Home / Browse projects / Pune, Maharashtra / Unnati-Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Unnati-Phase 2

By Sigma Realty

RG-MH-17494 · RERA P52100029549 · Last updated on MahaRERA portal: 4 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 80%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Unnati-Phase 2 is a Residential / Group Housing project by Sigma Realty in Pune, Maharashtra, registered with MahaRERA as P52100029549 on 4 Jun 2021. Possession was promised by 31 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameUnnati-Phase 2
  • TypeResidential / Group Housing
  • Location
    • Nere to Punawale
    • Nere
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029549
  • ReraGenie IDRG-MH-17494

Builder

  • NameSigma Realty
  • Entity typePartnership
  • PartnersShailesh Kantilal Shah, Sachin Rikhablal Bhandari, Sachin Rikhablal Bhandari, Shailesh Kantilal Shah
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

34 months past promisethis monthRegisteredJun 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jun 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings2 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A3A4NA50000
B1B2B3NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

A3A440%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.16%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B1B2B364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 4 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes70%
Street LightingYes70%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered24
Open Space25
BuildingClosed/CoveredOpen SpaceTotal
A3A4122436
B1B2B312113

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,418 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Sambhaji JadhavNerePune
Chaggan Dattatray YelwandeNerePune
Magan Dattatray YelwandeNerePune
Shantaram Dattatray KudaleNerePune

Approvals and building plan

Permissible FSI4295.75
Proposed, not sanctioned4,296 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCamp Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Kapil Jain
EngineerM/s. G. A. Bhilare Consultants Pvt. Ltd.
Chartered AccountantRV Porwal and associates
PartnerRole in project
Sigma Realty-

Litigation declared1

CaseCourtStatus
RCS 888/2018/2018C C J D PunePending Awaiting Report

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Feb 2024

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Unnati Phase II - 2023-24.pdf4 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC_5665_2023_Clubhouse_11zon.pdf23 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q3-2023-2024.pdf22 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q3-2023-2024.pdf22 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q3-2023-2024.pdf22 Feb 2024
Details of encumbrances concerned to FinanceFile: Unnati phase 2.pdf7 Feb 2024
Details of encumbrances concerned to LegalFile: Unnati phase 2.pdf7 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FG.pdf7 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q3-2023-2024.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q2-2023-2024.pdf4 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q2-2023-2024.pdf4 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q2-2023-2024.pdf4 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC_5665_2023_Clubhouse_compressed (1).pdf31 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q1-2023-2024.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q1-2023-2024.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q1-2023-2024_compressed.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Sigma Realty - Unnati - Phase 2 - FY-2022-23.pdf5 Oct 2023
Declaration about Commencement CertificateFile: Compeltion_Unnati-B1B2B3.pdf7 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Compeltion_Unnati-B1B2B3.pdf27 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q4-2022-2023.pdf1 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q4-2022-2023.pdf1 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q4-2022-2023_compressed.pdf1 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q1-2021-2022.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q2-2021-2022.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q3-2021-2022.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q4-2021-2022.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q1-2022-2023.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q2-2022-2023.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Unnati Phase II - Q3-2022-2023.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q1-2021-2022.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q2-2021-2022.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q3-2021-2022.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q4-2021-2022.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q1-2022-2023.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q2-2022-2023.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Unnati Phase II - Q3-2022-2023.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q1-2021-2022.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q2-2021-2022.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q3-2021-2022.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q4-2021-2022.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q1-2022-2023.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q2-2022-2023.pdf27 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Unnati Phase II - Q3-2022-2023.pdf27 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sigma Realty - Phase II - FY -2021-22.pdf20 Jan 2023
OtherFile: 1.pdf28 Jan 2022
OtherFile: 2.pdf28 Jan 2022
OtherFile: 3.pdf28 Jan 2022
OtherFile: 4.pdf28 Jan 2022
OtherFile: 5.pdf28 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate-Unnati Phase 02.pdf1 Nov 2021
Copy of the legal title reportFile: Title Search-Updated.pdf26 May 2021
Declaration in FORM BFile: Form B-Revised.pdf24 May 2021
Proforma of Allotment letterFile: Standard Draft Agreement Unnati Phase 2.pdf24 May 2021
Proforma of Allotment letterFile: Allotment letter.pdf24 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf13 May 2021
Details of encumbrancesFile: phase 2 rera self declaration.pdf7 May 2021
Layout approvalFile: Layout Plan 1.pdf5 Apr 2021
Building plan approvalFile: 3A.pdf5 Apr 2021
Building plan approvalFile: 4A.pdf5 Apr 2021
Building plan approvalFile: 6A.pdf5 Apr 2021
Building plan approvalFile: 7A.pdf5 Apr 2021
PAN CardFile: Sigma Realty - Pan Card.pdf5 Apr 2021
Copy of the legal title reportFile: 2 report 2021.pdf5 Apr 2021
Copy of the legal title reportFile: 3 report 2021.pdf5 Apr 2021
Copy of the legal title reportFile: 4 report 2021.pdf5 Apr 2021
Copy of Layout Approval (in case of layout)File: Layout Plan 1.pdf5 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 3A.pdf5 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 4A.pdf5 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 6A.pdf5 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 7A.pdf5 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf5 Apr 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2-Unnati.pdf5 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sigma Realty Unnati-CA-Form3.pdf5 Apr 2021

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
43 Privet Drive PH 1Balewadi Pune204CompletedOct 2015Late, Dec 2015
LatitudeWakad Pune165CompletedMay 2012Mar 2012

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Unnati-Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nere13,700+ in Pune

2 kmUnnati-Phase 2Completed 122Lapsed / revoked 46Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 235 registered projects within 2 km.

Builder: Sigma Realty

Sigma Realty has 4 registrations on MahaRERA, including Unnati and Unnati-Phase 2. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Unnati-Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Unnati-Phase 2 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Unnati-Phase 2?

The registered promoter entity is Sigma Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Unnati-Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Unnati-Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Unnati-Phase 2?

The professionals named in the filing: Architect: Ar Kapil Jain; Engineer: M/s. G. A. Bhilare Consultants Pvt. Ltd.; Chartered Accountant: RV Porwal and associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Unnati-Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Unnati-Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Unnati-Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.