Home / Browse projects / Raigarh, Maharashtra / UNIMONT CORAL

Completed No litigation declared Others project

UNIMONT CORAL

By RSM HOMES LLP

RG-MH-11319 · RERA P52000002634 · Last updated on MahaRERA portal: 10 May 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

UNIMONT CORAL is a Others project by RSM HOMES LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000002634 on 2 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing.

At a glance

Project

  • NameUNIMONT CORAL
  • TypeOthers
  • Location
    • Bokadvira
    • Dronagiri
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000002634
  • ReraGenie IDRG-MH-11319

Builder

  • NameRSM HOMES LLP
  • Entity typePartnership
  • PartnersNARENDRASINGH SURATSINGH DASANA, KGK DWELLINGS PRIVATE LIMITED THROUGH DIRECTOR SAMPAT RAJ KOTHARI, RAMESH CHINNAYA BANGERA
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed84 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UNIMONT CORALNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

UNIMONT CORAL: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 10 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%
BRANDED ELEVATOR OF BRAND KONE OR EQUIVALENT BRANDYes100%
CCTV CAMERASYes0%
FITNESS CENTRE AND SOCIETY OFFICEYes80%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered19
Open Space7

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,299 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1933.13
Proposed, not sanctioned1,933 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchURAN

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTRIARCH DESIGN STUDIO
EngineerS V PATEL & ASSOCIATES
PartnerRole in project
RSM HOMES LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013242Dec 2022 → Dec 2023

Reason as filed by the promoterThe Promoter have completed the construction work of the project. However it appears that CIDCO is unable to issue Occupancy Certificate at the moment due to issuance of said Coastal Regulation Zone (CRZ) notification by Government of India and we along with stakeholder of 200 other real estate developers in Dronagiri and other coastal town of Navi Mumbai are making every effort to resolve the issue.

EXT52000019479Dec 2022 → Dec 2027

Reason as filed by the promoterAs per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I seek extension of the project till 31/12/2027. We have also received the MahaRERA order for the same

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Sep 2022

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral March 2022.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral March 2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral June 2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral Sept 2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral Dec 2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Unimont Coral March 2024.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Unimont Coral March 2022.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Unimont Coral March 2023.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Unimont Coral June 2023.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Unimont Coral Sept 2023.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Unimont Coral Dec 2023.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: Informtion of Sold and Booked Inventory-RSM Homes LLP.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: img-425001213.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL MAR 22.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL MAR 23.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL JUNE 23.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL SEPT 23.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL DEC 23.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM 3 CORAL MAR 24.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 CORAL 21-22.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CORAL 22-23.pdf29 Apr 2024
Declaration in FORM BFile: Form B.pdf18 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf18 Mar 2024
Certificates of CA (Form 5)File: Form 5 - 17-18.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 18-19.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 19-20.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 20-21.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 21-22.pdf18 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 21-22.pdf10 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 19-20.pdf10 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20-21.pdf10 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf10 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of int.pdf10 Feb 2023
Details of encumbrances concerned to FinanceFile: Declaration .pdf31 Dec 2022
Details of encumbrances concerned to LegalFile: Declaration .pdf31 Dec 2022
Declaration about Commencement CertificateFile: Declaration about cc 0001.pdf31 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf31 Dec 2022
Disclosure of sold/ booked inventoryFile: disclosour of sold booked investory.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf31 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Seperate Account- Format A.pdf31 Dec 2022
Certificates of CA (Form 5)File: Form-5-Coral.pdf19 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5-Coral.pdf19 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: refusal of OC by CIDCO.pdf8 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Application for OC.pdf8 Sep 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Final Order.pdf8 Sep 2022
Foreclosure of the ProjectFile: Letter to RERA with respect to Refusal of OC_compressed.pdf8 Sep 2022
Other - LegalFile: Final Order.pdf8 Sep 2022
Other - LegalFile: Final Order.pdf8 Sep 2022
Other - LegalFile: Aviation NOC.pdf8 Sep 2022
Other - LegalFile: UNIMONT CORAL -PLINTH CERTIFICATE CIDCO178.pdf8 Sep 2022
Other - LegalFile: Lift Certificate.pdf8 Sep 2022
Other - LegalFile: DCC_Undertaking.pdf8 Sep 2022
Other - LegalFile: Health_NOC.pdf8 Sep 2022
Other - LegalFile: Fire_NOC.pdf8 Sep 2022
Other - LegalFile: letter to TPO, MD CIDCO.pdf8 Sep 2022
Other - LegalFile: Coral letter to TPO -Reminder 1.pdf8 Sep 2022
Other - LegalFile: CIDCO Reply.pdf8 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Coral form 5_21.pdf27 Sep 2021
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate 36-36A 47 Dronagiri form 4-05042021.pdf28 Apr 2021
Certificates of CA (Form 5)File: Form 5 CORAL 31032020.pdf21 Oct 2020
Certificates of CA (Form 5)File: Form 5 Unimont Coral 290919.pdf30 Sep 2019
Certificates of CA (Form 5)File: Form 5 Unimont Coral.pdf6 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Habitable Floor CC.pdf16 May 2018
Proforma of Allotment letterFile: Proforma Allotment Letter and Agreement for Sale.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Form 3.pdf24 Jul 2017
Building plan approvalFile: Declaration No IOD.pdf19 Jul 2017
Details of encumbrancesFile: Declaration No Encumbrances.pdf19 Jul 2017
Building Plan Approval (IOD)File: Declaration No IOD.pdf19 Jul 2017
Declaration in FORM BFile: Declaration From B.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Form 1.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate Form 2.pdf19 Jul 2017
Layout approvalFile: 1-4.pdf17 Jul 2017
Layout approvalFile: 2-4.pdf17 Jul 2017
Layout approvalFile: 3-4.pdf17 Jul 2017
Layout approvalFile: 4-4.pdf17 Jul 2017
PAN CardFile: Pan Card.pdf17 Jul 2017
Copy of the legal title reportFile: Title Report.pdf17 Jul 2017
Copy of Layout Approval (in case of layout)File: 1-4.pdf17 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
RSM PEARLPLOT NO 132 SECTOR 41 DRONAGIRI28CompletedDec 2015Late, May 2016
RSM CRYSTALPLOT NO 118 SECTOR 23 ULWE35CompletedMar 2015Late, Aug 2015
RSM DIAMONDPLOT NUMBER 43 SECTOR 17 ULWE TALUKA PANVEL DISTRICT RAIGAD50CompletedJun 2014Late, Dec 2015

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 60 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UNIMONT CORAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dronagiri5,900+ in Raigarh

2 kmUNIMONT CORALCompleted 63Lapsed / revoked 24Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: RSM HOMES LLP

RSM HOMES LLP has 3 registrations on MahaRERA, including RSM NIYATI and UNIMONT CORAL. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if UNIMONT CORAL is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UNIMONT CORAL?

The registered promoter entity is RSM HOMES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UNIMONT CORAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for UNIMONT CORAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UNIMONT CORAL?

The professionals named in the filing: Architect: TRIARCH DESIGN STUDIO; Engineer: S V PATEL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNIMONT CORAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNIMONT CORAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNIMONT CORAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.