ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / UNIQUE ESTATE WING E

Registered No litigation declared Residential / Group Housing project

UNIQUE ESTATE WING E

By UNIQUE SHANTI REALTORS

RG-MH-28719 · RERA P51700026813 · Last updated on MahaRERA portal: 17 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 42 months from the original
7 of 11Construction stages donefurthest along: Installation of Lifts, 95%
37 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

UNIQUE ESTATE WING E is a Residential / Group Housing project by UNIQUE SHANTI REALTORS in Thane, Maharashtra, registered with MahaRERA as P51700026813 on 25 Oct 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 42 months from the original filing. 16 of the 53 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameUNIQUE ESTATE WING E
  • TypeResidential / Group Housing
  • Location
    • Off Kanakia Road
    • Near Kamal Park
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • RERA no.P51700026813
  • ReraGenie IDRG-MH-28719

Builder

  • NameUNIQUE SHANTI REALTORS
  • Entity typeOthers
  • Named personsUNIQUE SHANTI DEVELOPERS LLP, ORBIT PROPERTIES
  • Other registrations4 more →
  • Completed3 of 5

Key dates

this monthRegisteredOct 2020First promiseJun 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed85 files

Current status

30%16 of 53 units booked
63.7%Work done, per cost certificate

Figures as on 17 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UNIQUE ESTATE WING E TYPE DNA1110431053

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

UNIQUE ESTATE WING E TYPE D: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes40%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed156

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots156
Closed/Covered10
Open Space146

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area318 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jul 2025

Approvals and building plan

Sanctioning authorityMIRA BHAYANDER MUNICIPAL CORPORATION
Permissible FSI3929.16
Proposed, not sanctioned3,929 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchE-41 POONAM CHAMBERS PHASE 3 OPP SEC NO 6 AND 7 SHANTI PARK MIRA ROAD EAST THANE -401107
Estimated costRs 17.99 cr
Cost incurredRs 11.46 cr
Work done63.74%
BuildingWingEstimatedIncurred
UNIQUE ESTATE WING E TYPE DNARs 16.99 crRs 11.46 cr
-NARs 1.00 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH MHATRE & ASSOCIATES
ArchitectSQUARE ARCHITECTS
EngineerMr Hiren M Tanna
EngineerEllora Projects Consultants
Chartered AccountantAJAY SHAH & CO
Chartered AccountantHITESH SHAH AND ASSOCIATES
PartnerRole in project
UNIQUE SHANTI REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700016632Jun 2023 → Dec 2026

Reason as filed by the promoterWe have done construction work upto 2 slab on site for the said building. The said project was running very smoothly and in a timely manner upto the hit of the Covid - 19, due to which the project has ran into delay in completion of the project as the availability of the labours and material is not with appropriate frequency. And due to the said pandemic we are facing financial crunch. The said project having 5 building and we are constructing the said project Phase wise. Out of 5 wing we have completed and obtained Occupation Certificate of the 3 wing (i.e. Wing A, B & C having MahaRERA Regis

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf17 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf17 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf17 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf17 Apr 2026
Withdrawal Update Form 3File: FROM 3.pdf17 Apr 2026
Withdrawal Update Form 3File: FROM 3.pdf17 Apr 2026
Withdrawal Update Form 1File: Form1.pdf13 Jan 2026
Withdrawal Update Form 2File: UNIQUE ESTATE E wing Engineer Form 2 Dec 2025.pdf13 Jan 2026
Withdrawal Update Form 3File: FORM 3 UE E WING DEC 2025.pdf13 Jan 2026
Form 5 (FY 2023-2024)File: UE FORM 5 2024.pdf13 Nov 2025
Form 5 (FY 2024-2025)File: UNIQUE ESTATE -E WING FORM 5 2024-25.pdf13 Nov 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf14 Oct 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf14 Oct 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf14 Oct 2025
Withdrawal Update Form 2File: Form-2.pdf14 Oct 2025
Withdrawal Update Form 2File: Form-2.pdf14 Oct 2025
Withdrawal Update Form 2File: Form-2.pdf14 Oct 2025
Withdrawal Update Form 3File: CA FORM 3 UE WING E Q 2 SEPT 2025.pdf14 Oct 2025
Withdrawal Update Form 3File: CA FORM 3 UE WING E Q 2 SEPT 2025.pdf14 Oct 2025
Withdrawal Update Form 3File: CA FORM 3 UE WING E Q 2 SEPT 2025.pdf14 Oct 2025
Withdrawal Update Form 1File: FORM 1.pdf19 Jul 2025
Withdrawal Update Form 2File: FORM 2.pdf19 Jul 2025
Withdrawal Update Form 3File: FORM 3 UE E WING.pdf19 Jul 2025
Form 1File: Architect Certificate wing E.pdf17 Jul 2025
Form 2File: FORM 2 Engineers Certificate Type D.pdf17 Jul 2025
Form 3File: E WING FORM 3 MARCH 2025.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-UNSOLD INVENTORY U Estate Wing E.pdf17 Jul 2025
Form 1File: Architect Certificate wing E.pdf17 Jul 2025
Form 2File: FORM 2 Engineers Certificate.pdf17 Jul 2025
Form 3File: CA FORM 3 E WING Q 3 2024 25.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf17 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: E WING FORM 3 MARCH 2025.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate wing E.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate Type D.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-UNSOLD INVENTORY U Estate Wing E.pdf12 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A MACRH 2025.pdf12 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: UE FORM 5 2024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate wing E.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf15 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A DEC 2024.pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 E WING Q 3 2024 25.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: USR CA CERTIFICATE FORM 3.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23.pdf9 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: PRAMOTER SELF DECLATION FORMAT A.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate Type D.pdf11 Jul 2024
Layout approvalFile: Layout Plan.pdf9 Jun 2023
Building plan approvalFile: Building Plan.pdf9 Jun 2023
Building plan approvalFile: Building Plan1.pdf9 Jun 2023
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf9 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf9 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan1.pdf9 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf27 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate.pdf27 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf27 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate.pdf27 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM - 5 2021-2022.pdf27 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM - 5 2022-2023.pdf27 May 2023
Declaration in FORM BFile: FORM B.pdf22 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf22 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate.pdf11 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A F Y 19-20.pdf11 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A F Y 20-21.pdf11 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A F Y 21-22.pdf11 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A F Y 22-23.pdf11 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A June 2023.pdf11 May 2023
CERSAI detailsFile: Undertaking NO CERSAI REPORT.pdf11 May 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-UNSOLD INVENTORY.pdf11 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf24 Feb 2023
Declaration about Commencement CertificateFile: Declaration About CC.pdf24 Feb 2023
Layout approvalFile: Layout Plan.pdf20 Oct 2020
Building plan approvalFile: Building Plan.pdf20 Oct 2020
PAN CardFile: PAN CARD.pdf20 Oct 2020
Copy of the legal title reportFile: TITLE CERTIFICATE Adv Jolani 16 12 2016.pdf20 Oct 2020
Details of encumbrancesFile: No Encumberances Certificate.pdf20 Oct 2020
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf20 Oct 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf20 Oct 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf20 Oct 2020
Declaration in FORM BFile: FORM B.pdf20 Oct 2020

How this compares with Thane

30%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 42 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UNIQUE ESTATE WING E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Kamal Park7,600+ in Thane

Builder: UNIQUE SHANTI REALTORS

UNIQUE SHANTI REALTORS has 5 registrations on MahaRERA, including UNIQUE ORBIT-I and UNIQUE ESTATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if UNIQUE ESTATE WING E is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UNIQUE ESTATE WING E?

The registered promoter entity is UNIQUE SHANTI REALTORS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UNIQUE ESTATE WING E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UNIQUE ESTATE WING E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UNIQUE ESTATE WING E?

The professionals named in the filing: Architect: AVINASH MHATRE & ASSOCIATES; Architect: SQUARE ARCHITECTS; Engineer: Mr Hiren M Tanna; Engineer: Ellora Projects Consultants; Chartered Accountant: AJAY SHAH & CO; Chartered Accountant: HITESH SHAH AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNIQUE ESTATE WING E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNIQUE ESTATE WING E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNIQUE ESTATE WING E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.