Home / Browse projects / Mumbai Suburban, Maharashtra / Umiya Parijat
Umiya Parijat
RG-MH-30157 · RERA P51800030978 · Last updated on MahaRERA portal: 25 Sep 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Umiya Parijat is a Residential / Group Housing project by D.D. Dezines Group in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030978 on 29 Sep 2021. The registration is recorded completed; possession was promised by 31 Oct 2025.
At a glance
Project
- NameUmiya Parijat
- TypeResidential / Group Housing
- Location
- Guru Datta Mandir Road
- Pant Nagar
- Ghatkopar
- Kurla
- Mumbai Suburban
- 400075
- Pincode400075
- RERA no.P51800030978
- ReraGenie IDRG-MH-30157
Builder
- NameD.D. Dezines Group
- Entity typePartnership
- PartnersTulsidas D Dama, Vrishabh vallabhdas Patel, Mayur Tulsidas Dama, Pratik Manilal Diwani, Darshil Arvind Ramijani, Chetan Bhanji Patel
- Other registrations2 more →
- Completed1 of 3
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Sep 2021
- Promised completion31 Oct 2025
- Revised completionNone
- Buildings1 building record
- Documents filed54 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Umiya Parijat | NA | 18 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Umiya Parijat: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 25 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Fitness Center | Yes | 100% |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| The Pantnagar Parijat CHS LTD | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARAS CONSULTANTS |
| Engineer | RAJESH N DHOLU |
| Chartered Accountant | Ketan Kataria & Associates |
| Partner | Role in project |
|---|---|
| D.D. Dezines Group | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 22 Sep 2023
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of ConveyanceFile: LEASE DEED_compressed.pdf | 25 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A D D FINAL.pdf | 22 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: D D Designz Form 5 22092023.pdf | 22 Sep 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ONLY OC BLD NO 37 UIMIYA PARIJAT.pdf | 22 Sep 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: Rera 100_ Architect Certificate Bldg no 37 _compressed.pdf | 22 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A D D FINAL.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: D D Dezines groups form 3_11zon.pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect D D FINAL.pdf | 19 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer DD FINAL.pdf | 19 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory D D FINAL.pdf | 19 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D D DEZINES ARCH CERTIFICATE BLDG NO 37 04-01-2023 (2)_compressed (1).pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: UMIYA PARIJAT INVENTORY BLDGNO 37 (1)_compressed.pdf | 16 Jan 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: 37 Soc Regi Copy.pdf | 30 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect Certificate Bldg no 37.pdf | 7 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: List of sold and unsold bldg no 37.pdf | 7 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DD FORM 5.pdf | 1 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf | 7 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: INVENTORY 300622_compressed.pdf | 7 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 7 Jul 2022 |
| OtherFile: FORM 5 D D DEZINE MARCH 22.pdf | 13 May 2022 |
| Details of encumbrancesFile: NEW ENCUMBRANCE LTTER BLDG NO 37 (1).pdf | 7 May 2022 |
| Proforma of Allotment letterFile: NEW DRAFT AGREEMENT.pdf | 7 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Arch certificate.pdf | 7 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Engineer certificate.pdf | 7 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: INVENTRY DETAIL.pdf | 7 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 D D DEZINE.pdf | 7 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 D D DEZINE - REVISED_compressed.pdf | 7 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archintect certificate bldg no 37_compressed.pdf | 7 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certificate bldg37 compressed.pdf | 7 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: flat detail.pdf | 7 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL 07012022.pdf | 7 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Word(1).pdf | 8 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DD.pdf | 7 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG DD.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE FINAL 1.pdf | 7 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 D D DEZINES GROUP 30092021_compressed.pdf | 5 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Cc (2).pdf | 21 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DDDezines Group CA Certificate compressed.pdf | 14 Aug 2021 |
| Building plan approvalFile: REVISED IOA D D DEZINES 1.pdf | 10 Aug 2021 |
| Building plan approvalFile: REVISED IOA D D DEZINES 2.pdf | 10 Aug 2021 |
| Details of encumbrancesFile: NEW DECLARTION 9-8-21.pdf | 10 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: REVISED IOA D D DEZINES 1.pdf | 10 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: REVISED IOA D D DEZINES 2.pdf | 10 Aug 2021 |
| Layout approvalFile: LAYOUT_.pdf | 27 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT_.pdf | 27 Jul 2021 |
| Declaration about Commencement CertificateFile: dd dezine cc decla.pdf | 27 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: 5 CONSENT LETTER FOR COMMENCEMNET CERTIFICATE.pdf | 26 Jul 2021 |
| PAN CardFile: PAN CARD OF FIRM.pdf | 13 Jul 2021 |
| Copy of the legal title reportFile: title report bldg 37 marketable by dc (1).pdf | 13 Jul 2021 |
| Details of encumbrancesFile: encumbrance certificate.pdf | 13 Jul 2021 |
| Declaration in FORM BFile: Promoter Form B affidavit cum declaration.pdf | 13 Jul 2021 |
| Proforma of Allotment letterFile: allotment letter 8-7-21.pdf | 13 Jul 2021 |
| Proforma of Allotment letterFile: agreement for sale main.pdf | 13 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
Keep Umiya Parijat on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ghatkopar6,700+ in Mumbai Suburban
THE VIEWS
AGNEL DEVELOPERS
THE VIEWS II
AGNEL DEVELOPERS
Drushti Emerald
SAMARTH DRUSHTI DEVELOPERS
East Syde
VL GAJAMUKH DEVELOPERS LLP
ROYAL ALTEZZA
SHRI GANESH DEVELOPERS
Damji Shamji Corporate Square - Wing C
Coronate Constructions
See every Mumbai Suburban project, with the district possession charts
Builder: D.D. Dezines Group
D.D. Dezines Group has 3 registrations on MahaRERA, including Umiya Parijat and OM NEELDHARA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Umiya Parijat is delayed beyond 31 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Umiya Parijat?
The registered promoter entity is D.D. Dezines Group, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Umiya Parijat?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Umiya Parijat?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Umiya Parijat?
The professionals named in the filing: Architect: PARAS CONSULTANTS; Engineer: RAJESH N DHOLU; Chartered Accountant: Ketan Kataria & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Umiya Parijat?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback