Completed No litigation declared Residential / Group Housing project

UJVAL

By PARANJAPE SCHEMES (CONSTRUCTION) LTD

RG-MH-08887 · RERA P51800000657 · Last updated on MahaRERA portal: 11 Oct 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 33 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2022Possession promisedregistration recorded completed
14 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
1Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

UJVAL is a Residential / Group Housing project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000657 on 19 Jul 2017. The registration is recorded completed; possession was promised by 30 Sep 2022. The completion date has moved by 33 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameUJVAL
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000657
  • ReraGenie IDRG-MH-08887

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LTD
  • Entity typeCompany
  • ChairpersonSHRIKANT PURUSHOTTAM PARANJAPE
  • Managing DirectorSHASHANK PURUSHOTTAM PARANJAPE
  • Other registrations28 more →
  • Completed15 of 29
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toSep 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Jul 2017
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA100000
BUILDING BNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

BUILDING A87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING B86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities16

As on 11 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Fitness CentreYes0%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22
BuildingClosed/CoveredTotal
BUILDING A1111
BUILDING B1111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,488 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4014.36
Proposed, not sanctioned2,776 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMARIGOLD PREMISES, BEHIND GOLD ADLABS, PUNE - 411006

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTOSH S PENDSE
EngineerJ + W Consultants
PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800003622Dec 2019 → Dec 2020

Reason as filed by the promoterThe Promoter is applying for extension because he is in the process of procuring TDR / FSI.

EXT51800010266Dec 2019 → Mar 2022

Reason as filed by the promoterPromoter has duly obtained project registration extension u/s 6 of RERA up to 30/12/2020 and further MahaRERA by virtue of MahaRERA Order No 14 /2020 dated 18/05/2020 has extended project registration automatically up to 30/06/2021. Furthermore due to present strict restrictions by Government authorities because of second wave of covid-19 and also due to migration of labour, the pace of construction activities at real estate project sites has disrupted considerably.

Litigation declared3

CaseCourtStatus
561/2015/2015City Civil DindoshiPending Notice of motion taken out by Paranjape Schemes for taking written Statement on record The
2674/2014/2014City Civil DindoshiPending Notice of motion taken out by Sandeep Desai for taking written Statement on record was argue
1702/2017/2017Civil Court DindoshiMediation between parties failed Notice of motion taken out Nikhil kakirde Matter is kept for servi

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600859Amarjeet Vilas DeshmukhPARANJAPE SCHEMES (CONSTRUCTION) LTD16/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Dec 2022

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Ujval-FY'22-23-uploaded110ct23.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Ujval-Inventory Report-Mar2023.pdf19 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ujval-FORM 5-FY 21-22.pdf23 Feb 2023
Disclosure of sold/ booked inventoryFile: Ujval-Disclosure of sold booked inventory.pdf15 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: UJVAL OC.pdf12 Dec 2022
Architect’s Certificate on Completion of Project (Form 4)File: Ujval Rera certificate final form 4.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory bldg wise Ujwal.pdf3 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Ujwal-min_compressed.pdf28 Oct 2021
Declaration about Commencement CertificateFile: Format D Circular32 Commencement Certificate-UJVAL.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ujval 2A Quality Assurance Certificate June 2021.pdf6 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Inventories 30June2021.pdf6 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19 RERA Ujwal compressed.pdf1 Apr 2021
Certificates of CA (Form 5)File: Ujval_Form 5_18-19.pdf7 Oct 2019
Certificates of CA (Form 5)File: Ujval.pdf6 Oct 2018
Proforma of Allotment letterFile: Proforma_Allotment Ltr and Agreement_Ujval.pdf15 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ujval.pdf14 Jul 2017
Building plan approvalFile: Ujval Sanction layout page 1.pdf13 Jul 2017
PAN CardFile: PAN and List of Directors.pdf13 Jul 2017
Building Plan Approval (IOD)File: Ujval Sanction layout page 1.pdf13 Jul 2017
Declaration in FORM BFile: Form B_Ujwal.pdf13 Jul 2017
Certificates of CA (Form 3)File: Form 3_Ujwal.pdf13 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer's certificate Ujval.pdf1 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate_Ujval_28-06-2017.pdf28 Jun 2017
Layout approvalFile: Ujval Sanction layout page 1.pdf27 Jun 2017
Copy of the legal title reportFile: Title Report Ujval project.pdf27 Jun 2017
Copy of Layout Approval (in case of layout)File: Ujval Sanction layout page 1.pdf27 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Ujval.pdf27 Jun 2017

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
127 UPPER EASTP51800000454Andheri, Mumbai Suburban-Jul 2017CompletedJun 2024Registered original: Dec 2019Jan 1970
PRATHAM RESIDENTIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103035-CompletedApr 2016Mar 2016
THE BUSINESS HUBSURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 41102986-CompletedJan 2016Nov 2015
MADHUKOSH - IIISNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune258-CompletedAug 2015Aug 2015
PRATHAM COMMERCIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103032-CompletedJun 2015Apr 2015
PUNARVASUPRABHAT ROAD ERANDWANE PUNE 41100410-CompletedDec 2014Late, Jun 2015
MADHUKOSH - IISNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune150-CompletedDec 2013Oct 2013
MADHUKOSH - ISNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune289-CompletedMar 2012Feb 2012

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 33 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UJVAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmUJVALCompleted 207Lapsed / revoked 126Other 193Dot size: filed unitsN

Filed coordinates, straight-line distance. 526 registered projects within 2 km.

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD

PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if UJVAL is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UJVAL?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UJVAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against UJVAL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for UJVAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UJVAL?

The professionals named in the filing: Architect: SANTOSH S PENDSE; Engineer: J + W Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UJVAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UJVAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UJVAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.