Withdrawal Update Form 2 | 24 Feb 2026 |
| Withdrawal Update Form 2 | 24 Feb 2026 |
| Withdrawal Update Form 2 | 24 Feb 2026 |
| Withdrawal Update Form 2 | 24 Feb 2026 |
| Withdrawal Update Form 2 | 24 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA PHASE A1 CA CERTIFICATE.pdf | 24 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA PHASE A1 CA CERTIFICATE.pdf | 24 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA PHASE A1 CA CERTIFICATE.pdf | 24 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA PHASE A1 CA CERTIFICATE.pdf | 24 Feb 2026 |
| Withdrawal Update Form 3File: VAARIVANA PHASE A1 CA CERTIFICATE.pdf | 24 Feb 2026 |
| Form 5 (FY 2024-2025)File: VAARIVANA PHASE A1_CA CERTIFICATE_FORM-5_2024-25.pdf | 6 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA PHASE A1_ARCHITECT CERTIFICATE_DECEMBER-24_ FORM-1.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA PHASE A1_ARCHITECT CERTIFICATE_SEP-24_ FORM-1.pdf | 9 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VAARIVANA PHASE A1_CA CERTIFICATE_FORM-5_2023-24.pdf | 15 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VAARIVANA PHASE A1 ARCHITECT CERTIFICATE JUNE-24 FORM-1_compressed.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_VAARIVANA PHASE A1_ARCHITECT CERTIFICATE_MAR-24_compressed.pdf | 21 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 19_VAARIVANA PHASE A1_QUALITY CERTIFICATE_FORM-2A_2023-24_compressed.pdf | 21 May 2024 |
| Disclosure of sold/ booked inventoryFile: VAARIVANA PHASE A1_SOLD UNSOLD INVENTORY CERTIFICATE_MAR-24_compressed.pdf | 7 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1_VAARIVANA PHASE A1_P52100018391_2022-23_compressed.pdf | 25 Apr 2024 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE_VAARIVANA PHASE A1.pdf | 9 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: VAARIVANA PHASE A1_SALES INVENTORY_DEC-2023.pdf | 23 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1_VAARIVANA PHASE A1_P52100018391_2019-20.pdf | 16 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1_VAARIVANA PHASE A1_P52100018391_2020-21.pdf | 16 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: VAARIVANA PHASE A1.pdf | 15 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1_VAARIVANA PHASE A1_P52100018391.pdf | 3 Aug 2020 |
| Building plan approvalFile: LAYOUT.pdf | 17 Mar 2020 |
| Layout approvalFile: A-1.pdf | 17 Mar 2020 |
| Layout approvalFile: A-2.pdf | 17 Mar 2020 |
| Layout approvalFile: A-3.pdf | 17 Mar 2020 |
| Layout approvalFile: A-4.pdf | 17 Mar 2020 |
| Layout approvalFile: A-5.pdf | 17 Mar 2020 |
| Layout approvalFile: A-6.pdf | 17 Mar 2020 |
| Layout approvalFile: A-7.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-1.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-2.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-3.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-4.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-5.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-6.pdf | 17 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: A-7.pdf | 17 Mar 2020 |
| Building Plan Approval (IOD)File: LAYOUT.pdf | 17 Mar 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 17 Mar 2020 |
| Proforma of Allotment letterFile: AGREEMENT.pdf | 14 Feb 2020 |
| Proforma of Allotment letterFile: 1-24-03-19_VAARIVAN_AGREEMENT_PHASE-A-1.pdf | 26 Mar 2019 |
| Proforma of Allotment letterFile: 1-09-03-19_For_RERA_Update_VAARIVAN_AGREEMENT_FOR_SALE_OF_PLOT_PHASE-A-1.pdf | 9 Mar 2019 |
| Building plan approvalFile: MAIN LAYOUT PLAN.pdf | 5 Oct 2018 |
| Layout approvalFile: A2.pdf | 5 Oct 2018 |
| Layout approvalFile: A3.pdf | 5 Oct 2018 |
| Layout approvalFile: A4.pdf | 5 Oct 2018 |
| Layout approvalFile: A5.pdf | 5 Oct 2018 |
| Layout approvalFile: A6.pdf | 5 Oct 2018 |
| Layout approvalFile: A7.pdf | 5 Oct 2018 |
| PAN CardFile: PAN CARD - SITLLP.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 1.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 2.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 3.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 4.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 5.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 6.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 7.pdf | 5 Oct 2018 |
| Copy of the legal title reportFile: 8.pdf | 5 Oct 2018 |
| Details of encumbrancesFile: SITLLP - ENCUMBRANCE.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A2.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A3.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A4.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A5.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A6.pdf | 5 Oct 2018 |
| Copy of Layout Approval (in case of layout)File: A7.pdf | 5 Oct 2018 |
| Building Plan Approval (IOD)File: MAIN LAYOUT PLAN.pdf | 5 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: SITLLP - PHASE A 1 - CERTIFICATE.pdf | 5 Oct 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 9 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vaarivana Phase A - 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Urse13,700+ in Pune
Filed coordinates, straight-line distance. 9 registered projects within 2 km.
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
ABHIMAAN HOMES PHASE 3
RISING PROPCON LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Builder: Sanjivani Integrated Township LLP
Sanjivani Integrated Township LLP has 10 registrations on MahaRERA, including Vaarivana Phase A - 1 and Vaarivana Phase C. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Vaarivana Phase A - 1 is delayed beyond 30 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vaarivana Phase A - 1?
The registered promoter entity is Sanjivani Integrated Township LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vaarivana Phase A - 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Vaarivana Phase A - 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Vaarivana Phase A - 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vaarivana Phase A - 1?
The professionals named in the filing: Architect: Sachin Funde; Architect: Landmark Design Group; Architect: Shivam Shubhash Ganore; Engineer: Umesh Joshi Designated Partner JW Consultants LLP; Engineer: l l l; Chartered Accountant: FAA & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vaarivana Phase A - 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback