Home / Browse projects / Thane, Maharashtra / Tycoons Valley Tower A
Tycoons Valley Tower A
RG-MH-12471 · RERA P51700009259 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Litigation declared, 1 case
- 9 complaints at MahaRERA
- Completion date moved by 66 months
- 5 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 4 earlier projects delivered on promise
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Tycoons Valley Tower A is a Others project by M/s. Milestone Space in Thane, Maharashtra, registered with MahaRERA as P51700009259 on 22 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 66 months from the original filing. 102 of the 124 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 9 complaints are on record with the regulator.
At a glance
Project
- NameTycoons Valley Tower A
- TypeOthers
- Location
- Barave
- Khadakpada
- Kalyan
- Thane
- 421301
- Pincode421301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700009259
- ReraGenie IDRG-MH-12471
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2020)
- Buildings1 building record
- Documents filed252 files
Current status
Figures as on 3 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building 1 Wing A Emerald | NA | 23 | 19 | 97 | 27 | 124 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
Building 1 Wing A Emerald: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building 1 Wing A Emerald | NA | Rs 31.84 cr | Rs 31.84 cr |
| - | NA | Rs 1.20 cr | Rs 1.07 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Aniruddha S Dastane S Dastane |
| Engineer | Epicons Consultants PVT LTD |
| Chartered Accountant | Malvika Mitra |
| Chartered Accountant | Tausif Shaikh |
| Chartered Accountant | Venkat Raghunath Chari |
| Chartered Accountant | AMRITA JAGNANNI |
| Partner | Role in project |
|---|---|
| M/s. Milestone Space | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDate:04/12/2019 To, The Maharashtra Real Estate Regulatory Authority, Bandra, Mumbai. Sub: Seeking extension of 12 months in Tycoons Solitaire Phase II Project Sir, The Promoter states that the Project is completing with 20 floors of which the Promoter completed the work of RCC upto 8th floor. The Promoter further states that delay caused due to pending litigation and further issue in respect of TDR. The Promoter states that considering the present period and the fact that the promoter has already completed 8th floors and there is no financial strain on Promoter, the Promoter will be completin
Reason as filed by the promoterDate: 17-05-2022 To, The Maharashtra Real Estate Regulatory Authority, Bandra, Mumbai. Sub: Seeking extension of 09 months in the project “Tycoons Valley Tower A”. Sir, The Promoters inform that the subject project is completed with RCC work up to 17 slabs, including terrace 4 slabs are in process; simultaneously internal finishing work is also going on. The Promoters state that delay caused due to the outbreak of Covid-19 pandemic followed by procedural norms to get the revised permission in revised format of UDCPR by Kalyan Dombivali Municipal Corporation. The Promoters further states that t
Reason as filed by the promoterRequest you to schedule the hearing in this matter under order no 40.
Reason as filed by the promoterWe as Promoter of this project namely ‘Tycoons Valley Tower A’ are putting total efforts till this date to complete the project but the delay is caused due to pending litigation, issue in respect of TDR and handover of constructed premises to the Kalyan Dombivli Municipal Corporation due to the reservation on the said plot. The promoter states that the main reason for delay in completion of the project is because the funding which was agreed by HDFC was not made by HDFC as promised. HDFC failed and neglected to disburse the fund as sanctioned to the promoter and therefore promoters were cash c
Reason as filed by the promoterDue to financial constraints, we are unable to complete the project within the scheduled timeframe. All updates up to this date have been communicated promptly to all registered customers of the project, with whom we hold weekly meetings to discuss the current status of the project work. Currently, the RCC work, internal and external plastering, internal painting, waterproofing, and other tasks have been completed, while electrical fittings (switch plates), plumbing, external drainage, door shutters and hardware, as well as flooring and tiling for a few units are still in progress.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 281/2010 | Civil Judge | Ongoing |
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001765 | sumandas savlaram salve | shrikant shitole | 07/11/2017 |
| CC006000000194251 | Pooja Dudani | M/S. Milestone Space | 11/10/2020 |
| CC006000000194601 | Nilesh Pawar | Milestone Space | 27/01/2021 |
| CC006000000196975 | Hamida Shaikh | M/s. Milestone Space | 12/05/2021 |
| CC006000000197223 | Dinesh Kulkarni | M/S Milestone space | 10/06/2021 |
| CC006000000429395 | murukraj nair | m/s milestone space | 23/02/2024 |
| CC12400929 | Nitin Purushottam Dhumal | M/s. Milestone Space | 28/11/2024 |
| CC12500871 | Vishal Shinde | M/s. Milestone Space | 13/03/2025 |
| CC12502703 | Vishal Sanjay Jadhav | M/s. Milestone Space | 02/08/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Feb 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed252
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 252 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 April to June 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 (3).pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 (1).pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 (1).pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 (11).pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Form 1 April to June 2025.pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Form 1 April to June 2025.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: FORM 2 Emerlad April to June 2025-2026.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: FORM 2 Emerlad April to June 2025-2026.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf | 25 May 2026 |
| Withdrawal Update Form 3File: FORM 3 APRIL TO JUNE 25 EMERALD pdf.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: FORM 3 APRIL TO JUNE 25 EMERALD pdf.pdf | 25 May 2026 |
| Form 5 (FY 2024-2025)File: Form 5 2024-2025.pdf | 1 Jul 2025 |
| Form 1File: Form 1 Jan2025 - March2025.pdf | 30 Jun 2025 |
| Form 2File: Form 2 Engineers Certificate - Jan 2025 - March 2025.pdf | 30 Jun 2025 |
| Form 3File: Form 3 Jan 2025-March 2025_compressed.pdf | 30 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories.pdf | 30 Jun 2025 |
| Form 2A (FY 2017-2018)File: Form 2A Quality Assurance Certificate 2017-2018.pdf | 30 Jun 2025 |
| Form 2A (FY 2022-2023)File: Form 2A Quality Assurance Certificate 2022-2023.pdf | 30 Jun 2025 |
| Form 2A (FY 2018-2019)File: Form 2A Quality Assurance Certificate 2018-2019.pdf | 30 Jun 2025 |
| Form 2A (FY 2019-2020)File: Form 2A Quality Assurance Certificate 2019-2020.pdf | 30 Jun 2025 |
| Form 2A (FY 2020-2021)File: Form 2A Quality Assurance Certificate 2020-2021.pdf | 30 Jun 2025 |
| Form 2A (FY 2021-2022)File: Form 2A Quality Assurance Certificate 2021-2022.pdf | 30 Jun 2025 |
| Form 2A (FY 2023-2024)File: Form 2A Quality Assurance Certificate 2023-2024.pdf | 30 Jun 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Quality Assurance Certificate 2024-2025.pdf | 30 Jun 2025 |
| Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate 2025-2026.pdf | 30 Jun 2025 |
| Form 5 (FY 2017-2018)File: FORM-5-dated-16-12-2019 2017-2018.pdf | 29 Jun 2025 |
| Form 5 (FY 2018-2019)File: FORM-5-dated-16-12-2019 2018-2019.pdf | 29 Jun 2025 |
| Form 5 (FY 2019-2020)File: Form 5 2019-2020.pdf | 29 Jun 2025 |
| Form 5 (FY 2020-2021)File: Form 5 2020-2021.PDF | 29 Jun 2025 |
| Form 5 (FY 2021-2022)File: Form 5 2021-2022.PDF | 29 Jun 2025 |
| Form 5 (FY 2022-2023)File: Form 5 2022-2023.pdf | 29 Jun 2025 |
| Form 1File: 28-07-2017 Form 1 Architect Certificate.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 23-07-2017.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 29-7-2017.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: 28-07-2017 Form 1 Architect Certificate.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 23-07-2017.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 29-7-2017.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: 31-03-2018 Form 1 Architect Certificate_compressed.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 2017-2018.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 2017-2018.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: 2018 Form 1 Architect Certificate_compressed.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 2018.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 2018.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: 2018 Form 1 Architect Certificate_compressed.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 2018.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 2018.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: 2018 Form 1 Architect Certificate_compressed.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 2018.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 2018.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: Form 1 Architect Certificate 2019.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dated 2019.pdf | 28 Jun 2025 |
| Form 3File: Form 3 CA Certificate dated 2019.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory Emerald_compressed.pdf | 28 Jun 2025 |
| Form 1File: Form 1_Jan 2024-March 2024.pdf | 28 Jun 2025 |
| Form 2File: FORM-2_dated 10-01-25_( Jan 24 to march24).pdf | 28 Jun 2025 |
| Form 3File: Form 3_January 2024 to March 2024_Emerald.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of inventories.pdf | 28 Jun 2025 |
| Form 1File: Form 1_April 2024-June 2024.pdf | 28 Jun 2025 |
| Form 2File: FORM-2_dated 10-01-25( Apr 24 to June 24).pdf | 28 Jun 2025 |
| Form 3File: Form 3_April 2024 to June 2024_Emerald.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of inventories.pdf | 28 Jun 2025 |
| Form 1File: Form 1_July 2024-Sep 2024.pdf | 28 Jun 2025 |
| Form 2File: FORM-2_dated 10-01-25(July 24 to sept 24).pdf | 28 Jun 2025 |
| Form 3File: Form 3_July 2024 to Sept 2024_Emerald.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of inventories.pdf | 28 Jun 2025 |
| Form 1File: Form-1 Architects Certificate-16-12-2024.pdf | 28 Jun 2025 |
| Form 2File: FORM-2_dated 10-01-25(Oct 24 to Dec 24)_compressed.pdf | 28 Jun 2025 |
| Form 3File: FORM-3 dated 28-12-2024.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of inventories.pdf | 28 Jun 2025 |
| Form 1File: Form 1_Oct 2023-Dec 2023.pdf | 28 Jun 2025 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Tycoons Solitaire Phase-I | Kalyan-West | 103 | Completed | Jul 2017 | Jul 2017 |
| Spring Avenue | Kalyan - west | 14 | Completed | Sep 2011 | Sep 2011 |
| Tycoons Residency | Kalyan - west | 48 | Completed | Jul 2011 | Jul 2011 |
| Tycoons Residency | Kalyan - west | 112 | Completed | Oct 2007 | Oct 2007 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 252 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Tycoons Valley Tower A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khadakpada7,600+ in Thane
Filed coordinates, straight-line distance. 294 registered projects within 2 km.
PODDAR RIVIERA PHASE - I
Poddar Housing and Development Limited
Sinhagad by Bhagwati Haware - Wing - B
Bhagwati Haware Properties Supertech
Pratapgad by Bhagwati Haware - Wing - C
Bhagwati Haware Properties Supertech
Rajgad by Bhagwati Haware - Wing - D
Bhagwati Haware Properties Supertech
PODDAR RIVIERA PHASE - III
Poddar Housing and Development Limited
THARWANI PARKGLEN PHASE I
THARWANI REALTORS
See every Thane project, with the district possession charts
Builder: M/s. Milestone Space
M/s. Milestone Space has 2 registrations on MahaRERA, including Tycoons Valley Tower A and Tycoons Valley Tower B. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Tycoons Valley Tower A shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Tycoons Valley Tower A is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Tycoons Valley Tower A?
The registered promoter entity is M/s. Milestone Space, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Tycoons Valley Tower A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Tycoons Valley Tower A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Tycoons Valley Tower A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Tycoons Valley Tower A?
The professionals named in the filing: Architect: Aniruddha S Dastane S Dastane; Engineer: Epicons Consultants PVT LTD; Chartered Accountant: Malvika Mitra; Chartered Accountant: Tausif Shaikh; Chartered Accountant: Venkat Raghunath Chari; Chartered Accountant: AMRITA JAGNANNI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Tycoons Valley Tower A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback