Home / Browse projects / Thane, Maharashtra / V KANTA
V KANTA
RG-MH-57322 · RERA PM1330002601632 · Last updated on MahaRERA portal: 5 Jun 2026
Source: official MahaRERA filing
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 11 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
V KANTA is a Mixed project by TARANG DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as PM1330002601632 on 24 Aug 2026. Possession is promised by 31 Dec 2032.
At a glance
Project
- NameV KANTA
- TypeMixed
- Location
- KOLSHET ROAD
- KOLSHET
- Thane
- 400607
- Pincode400607
- MapView location on Google Maps (as filed on RERA)
- RERA no.PM1330002601632
- ReraGenie IDRG-MH-57322
Builder
- NameTARANG DEVELOPERS
- Entity typePartnership
- GSTIN27AAIFT2445C1ZC
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Aug 2026
- Promised completion31 Dec 2032
- Revised completionNone
- Buildings4 building records
- Documents filed11 files
Current status
Figures as on 5 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 1 | NA | 8 | 8 | 28 | 4 | 32 |
| BUILDING 2 | WING A | 10 | 9 | 43 | 0 | 43 |
| BUILDING 2 | WING B | 11 | 10 | 38 | 0 | 38 |
| BUILDING 2 | WING C | 11 | 10 | 38 | 0 | 38 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 5 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
BUILDING 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 2 · wing WING A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 2 · wing WING B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 2 · wing WING C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | 0% |
Parking filed334
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Separate Building | Stack Parking | Mechanical | Total |
|---|---|---|---|---|---|
| BUILDING 1 | 35 | 0 | 8 | 10 | 53 |
| BUILDING 2 WING A | 6 | 168 | 22 | 0 | 196 |
| BUILDING 2 WING B | 6 | 26 | 23 | 0 | 55 |
| BUILDING 2 WING C | 7 | 0 | 23 | 0 | 30 |
Land and ownership3
MahaRERA does not publish landowner contact details.
| Landowner | Village | District |
|---|---|---|
| DEVENDRA DAMODAR SHELKE | Kolshet | Thane |
| CHAYA KAILAS BHAGAT | DOMBIVLI | Thane |
| SMITA ASHOK RAUT | Kanhor | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUVARNA GHOSH |
| Engineer | ASSOCIATED STRUCTURAL ENGINEERS LLP |
| Chartered Accountant | SNH AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| TARANG DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed11
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| PLAN TARANG DEVELOPERS_1-1 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_2-2 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_3-3 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_4-4 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_5-5 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_6-6 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_7-7 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_8-8 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_9-9 | 5 Jun 2026 |
| PLAN TARANG DEVELOPERS_10-end | 5 Jun 2026 |
| ANNEXURE-A Declaration cum Understanding | 5 Jun 2026 |
How this compares with Thane
Computed across the 7,562 Thane projects on ReraGenie, from their own filings.
Keep V KANTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KOLSHET7,562 in Thane
Hiranandani Westgate Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Forestville - Phase 1
Oberoi Realty Limited
DOSTI WEST COUNTY - PHASE 4- DOSTI PINE
DOSTI ENTERPRISES
Y SQUARE
SHREE MALLINATH ENTERPRISE LLP
Primera
Agile Real Estate Dev Private Limited
UNIQUE VISTAS MHADA BUILDINGNO. 4 5 6 7
MADHU HARSHAD DOSHI
See every Thane project, with the district possession charts
Builder: TARANG DEVELOPERS
TARANG DEVELOPERS has 1 registration on MahaRERA, including V KANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if V KANTA is delayed beyond 31 Dec 2032?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of V KANTA?
The registered promoter entity is TARANG DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAIFT2445C1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in V KANTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for V KANTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at V KANTA?
The professionals named in the filing: Architect: SUVARNA GHOSH; Engineer: ASSOCIATED STRUCTURAL ENGINEERS LLP; Chartered Accountant: SNH AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in V KANTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback