Home / Browse projects / Pune, Maharashtra / ULTIMATE
ULTIMATE
RG-MH-54190 · RERA PR1260002601706 · Last updated on MahaRERA portal: 24 Aug 2026
Source: official MahaRERA filing
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 10 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ULTIMATE is a Residential / Group Housing project by Chintamani Mahadeo Nimhan in Pune, Maharashtra, registered with MahaRERA as PR1260002601706 on 31 Aug 2026. Possession is promised by 31 Dec 2031.
At a glance
Project
- NameULTIMATE
- TypeResidential / Group Housing
- Location
- Survey No 29
- Hissa No. 7/1
- Balewadi
- Haveli
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1260002601706
- ReraGenie IDRG-MH-54190
Builder
- NameChintamani Mahadeo Nimhan
- Entity typeProprietor
- GSTIN27AAIPN2646R2ZY
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2026
- Promised completion31 Dec 2031
- Revised completionNone
- Buildings2 building records
- Documents filed10 files
Current status
Figures as on 24 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing- A | NA | 17 | 14 | 52 | 0 | 52 |
| Wing- B | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
Wing- A3%
| Activity | Progress |
|---|---|
| Excavation | 30% |
| Basement (if any) | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing- B4%
| Activity | Progress |
|---|---|
| Excavation | 30% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | Not applicable |
Parking filed71
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANA Consortium Pvt Ltd |
| Engineer | Vireshwar Krishna Babar |
| Chartered Accountant | Phule Wagh & Associates LLP |
| Partner | Role in project |
|---|---|
| Savitri Construction Company | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed10
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| Order 50 Annex revised | 24 Aug 2026 |
| non fsi Affidavit wing B upload | 24 Aug 2026 |
| Layout plan 1 of 8 | 30 Jul 2026 |
| 02 of 8 | 28 Feb 2026 |
| 03 of 8 | 28 Feb 2026 |
| 04 of 8 | 28 Feb 2026 |
| 05 of 8 | 28 Feb 2026 |
| 06 of 8 | 28 Feb 2026 |
| 07 of 8 | 28 Feb 2026 |
| 08 of 8 | 28 Feb 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,674 Pune projects on ReraGenie, from their own filings.
Keep ULTIMATE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Balewadi13,674 in Pune
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: Chintamani Mahadeo Nimhan
Chintamani Mahadeo Nimhan has 1 registration on MahaRERA, including ULTIMATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ULTIMATE is delayed beyond 31 Dec 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ULTIMATE?
The registered promoter entity is Chintamani Mahadeo Nimhan, a proprietor as per the filing. Its GSTIN 27AAIPN2646R2ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ULTIMATE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ULTIMATE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ULTIMATE?
The professionals named in the filing: Architect: ANA Consortium Pvt Ltd; Engineer: Vireshwar Krishna Babar; Chartered Accountant: Phule Wagh & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ULTIMATE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback