Home / Browse projects / Mumbai Suburban, Maharashtra / UDAY BUILDING

Registration lapsed No litigation declared Residential / Group Housing project

UDAY BUILDING

By VIKRAM DEVELOPERS PRIVATE LIMITED

RG-MH-08497 · RERA P51800007935 · Last updated on MahaRERA portal: 29 Jul 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
0 of 11Construction stages donefurthest along: Excavation, 80%
1Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

UDAY BUILDING is a Residential / Group Housing project by VIKRAM DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007935 on 18 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameUDAY BUILDING
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007935
  • ReraGenie IDRG-MH-08497

Builder

  • NameVIKRAM DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorARVIND VINAYAK VAKADKAR
  • DirectorVIKRAM ARVIND VAKADKAR

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
UDAY BUILDINGNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 80%.

UDAY BUILDING: 15% average across the applicable activities

ActivityProgress
Excavation80%
Basement (if any)40%
Podiums (if any)0%
Plinth40%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area882 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4405.73
Proposed, not sanctioned1,742 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKONARK DARSHAN, NEW SURVEY 1000 CTS NO 1195, ZAVER ROAD, MULUND WEST, MUMBAI 400080

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMESH DALVI
PartnerRole in project
VIKRAM DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005160Dec 2019 → Dec 2020

Reason as filed by the promoterGovernment policies and changes in Dc rules and Regulations and suddenly death of Land owner Shri NANDAN VISHWAS WAKATKAR. Has exprie on 26/05/2016 there fore heirs name has to be added in property card and document has to be done. there fore there was delay.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000408406UDAY HEIGHTS SOCIETY UDAY HEIGHTS SOCIETYVIKRAM DEVELOPERS PRIVATE LIMITED05/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Signed by architect).pdf29 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2018.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2019.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2020.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2021.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-12-2021.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-2022_compressed.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30-06-2022.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30-09-2022.pdf23 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-12-2022.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-18.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-19.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-20.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-21.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-12-21.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-22.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 30-06-22.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 30-09-22.pdf23 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-12-22.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5-Uday building as on 31-03-2019.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5-Uday building as on 31-03-2020.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-Uday building as on 31-03-2021.pdf23 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-Uday building as on 31-03-2022.pdf23 Mar 2023
Declaration about Commencement CertificateFile: Uday Building Dormat D.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Uday Building 2021-22.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Uday Building 2020-21.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Uday Building 2021-22.pdf18 Mar 2023
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 (6).pdf18 Mar 2023
Proforma of Agreement for saleFile: Part 1 - Uday Heights - Agreement For Sale.pdf21 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Ac Details.pdf21 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA FORM NO5.pdf27 Dec 2019
Annual Audit Report of Statutory CA (Form 5)File: Form 5 and Architect certificate Merge.pdf10 Oct 2019
Declaration in FORM BFile: new form b.pdf14 Aug 2017
Building plan approvalFile: INTIMATION OF DISAPPROVAL0001.pdf31 Jul 2017
Layout approvalFile: LAYOUT.pdf31 Jul 2017
PAN CardFile: PanCardVDPL.pdf31 Jul 2017
Copy of the legal title reportFile: title report land.pdf31 Jul 2017
Details of encumbrancesFile: declaration of legal encumbrance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf31 Jul 2017
Building Plan Approval (IOD)File: INTIMATION OF DISAPPROVAL0001.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: FORM A COMMENCEMENT.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERT FORM 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA certificate0001.pdf31 Jul 2017
Proforma of Allotment letterFile: agreement to sale.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UDAY BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmUDAY BUILDINGCompleted 100Lapsed / revoked 63Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 234 registered projects within 2 km.

Builder: VIKRAM DEVELOPERS PRIVATE LIMITED

VIKRAM DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including UDAY BUILDING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that UDAY BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if UDAY BUILDING is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UDAY BUILDING?

The registered promoter entity is VIKRAM DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UDAY BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against UDAY BUILDING?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for UDAY BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UDAY BUILDING?

The professionals named in the filing: Architect: RAMESH DALVI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UDAY BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UDAY BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UDAY BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.