UNITY TOWERS

By Anshul Buildcon

RG-MH-33331 · RERA P52100080684 · Last updated on MahaRERA portal: 15 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2028Possession promisedmoved 4 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 36%
61 of 129Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

UNITY TOWERS is a Others project by Anshul Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100080684 on 25 Jun 2025. Possession is promised by 3 Jul 2028. The completion date has moved by 4 months from the original filing. 68 of the 129 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameUNITY TOWERS
  • TypeOthers
  • Location
    • S No 63/3B
    • Handewadi Hadapsar Road
    • Hadapsar
    • Pune
    • Handewadi
    • Hadapsar
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080684
  • ReraGenie IDRG-MH-33331

Builder

  • NameAnshul Buildcon
  • Entity typePartnership

Key dates

this monthRegisteredJun 2025First promiseMar 2028Revised toJul 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Jun 2025
  • Promised completion3 Jul 2028
  • Revised completionRevised to 3 Jul 2028 (originally 3 Mar 2028)
  • Buildings2 building records
  • Documents filed78 files

Current status

53%68 of 129 units booked
47.3%Work done, per cost certificate

Figures as on 15 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA99522981
Wing BNA10848048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 36%.

Wing A33%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure36%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B33%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed117

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots117
Closed/Covered117

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,892 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Oct 2025
LandownerVillageDistrict
J. K. DevelopersPune (CB)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI19839.39
Proposed, not sanctioned9,683 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR SHOP NO 7 AND 8 AND MEZZANINE OFFICE NO 102, FORTUNE EMPRESS, SR NO 1611245, HANDEWADI MANTARWADI ROAD
Estimated costRs 26.09 cr
Cost incurredRs 12.35 cr
Work done47.34%
BuildingWingEstimatedIncurred
Wing ANARs 13.16 crRs 6.94 cr
Wing BNARs 10.76 crRs 5.22 cr
-NARs 2.17 crRs 18.89 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParvez Jamadar
EngineerSantosh D Kudale
Chartered AccountantCA Pradyumna Kumar Kolaparti
Chartered AccountantAACHAL M KALE
Chartered AccountantMathi Ramesh Rajavel & Associates
Chartered AccountantM s. Singh Ranjan & Co
PartnerRole in project
Anshul Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100080684/WarMar 2028 → Jul 2028

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 May 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 3 Jul 2028

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf15 Sep 2026
Withdrawal Update Form 2File: Form 2 .pdf15 Sep 2026
Withdrawal Update Form 3File: Form 3 Anshul Buildcon 30-06-2026 sign - converted.pdf15 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf7 Sep 2026
Withdrawal Update Form 1File: Form_1_Signed_Q4.pdf5 Jun 2026
Withdrawal Update Form 2File: Form_2_Signed_Q4.pdf5 Jun 2026
Withdrawal Update Form 3File: Form_3_Signed_Q4_Size.pdf5 Jun 2026
Withdrawal Update Form 1File: Form_1_Signed_Q4.pdf2 May 2026
Withdrawal Update Form 2File: Form_2_Signed_Q4.pdf2 May 2026
Withdrawal Update Form 3File: Form_3_Signed_Q4_Size.pdf2 May 2026
Withdrawal Update Form 1File: AB_Q3_Form1_Signed.pdf17 Feb 2026
Withdrawal Update Form 2File: AB_Q3_Form2_Signed.pdf17 Feb 2026
Withdrawal Update Form 3File: AB_Q3_Form3_Signed.pdf17 Feb 2026
Withdrawal Update Form 1File: Form 1 Arch Certificate Q2.pdf11 Jan 2026
Withdrawal Update Form 2File: Form 2 Engg Certificate Q2.pdf11 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Q2_Signed.pdf11 Jan 2026
Withdrawal Update Form 1File: Form 1_Unity Towers_Q1_2025-26.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2 Engg Certificate Q2.pdf10 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Q2_Signed.pdf10 Jan 2026
Withdrawal Update Form 1File: Form 1_Unity Towers_Q1_2025-26.pdf5 Dec 2025
Withdrawal Update Form 2File: AB_Form_2_Jun_2025.pdf5 Dec 2025
Withdrawal Update Form 3File: AB_Jun_2025_Form_3_Signed.pdf5 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3.pdf18 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Designated Bank Account_R.pdf18 Jun 2025
Other - FinanceFile: Desk_Queries_Replies_18062025.pdf18 Jun 2025
Other - TechnicalFile: Annex_A_Declaration on Multiple Projects.pdf8 Jun 2025
Other - TechnicalFile: Desk_Queries_Replies_05062025.pdf8 Jun 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Opening of RERA Designated Bank Accounts.pdf8 Jun 2025
Layout approvalFile: BP_1of9.pdf1 May 2025
Layout approvalFile: Dev_Plan_1of2.pdf1 May 2025
Building plan approvalFile: Dev_Plan_2of2.pdf1 May 2025
Copy of Layout Approval (in case of layout)File: BP_1of9.pdf1 May 2025
Copy of Layout Approval (in case of layout)File: Dev_Plan_1of2.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf1 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Engineer Certificate.pdf1 May 2025
Commencement Certificates / NA Order for plotted developmentFile: DP_CC.pdf1 May 2025
Building Plan Approval / NA Order for plotted developmentFile: Dev_Plan_2of2.pdf1 May 2025
Other - LegalFile: Road Conveyance.pdf1 May 2025
Other - LegalFile: Units Allotment Agreement.pdf1 May 2025
Other - LegalFile: Authorization_Letter.pdf1 May 2025
Other - LegalFile: Annex_A_Declaration on Multiple Projects.pdf1 May 2025
Declaration about Commencement CertificateFile: Commencement Certificate Declaration.pdf1 May 2025
Building plan approvalFile: BP_2of9.pdf30 Apr 2025
Building plan approvalFile: BP_3of9.pdf30 Apr 2025
Building plan approvalFile: BP_4of9.pdf30 Apr 2025
Building plan approvalFile: BP_5of9.pdf30 Apr 2025
Building plan approvalFile: BP_6of9.pdf30 Apr 2025
Building plan approvalFile: BP_7of9.pdf30 Apr 2025
Building plan approvalFile: BP_8of9.pdf30 Apr 2025
Building plan approvalFile: BP_9of9.pdf30 Apr 2025
PAN CardFile: Pan card firm.pdf30 Apr 2025
Copy of the legal title reportFile: Format A Search and Legal Report.pdf30 Apr 2025
Details of encumbrances concerned to FinanceFile: Declaration_Legal_Financial_Encumbrances.pdf30 Apr 2025
Proforma of Allotment letterFile: Model Allotment Letter.pdf30 Apr 2025
Declaration in FORM BFile: Affidavit_Promoter.pdf30 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: BP_CC.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_2of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_9of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_8of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_7of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_6of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_5of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_4of9.pdf30 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: BP_3of9.pdf30 Apr 2025
Other - LegalFile: POA To Anshul_1.pdf30 Apr 2025
Declaration about Commencement CertificateFile: Format D Commencement Certificate.pdf30 Apr 2025
CERSAI detailsFile: CERSAI_Search_Report.pdf30 Apr 2025
CERSAI detailsFile: CERSAI_Undertaking.pdf30 Apr 2025
Deviation Report with respect to Allotment letterFile: Allotment_No_Deviations.pdf30 Apr 2025
Details of encumbrances concerned to LegalFile: Declaration_Legal_Financial_Encumbrances.pdf30 Apr 2025
Deviation Report with respect to model copy of AgreementFile: AFS_Deviations.pdf30 Apr 2025
Proforma of Agreement for saleFile: Model Agreement for Sale.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Dattatray_Interest_Other_Projects.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Sanjay_Harpale_Interest_Other_Projects.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Bhintade_Interest_Other_Projects.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Sanjay_Deshmukh_Interest_Other_Projects.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Vivek_Interest_Other_Projects.pdf30 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Secured_Unsecured_Declaration.pdf30 Apr 2025

How this compares with Pune

53%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UNITY TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Handewadi13,700+ in Pune

2 kmUNITY TOWERSCompleted 51Lapsed / revoked 20Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: Anshul Buildcon

Anshul Buildcon has 1 registration on MahaRERA, including UNITY TOWERS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if UNITY TOWERS is delayed beyond 3 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UNITY TOWERS?

The registered promoter entity is Anshul Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UNITY TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UNITY TOWERS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UNITY TOWERS?

The professionals named in the filing: Architect: Parvez Jamadar; Engineer: Santosh D Kudale; Chartered Accountant: CA Pradyumna Kumar Kolaparti; Chartered Accountant: AACHAL M KALE; Chartered Accountant: Mathi Ramesh Rajavel & Associates; Chartered Accountant: M s. Singh Ranjan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNITY TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNITY TOWERS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNITY TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.