Registration lapsed No litigation declared Residential / Group Housing project

URBANIA

By AVENUE'S FORTUN LLP

RG-MH-14234 · RERA P51600031451 · Last updated on MahaRERA portal: 18 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 80%
29 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

URBANIA is a Residential / Group Housing project by AVENUE'S FORTUN LLP in Nashik, Maharashtra, registered with MahaRERA as P51600031451 on 23 Oct 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 43 of the 72 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameURBANIA
  • TypeResidential / Group Housing
  • Location
    • S. NO.772
    • KARMAYOGI NAGAR
    • NEAR RUNBHOOMI
    • Nashik
    • 422009
  • Pincode422009
  • RERA no.P51600031451
  • ReraGenie IDRG-MH-14234

Builder

  • NameAVENUE'S FORTUN LLP
  • Entity typePartnership
  • PartnersPOONAM MUKUND SABU, CHINTAN NARENDRA MUTHA, DILIPKUMARA JAGANNATH KARWA, KIRTI SURESH JAIN, MANIK ANILKUMAR KARWA, SUNNY NARENDRA PARAKH, NAYAN SUBHASH BHANDARI, SAMEER RAJENDRA TOTALE

Key dates

10 months past promisethis monthRegisteredOct 2021PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Oct 2021
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed78 files

Current status

60%43 of 72 units booked
73.7%Work done, per cost certificate

Figures as on 18 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
URBANIANA221872072

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

URBANIA: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 18 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes15%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,205 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Aug 2025

Approvals and building plan

Sanctioning authorityNashik Muncipal Corporation
Permissible FSI14978.28
Proposed, not sanctioned14,978 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLR 712 2A 2D 74 74 GANGAPUR ROAD NASHIK
Estimated costRs 48.00 cr
Cost incurredRs 35.37 cr
Work done73.68%
BuildingWingEstimatedIncurred
URBANIANARs 45.00 crRs 33.16 cr
-NARs 3.00 crRs 2.21 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUMIT KAMATH
EngineerSHRIKANT S NAVALE
EngineerKanchan Balasaheb Tupe
Chartered AccountantCHETAN BUMB
Chartered AccountantBhavana Loya
PartnerRole in project
Avenue's Fortune LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Avenues Fortune LLP Architech Certificate_0001.pdf18 Mar 2026
Withdrawal Update Form 2File: Avenues Fortune LLP Engineers Certificate 0001_0001.pdf18 Mar 2026
Withdrawal Update Form 3File: Form 3 Final.pdf18 Mar 2026
Form 5 (FY 2023-2024)File: The Avenue Fortune LLP_2023-24.pdf29 Nov 2025
Form 5 (FY 2024-2025)File: Avenues fortune llp- form-5_0001.pdf29 Nov 2025
Withdrawal Update Form 1File: Avenue Fortune LLP Architect Certificate_0001.pdf20 Nov 2025
Withdrawal Update Form 1File: Avenue Fortune LLP Architect Certificate_0001.pdf20 Nov 2025
Withdrawal Update Form 2File: Avenue Fortune LLP Engineers Certificate_0001.pdf20 Nov 2025
Withdrawal Update Form 2File: Avenue Fortune LLP Engineers Certificate_0001.pdf20 Nov 2025
Withdrawal Update Form 3File: Avenue Fortune LLP (Form-3)_0001.pdf20 Nov 2025
Withdrawal Update Form 3File: Form 3 Uploaded.pdf20 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2025
Withdrawal Update Form 3File: Form 3.pdf19 Sep 2025
Withdrawal Update Form 1File: Urbania Architect Certificate.pdf4 Aug 2025
Withdrawal Update Form 2File: Engineers Certificate.pdf4 Aug 2025
Withdrawal Update Form 3File: Urbania avenueu0027s fortune llp.pdf4 Aug 2025
Form 1File: Urbania Architect Certificate.pdf28 May 2025
Form 2File: Engineers Certificate.pdf28 May 2025
Form 3File: Urbania avenue's fortune llp.pdf28 May 2025
Proforma of Agreement for saleFile: Agreement for sale draft Urbania.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q4 Form 1 FY 23-24.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q1 - Form 1 - FY 24-25.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q2 - Form 1 - FY 24-25.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q3 - Form 1 - FY 24-25.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Urbania F Y 23-24 Q4_0001_compressed.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Urbania F Y 24-25 Q1_0001_compressed.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Urbania F Y 24-25 Q2_0001_compressed.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Urbania F Y 24-25 Q3_0001_compressed.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q1.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q2.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q3.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CER.PDF10 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHRIKANT NAWALE EC.PDF10 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.PDF10 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect certificate.PDF7 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate.PDF7 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2.pdf7 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Avenue Fortune LLP Form 5.pdf28 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate Q4 22-23.PDF19 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate Q1 23-24.PDF19 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Q4 22-23.PDF19 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Q1 23-24.PDF19 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Avenue Fortune Q4 22-23.PDF19 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Avenue Fortune Q1 23-24.PDF19 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Q2 22-23.PDF3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Q3 22-23.PDF3 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE OCT.PDF3 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE JAN.PDF3 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q2 22- 23 1 MB.pdf3 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q3 22-23.PDF3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Q1 22-23.PDF2 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE JULY.PDF2 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q1 22-23 1MB.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: the avenue fortune llp-- RERA CA Certificate-Form 5.PDF30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: the avenue fortune llp-- RERA CA Certificate-Form 5.PDF27 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: the avenue fortune llp-- RERA CA Certificate-Form 5.PDF27 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE (2)_compressed.pdf30 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE (2)_compressed.pdf30 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3-compressed.pdf30 Apr 2022
Layout approvalFile: URBANIA Approved Plan_compressed.pdf12 Oct 2021
Building plan approvalFile: URBANIA Approved Plan_compressed.pdf12 Oct 2021
PAN CardFile: PAN PDF.pdf12 Oct 2021
Copy of the legal title reportFile: Urbania - RERA SEARCH.pdf12 Oct 2021
Details of encumbrancesFile: Non Encumbrance Certificate.pdf12 Oct 2021
Copy of Layout Approval (in case of layout)File: URBANIA Approved Plan_compressed.pdf12 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: URBANIA Approved Plan_compressed.pdf12 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: URBANIA Commencement Certificate.pdf12 Oct 2021
Declaration about Commencement CertificateFile: Declaration in Form D.pdf12 Oct 2021
Declaration in FORM BFile: Declaration in Form B on 100 RS Stamp.pdf12 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - URBANIA- Architect's certificate_compressed.pdf12 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certiifcate (06-10-2021)_compressed.pdf12 Oct 2021
Disclosure of sold/ booked inventoryFile: Annexure A Soldunsold invetory.pdf12 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate form3 Urbania.PDF12 Oct 2021
Proforma of Allotment letterFile: Proforma of allotment letter.pdf12 Oct 2021
Proforma of Allotment letterFile: SAMPLE SALE FORMAT URBANIA.pdf12 Oct 2021
OtherFile: Letter of Authorisation PDF.pdf12 Oct 2021

How this compares with Nashik

60%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep URBANIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARMAYOGI NAGAR, NEAR RUNBHOOMI4,100+ in Nashik

Builder: AVENUE'S FORTUN LLP

AVENUE'S FORTUN LLP has 1 registration on MahaRERA, including URBANIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that URBANIA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if URBANIA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of URBANIA?

The registered promoter entity is AVENUE'S FORTUN LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in URBANIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for URBANIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at URBANIA?

The professionals named in the filing: Architect: SUMIT KAMATH; Engineer: SHRIKANT S NAVALE; Engineer: Kanchan Balasaheb Tupe; Chartered Accountant: CHETAN BUMB; Chartered Accountant: Bhavana Loya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in URBANIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About URBANIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save URBANIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.